The hardest part of the Hampton Roads Bridge-Tunnel Expansion has been finished for more than a year, and most drivers on I-64 have no idea. Both tubes were fully excavated when the tunnel boring machine broke through on September 24, 2025. The machine was then taken apart on the South Island and shipped back to its German manufacturer. And the project still will not reach substantial completion until 2027.
That gap between the last cut of soil and the first car through the tunnel is the most misunderstood thing about tunnel construction, and the HRBT is a good live demonstration of it.
What the $3.9 Billion Buys
VDOT describes the HRBT Expansion as the largest highway construction project in Virginia's history at $3.9 billion. The project improves the I-64 corridor from Mallory Street in Hampton to Patrol Road in Norfolk. According to VDOT's project page, the Hampton Roads Transportation Accountability Commission (HRTAC) is the primary funding agent, financed with regional sales and gas tax collections, with additional funding of $200 million from the Commonwealth's SMART SCALE program and $108 million from VDOT. The project homepage says the partnership is 92% paid for by HRTAC with regionally controlled funds.
The scope is much broader than the tunnel:
- Twin two-lane bored tunnels under the harbor, bringing total capacity across the water to eight lanes
- A third lane and a drivable shoulder added to I-64 in each direction
- About 14,000 feet of new marine bridges and replacement of more than two dozen existing bridge structures, per ENR's 2022 description of the scope
VDOT owns the project. Hampton Roads Connector Partners (HRCP) is the design-build team, with Dragados USA as lead contractor and HDR and Mott MacDonald as lead designers. Herrenknecht's project reference lists the joint venture partners as Dragados USA, VINCI Construction Grands Projets, Flatiron Constructors and Dodin Campenon Bernard. Construction Dive reported that work started in 2020 and was originally scheduled to finish by November 2025.
With that much marine bridge and trestle work, schedule and material exposure on this job never sat entirely in the tunnel. Contractors pricing similar marine and bridge packages should be tracking structural steel pricing alongside the civil quantities.
Bored Tunnel, Not Immersed Tube
The existing HRBT tubes are immersed-tube tunnels: precast sections floated into position, sunk into a dredged trench, joined and backfilled. That is the traditional method for a harbor crossing.
VDOT went with bored tunnels instead. VDOT's tunnel page says the new tubes sit approximately 50 feet below the existing tunnels and that, unlike the existing immersed-tube tunnels, the bored approach eliminated disruptions to the busy federal channel. Hampton Roads is a major port and naval center, and an immersed tube would have required dredging a trench across that channel. When a bored tunnel looks expensive next to an immersed-tube alternative, part of what the owner is buying is uninterrupted channel operations.
One Machine, Two Drives
The machine, named Mary after a 2020 student naming contest, was built by Herrenknecht in Germany and arrived in the United States in December 2021, according to VDOT. Herrenknecht's reference page lists it as a Variable Density TBM with a shield diameter of 13,990 millimeters (just under 46 feet), cutterhead power of 5,600 kW and torque of 36,947 kNm, built to drive 2 x 2,440 meters of road tunnel through heterogeneous ground. VDOT puts the machine's weight at 4,700 tons.
The "variable density" designation matters more than the size. A conventional slurry machine supports the face with a bentonite suspension; an earth pressure balance machine supports it with conditioned spoil. A variable-density machine can shift between modes as ground conditions change, which suits mixed marine sediments under significant water pressure. Mary installed precast tunnel rings as she excavated.
| Milestone | Date | Source |
|---|---|---|
| Launch from South Island (Norfolk side) | April 2023 | VDOT |
| First breakthrough, North Island | April 17, 2024 | VDOT, Herrenknecht |
| Turnaround in the shaft, second drive starts | November 2024 | Herrenknecht |
| Final breakthrough, South Island | September 24, 2025 | VDOT |
| Final piece of the shield extracted | January 14, 2026 | WAVY via VDOT newsroom |
One machine bored both tubes. Herrenknecht describes the crew turning the shield, cutterhead and gantries 180 degrees in the shaft to drive the parallel tunnel; VDOT says the turnaround took six months.
Run the arithmetic on the first drive and you get an estimator's lesson. About 2,440 meters mined between an April 2023 launch and an April 17, 2024 breakthrough works out to an average on the order of 6 to 7 meters (roughly 20 to 22 feet) per calendar day. That average includes launch, learning curve, interventions, maintenance and segment logistics, which is exactly the point: price a tunnel drive off a calendar-day average from comparable work, not a peak shift rate. The same lesson applies to the other active US TBM drives we track.
Outfitting: Why "Done Boring" Is Not "Done"
An excavated, lined tunnel is a concrete tube. It is not a road.
Virginia Business reported on September 29, 2026 that crews have begun pouring ballast in sections to form the roadbed inside the tunnels, with paving and striping expected later in the fall. Lighting, message signs, fire suppression and emergency-exit corridors are being installed. On the North Island, the operations office that will house a 24-hour control room is under construction; on the South Island, the ventilation building interior is being completed and the foundation for the South Trestle's connection to the new eastbound tunnels is finished. VDOT has confirmed the new tubes will include an egress corridor, a protected pathway separated from the roadway by sliding doors, providing fresh air for evacuation to the North or South Island.
The trade mix inverts at this stage. Heavy civil winds down; electrical, mechanical, fire protection, controls and finish contractors take over, working inside a confined bore with limited access points. Commissioning and integrated systems testing follow, and on a highway tunnel that testing is not a formality: fire-life-safety systems have to work before an owner will accept traffic.
This is why a tunnel can be fully mined in September 2025 and not open until 2027. It is also why the remaining subcontract opportunity on jobs like this sits in the electrical, mechanical and systems tiers. Watch the public bid board for those packages rather than civil work that closed years ago.
The 2022 Reset and the $90 Million Incentive
The commercial story explains the dates. ENR reported that on March 28, 2022, VDOT announced it had revised its comprehensive agreement with HRCP after "unforeseen cost and schedule impacts," pushing projected substantial completion back 18 months to February 2027 while preserving the original budget. VDOT said the reset would "provide construction schedule certainty, enhance contractor schedule accountability, and reduce the potential of litigation."
Per ENR and WTKR, the revised agreement:
- Set substantial completion for February 26, 2027 and final completion for August 27, 2027
- Added a $90 million incentive if HRCP reached substantial completion no later than September 25, 2026
- Made the team eligible for additional compensation for increased costs of materials tied to tunnel construction, such as asphalt, fuel and steel, and marine-related commodities including precast tunnel segments, concrete cylinder piles and bulb tee girders
- Gave VDOT a credit if the final cost came in below the bid cost
The September 25, 2026 incentive date has now passed with tunnel outfitting still underway. As of Virginia Business's September 29, 2026 report, substantial completion is on track for 2027, and VDOT project director Ryan Banas said: "Right now, we're confident about 2027, but as we get closer to 2027, we can provide a closer, more accurate date."
There is a broader point about design-build risk allocation. When a contractor demonstrates impacts it did not price, an owner's realistic options are litigation, a negotiated reset, or both. Virginia chose a reset with a bounded incentive and a material escalation mechanism instead of a years-long claim. That structure is worth studying if you bid public work at this scale. Virginia's overall contract volume is visible in Buildermuse's state construction dashboards.
A small disambiguation for anyone searching: DC Water is running a separate tunnel boring machine also named Mary on its Potomac River Tunnel. Two different machines, two different owners.
What Opens When
Lane openings are now a recurring event rather than a single milestone:
- November 2025: the South Trestle superstructure between the HRBT and the Norfolk shoreline opened, per the VDOT project site.
- July 24, 2026: the Mallory Street Bridge in Hampton opened with a pedestrian lane and bike lanes (Virginia Business).
- July 27, 2026: the first westbound shift onto newly widened I-64 in Norfolk moved traffic from Oates Creek to Bay Avenue (VDOT newsroom, WAVY).
- Later in 2026: westbound traffic is to shift onto the North Trestle, after which parts of the existing bridge will be demolished so the new trestle can be widened to full width (Virginia Business).
When the project is complete, the two new tubes will carry the four eastbound lanes and the existing tunnels will carry westbound traffic. VDOT also reports that about 100,000 tons of demolished bridge concrete is going to artificial reef sites in the Chesapeake Bay.
For contractors, the transferable takeaway is the trade sequencing: on any tunnel, the civil scope ends long before the job does, and the final year or more belongs to systems. For owners, it is a schedule communication problem: commuters who watched a breakthrough in September 2025 have spent a year wondering why the tunnel is still closed. For a look at why US tunnels cost what they do, see why US tunnel construction costs so much.
More coverage of federally and state-funded heavy civil work is in Buildermuse's infrastructure section.
Frequently Asked Questions
How much does the HRBT Expansion cost?
VDOT puts the project at $3.9 billion, the largest highway project in Virginia history. HRTAC is the primary funding agent using regional sales and gas tax revenue, with $200 million from SMART SCALE and $108 million from VDOT.
When will the new HRBT tunnels open?
The revised 2022 agreement set substantial completion for February 26, 2027 and final completion for August 27, 2027. As of late September 2026, VDOT said substantial completion, when the new lanes and tunnels are expected to open, is on track for 2027 and that a more precise date will come closer to it.
Who is building the HRBT Expansion?
Hampton Roads Connector Partners, a design-build joint venture led by Dragados USA with VINCI Construction Grands Projets, Flatiron Constructors and Dodin Campenon Bernard. HDR and Mott MacDonald are lead designers.
How big was the tunnel boring machine?
Herrenknecht lists Mary as a Variable Density TBM with a 13,990 mm (about 46 ft) shield, 5,600 kW of cutterhead power and 36,947 kNm of torque. VDOT says it weighed 4,700 tons. It bored both tubes, about 2,440 meters each.
What was the $90 million incentive?
The 2022 revised agreement offered HRCP up to $90 million for reaching substantial completion by September 25, 2026. That date has passed with outfitting still underway, and the current target is substantial completion in 2027.



