ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Construction Projects

Potomac River Tunnel: DC Water's $819M Bore and Two TBMs

Lisa Chen·August 27, 2026·Updated October 18, 2026·12 min read

Share this with your estimator.

Tunnel boring works. Representative image — not the Potomac River Tunnel.
Tunnel boring works. Representative image — not the Potomac River Tunnel. Photo: Ibbre Sharif / Pexels

Project Facts

constructionUnder Construction
Project
Potomac River Tunnel (DC Water Clean Rivers Project)
Location
Washington, D.C. — Georgetown waterfront to Hains Point and Joint Base Anacostia-Bolling, via West Potomac Park
Project Type
Deep combined sewer overflow (CSO) storage and conveyance tunnel
Estimated Cost
$819 million design-build contract (DC Water, Oct 6 2023) — the largest DC Water has awarded; part of the $2.99 billion Clean Rivers Project
Size / Scope
5.5 miles of tunnel at 18 ft internal diameter, about 80 to 100 ft deep, five large drop shafts
Owner / Developer
DC Water (District of Columbia Water and Sewer Authority)
General Contractor / CM
CBNA (Civil and Building in North America, a member of Bouygues Construction) and Halmar International — design-build joint venture
Architect
Not publicly announced
Engineer of Record
Hatch (design management and detailed design of underground works); COWI (tunnel and adit design, geotechnical)
Construction Start
Contract approved October 2023; mobilization at West Potomac Park in 2024; TBM Mary launched April 10, 2026
Expected Completion
2030 (early 2030 per the 2005 consent decree with EPA, DOJ and the District)
Published Aug 28, 2026Last updated Oct 18, 202611 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

Two tunnel boring machines are working the same alignment under Washington, D.C., and they were specified for different ground. One is driving north toward Georgetown and will spend most of its run in rock. The other is being readied to push south through mixed ground and then soft soil toward Joint Base Anacostia-Bolling. Same owner, same contract, same 18-foot finished tunnel, two different machines, because the ground under the District changes character along the route.

That is the engineering story on the Potomac River Tunnel. It is one of the few TBM drives actually underway in the US right now; our verified count of active US tunnel boring machines found five machines on three projects as of October 2026, and this job accounts for two of them.

The Job

DC Water is building a 5.5-mile tunnel with an 18-foot internal diameter, according to its October 6, 2023 contract award announcement. The alignment runs beneath the Georgetown waterfront, along the edge of the National Mall and East Potomac Park, past Hains Point, and connects by gravity to the existing Anacostia River Tunnel, which carries flow on to the Blue Plains treatment plant.

The word doing the work in that description is gravity. This is not a pumped system. CBNA's Nicolas Duchemin told ASCE's Civil Engineering magazine in November 2023 that the tunnel will slope downward at 0.1 percent, with average depths ranging from 80 to 100 feet. On a 5.5-mile run, that slope sets how deep the Georgetown end sits and how tall every shaft has to be. Anyone sizing gravity sewer runs at any scale will recognize the tradeoff; the pipe slope calculator runs the same arithmetic on a job you can build in a week.

The performance target is specific. DC Water's project page says eight CSO outfalls discharge to the Potomac, and in a year of average rainfall about 74 overflow events send roughly 654 million gallons of combined sewage and stormwater into the river. When the tunnel is operating, DC Water expects that to drop to about four events a year and overflow volume to fall 93 percent.

Why the Geology Flips

The alignment starts in rock and ends in soft ground. Duchemin's description in the same ASCE article is the clearest public account of what the contractor is dealing with: the northern section is mostly hard rock, predominantly schist. The southern tunnel starts with low rock cover, transitions quickly into mixed ground with alluvium at the crown and rock at the invert, and the final 2.5 miles are in varying soft ground, mostly dense silty and clayey sands.

A tunnel that crosses that kind of boundary crosses a machine-selection boundary with it. Hard-rock tunneling is a cutting and abrasion problem: disc cutters, cutterhead wear, muck handling, and the chance that a fractured zone delivers water faster than it can be grouted off. Soft-ground tunneling near a river is a face-stability problem: the machine has to hold pressure at the face against groundwater continuously, because saturated sand does not stand up on its own. Mixed face, with rock at the bottom of the cutterhead and soil at the top, is harder than either, because the machine has to do both jobs at once and the softer material tends to run ahead of the harder.

The contractor's answer, per ASCE, was two hybrid machines. The northbound TBM is a hybrid that can run in open mode and slurry mode, because it has to get through a former riverbed (a paleochannel) as well as rock. The southbound TBM is a variable density machine, a hybrid of earth pressure balance and slurry operation, built to start in rock and finish in soft ground. ASCE reported the planned drive lengths as 12,800 feet north and 16,600 feet south.

Shafts and the Connection Nobody Designed For

The job is more than two drives. ASCE's 2023 account lists five large drop shafts: two 50-foot-diameter shafts used to launch the TBMs, two shafts of 45 and 42 feet in diameter at large CSO outfalls, and a 45-foot shaft near Georgetown University to retrieve the northbound machine.

The southbound machine has no retrieval shaft. It ends at an existing shaft on the Anacostia River Tunnel that was never designed to receive a TBM. Duchemin told ASCE that the existing shaft is a fully reinforced structure with no soft eye. The plan is to jet grout a concrete plug beside the shaft, drive the TBM into the plug, strip everything but the shield from the inside, mine the rest of the plug with sequential excavation, then cut into the existing shaft and rebuild a collar to make the connection. For specialty contractors, that one connection is a jet grouting, SEM and structural concrete package in its own right.

Two other details from that article matter to anyone pricing logistics. Muck leaves by truck, not barge, because the Potomac is too shallow without extensive dredging. And major trucking is kept out of overnight and peak traffic hours. The alignment also passes in front of the Kennedy Center, the Watergate, the Georgetown waterfront and Georgetown University, which means a full instrumentation and monitoring program along the route and at each shaft. Before the main contract, DC Water had already spent $13.9 million installing temporary and permanent power at several project sites, ASCE reported.

Mary: North to Georgetown

DC Water announced on April 10, 2026 that TBM Mary had launched from a 100-foot-deep overflow mining shaft at West Potomac Park, after crews excavated a starter tunnel and lowered and assembled her front section inside it. DC Water describes Mary as a 21-foot-diameter, 1,200-ton machine. She is boring about 2.4 miles north to Georgetown University.

Mary did not start at full production. Her trailing gantries were lowered one at a time, each about 30 tons, and connected as she advanced. DC Water said on August 27, 2026 that the final gantry was in place and Mary now stretches 706 feet end to end. The same release laid out the next step: Mary would excavate about 350 feet farther, then stop in place for a changeover of more than two months as she moves from softer soil near the river into hard bedrock for the rest of her drive. That changeover is the kind of schedule item that rarely shows up in general news coverage and matters a great deal to anyone tracking production on a hybrid machine.

At the north end, DC Water said in a July 6, 2026 notice that controlled blasting for the deep shaft near the Canal Road NW entrance to Georgetown University would start the week of July 13, 2026 and continue through June 2027, about every two weeks after test blasts. Police and flaggers stop traffic on Canal Road NW for about five minutes per blast, and DC Water is coordinating with DC Fire and EMS, the Metropolitan Police Department and the National Park Service. Blasting in a dense urban block means pre-construction condition surveys of neighboring buildings, vibration monitoring and a public notification program, and it is the phase that draws neighbor attention, since the mining itself is invisible from the street.

Emily: South Into Soft Ground

TBM Emily arrived at the West Potomac Park site early on May 27, 2026, according to DC Water. She was built and factory tested in Germany, disassembled, shipped across the Atlantic, and trucked from the Port of Baltimore for reassembly. DC Water describes her as nearly 21 feet wide and able to adjust her operation to hold the surrounding earth in place through softer soils beneath the river.

DC Water christened Emily on September 19, 2026, at a community day that took visitors 105 feet underground into the tunnel. At that point the authority said crews would soon lower Emily underground, and that she will travel about 3.1 miles south to Joint Base Anacostia-Bolling, where the Potomac River Tunnel connects to the existing Anacostia River Tunnel.

Reassembly is its own schedule item. A machine of this size arrives as a shield, cutterhead, drive unit, segment erector, slurry or screw circuit, and hundreds of feet of backup gantries. All of it has to go down a shaft that is shared with Mary's ongoing muck haul and segment delivery. Tunneling under an active military installation also adds an access and coordination layer that most utility jobs never see.

The Contract and the Team

DC Water's board approved the $819 million design-build contract in the week of October 6, 2023, the largest contract the authority has ever awarded. The winning team is a joint venture of CBNA (Civil and Building in North America, which ASCE identifies as a member of Bouygues Construction) and Halmar International. DC Water said the JV was selected on its lowest price proposal and second-highest technical score, which it judged best value. That is a useful data point for anyone reading best-value scoring on public work: neither price nor technical rank decided it alone.

On design, Hatch's February 2024 announcement says it handles overall design management and detailed design of the underground works, including support of excavation and concrete structures. COWI leads the design of the tunnel and adits and provides geotechnical support for the whole project.

DC Water says design work began in 2019 and mobilization at West Potomac Park began in 2024. Its current materials say the tunnel will be finished and operating in 2030.

A Consent Decree Is a Bid Pipeline

The 2030 date comes from the consent decree DC Water signed in 2005 with the US Environmental Protection Agency, the Department of Justice and the District of Columbia, according to the 2023 award announcement. The Potomac River Tunnel is part of the Clean Rivers Project, which DC Water describes as a $2.99 billion program covering the Anacostia and Potomac rivers and Rock Creek.

It is not the only decree tunnel underway in the District. DC Water broke ground on the Piney Branch Tunnel on July 9, 2026: about a half-mile, 22-foot-wide tunnel that will hold at least 4.2 million gallons and is scheduled to be finished by the end of 2029. DC Water describes Piney Branch and the Potomac River Tunnel together as the work that completes the Clean Rivers Project.

This is the part of the market contractors tend to underweight. Decree-driven work does not follow interest rates or private development sentiment. A court-entered schedule sets the date, the utility has to hit it, and the capital plan is effectively non-discretionary for the life of the decree. Many large US cities with combined sewer systems run similar long-term control programs, and for heavy civil and utility contractors that work is about as predictable as backlog gets.

The follow-on tiers are where most firms will actually take part: shaft and drop structure work, adits and near-surface diversion structures, precast segment supply, grouting, instrumentation and settlement monitoring, dewatering, odor control, and mechanical and electrical fit-out. Smaller utility contractors can see what similar work costs at the pipe scale in our sewer line replacement cost per foot breakdown. Federal packages surface on the public bid board, and segment and shaft concrete tracks with concrete input pricing over a multi-year program. For why US tunnel work costs what it does, see US tunnel construction costs.

What Happens Next

Watch three things. Mary's changeover from soft ground to rock and her advance rate afterward, which will tell you whether the northern drive holds its share of the schedule. Emily's lowering, reassembly and launch from West Potomac Park, which is the near-term critical path for the southern 3.1 miles. And the Georgetown shaft, where blasting is scheduled to run through June 2027 and where a slip would show up first.

For more coverage of utility and municipal capital programs, see Buildermuse's public works section.

FAQ

How much does the Potomac River Tunnel cost?

The design-build contract is $819 million, approved by DC Water's board in October 2023 and the largest contract DC Water has awarded. It is one piece of the $2.99 billion Clean Rivers Project.

Who is building the Potomac River Tunnel?

A design-build joint venture of CBNA (Civil and Building in North America) and Halmar International. Hatch handles design management and detailed design of underground works, and COWI designs the tunnel and adits and provides geotechnical engineering.

How long and how deep is the tunnel?

It is 5.5 miles long with an 18-foot internal diameter. Average depths range from about 80 to 100 feet, and Mary launched from a 100-foot-deep shaft at West Potomac Park.

Why does the project use two different TBMs?

The north end is mostly hard rock (schist), while the south end moves through mixed ground into dense silty and clayey sands. The northbound machine is an open-mode and slurry hybrid; the southbound machine is a variable density TBM that combines earth pressure balance and slurry operation.

When will the Potomac River Tunnel be finished?

DC Water says the tunnel will be finished and begin operating in 2030. The 2005 consent decree with EPA, the Justice Department and the District sets the deadline.

What will the tunnel do for the river?

DC Water expects it to cut combined sewer overflows to the Potomac by 93 percent by volume and reduce overflow events from about 74 to about four in an average rainfall year.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free