ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Construction Projects

Hudson Tunnel Project: $16B Cost, Contractor Lineup, and TBM Timeline

Lisa Chen·August 23, 2026·Updated October 29, 2026·13 min read

Share this with your estimator.

Tunnel construction underground. Representative image — not the Hudson Tunnel Project.
Tunnel construction underground. Representative image — not the Hudson Tunnel Project. Photo: Anil Sharma / Pexels

Project Facts

constructionUnder Construction
Project
Hudson Tunnel Project (Gateway Program)
Location
North Bergen, NJ to Manhattan, NY — under the Hudson River
Project Type
Twin-tube passenger rail tunnel plus rehabilitation of the 1910 North River Tunnel (Northeast Corridor)
Estimated Cost
$16 billion total program cost (Gateway Development Commission); $6.88 billion FTA Capital Investment Grant signed July 8, 2024, plus $4.06 billion in federal RRIF loans for the local share
Size / Scope
About 9 miles of new passenger rail track including nearly 5 miles of tunnel boring for a two-tube tunnel; Palisades TBM cutterhead 28 ft 8 in, finished inside diameter 25 ft 2 in
Owner / Developer
Gateway Development Commission, with Amtrak, NJ Transit, FRA and FTA as partners
General Contractor / CM
Multiple primes — Schiavone/Dragados/Lane JV (Palisades Tunnel, $465.6M); Frontier-Kemper/Tutor Perini JV (Manhattan Tunnel, about $1.2B); Traylor Bros./Walsh/Skanska JV (Hudson River Tunnel Section, $1.29B); Skanska Creamer Sanzari NJSA JV (NJ Surface Alignment, $711.7M); Weeks Marine (Hudson River Ground Stabilization)
Architect
Not publicly announced
Engineer of Record
Not publicly announced
Construction Start
November 2023 (Tonnelle Avenue in New Jersey and Hudson Yards Concrete Casing Section 3 in Manhattan); Palisades TBM boring began October 2026
Expected Completion
New tunnel in revenue service 2035; North River Tunnel rehabilitation complete 2038
Published Aug 24, 2026Last updated Oct 29, 202610 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

The Hudson Tunnel Project stopped being a procurement story in October 2026. The Gateway Development Commission said on October 8 that the first tunnel boring machine had started cutting the northern tube under the Palisades, according to NJBIZ (Oct. 9, 2026), with the second machine due to start the southern tube in the following weeks. As of October 29, 2026, Gateway had not announced a start date for that second machine. Every major tunneling contract on the $16 billion program has been awarded. Gateway's project page says seven of the ten construction packages are in progress or complete (gatewayprogram.org, accessed Oct. 29, 2026).

This profile covers what is being built, who holds each contract, how the money was assembled, and what has gone wrong or nearly gone wrong along the way. All figures come from the Gateway Development Commission or dated trade and news coverage, cited as we go.

What Is Being Built

The Hudson Tunnel Project is two jobs sold as one. Gateway describes the first as nine miles of new passenger rail track between New Jersey and New York, including nearly five miles of tunnel boring for a new two-tube tunnel under the Hudson River. The second is the rehabilitation of the North River Tunnel, which entered service in 1910 and was flooded by Hurricane Sandy in 2012.

The sequencing is the whole point. The new tunnel has to carry trains before the old one can be taken out of service and rebuilt. That dependency is why Gateway targets 2035 for the new tunnel to open and 2038 for the North River Tunnel rehabilitation to finish. When both are done, the Northeast Corridor goes from two tracks under the river to four.

The Gateway Development Commission is the owner, working with Amtrak, NJ Transit, the Federal Railroad Administration and the Federal Transit Administration. Gateway lists ten construction packages. The ones with their own project pages are the Tonnelle Avenue Bridge and Utility Relocation, Hudson Yards Concrete Casing Section 3, Hudson River Ground Stabilization, the Palisades Tunnel, the Manhattan Tunnel, the Hudson River Tunnel Section, the New Jersey Surface Alignment, and a noise abatement program.

Two packages are early-works anchors worth knowing:

  • Tonnelle Avenue Bridge and Utility Relocation broke ground in November 2023 and Gateway lists it as complete, finished in 2026. It dug out the ground under U.S. Routes 1 and 9 in North Bergen and built a bridge so the Palisades machines could be assembled and launched below the highway.
  • Hudson Yards Concrete Casing Section 3 also launched in November 2023. Gateway says it extends the rail right-of-way under Hudson Yards with a casing about 500 feet long, 60 feet wide and 60 feet high, with reinforced concrete walls 3.5 to 10 feet thick. Sections 1 and 2 were finished in 2018.

The Contract Stack

There is no single general contractor. Gateway split the heavy civil work into three tunnel packages plus supporting civil contracts, and the awards went to different teams.

Package Contractor Value Award
1A Palisades Tunnel Schiavone Dragados Lane JV $465.6 million August 2024
1B Manhattan Tunnel Frontier-Kemper / Tutor Perini JV $1.2 billion Feb. 3, 2025
1C Hudson River Tunnel Section Traylor Bros. / Walsh / Skanska JV $1.29 billion April 27, 2026
New Jersey Surface Alignment Skanska Creamer Sanzari NJSA JV $711.7 million June 1, 2026
Hudson River Ground Stabilization Weeks Marine not stated in our sources; $88 million change order July 2026 2024 start

Sources for the table: Mass Transit for the $465.6 million design-bid-build Palisades award (Underground Infrastructure reported it Aug. 6, 2024, with completion anticipated by 2027); ENR (Feb. 2025) for the Manhattan Tunnel award, a $1.2 billion design-build contract approved Feb. 3, 2025; ENR (April 28, 2026) for Package 1C; ENR (June 1, 2026) for the surface alignment; and Construction Dive (July 14, 2026) for the Weeks Marine change order.

Gateway says Packages 1A, 1B and 1C together account for all tunnel boring and the core and shell of the new tunnel, which it calls the entire heavy civil portion of the project. ENR reported that an owner-controlled insurance program covers the Package 1C award and two future packages.

A few details from the procurement record are useful to bidders watching how this owner buys work. The Palisades contract was one of five proposals, per Mass Transit. On the New Jersey Surface Alignment, ENR reported that four teams were shortlisted but only two bid, after the George Harms/Hardesty & Hanover team and a Halmar-led team declined. When a shortlist thins out on bid day, it says something about how much heavy civil capacity is left in the region.

The Palisades Drive: Hard Rock

The New Jersey side is a hard-rock job. Gateway says the Palisades Tunnel is two parallel tubes of about 5,100 feet each, running from the portal at Tonnelle Avenue in North Bergen to the Hudson County Access Shaft on the Weehawken/Hoboken line. Each tube gets an inside diameter of 25 feet 2 inches, and the package includes six cross passages.

Two single-shield Herrenknecht machines do the boring. Gateway's figures: each weighs 1,680 tons, the trailing gantries stretch back roughly 500 feet, and the cutterhead is 28 feet 8 inches in diameter. Gateway expects about 30 feet of new tunnel per day. NJBIZ reported the drive is expected to take about a year.

The most detailed site reporting came from the Daily Commercial News (May 14, 2026), quoting the contractor team:

  • The rock averages about 35,000 psi. For comparison, structural concrete on most commercial jobs is specified somewhere in the single-digit thousands of psi.
  • Cutterhead maintenance or parts changes may be needed every two days, rather than about once a week in normal ground.
  • The machines probe-drill 150 feet ahead of the face to look for water. The geotechnical report flags a fault that could bring in water, and grout is the planned mitigation.
  • The tunnels start about 80 feet below grade and reach about 280 feet under the Palisades, and the two tubes run roughly 50 feet apart.
  • Each machine runs with roughly a 40-person crew.
  • The launch box is about 600 feet long and roughly 80 feet deep, supported with soldier piles and lagging and stabilized with shotcrete. A 300-ton crane on concrete pads lowered the heaviest parts.
  • Factory acceptance testing in Germany took 18 months, and parts came in through the ports of Baltimore and Newark.

That same article put the excavated diameter at just under 29 feet and the finished diameter at 25 feet 4 inches. Gateway's official figure is 25 feet 2 inches. The gap is two inches, and we use Gateway's number.

The estimating lesson is in the grout. In fractured hard rock with a known fault on the alignment, probe-and-grout cycles are a planned production activity, not a contingency. Anyone pricing similar rock tunneling should carry those cycles in the base schedule. If you need to rough out spoil volume on a launch box of that size, the excavation calculator gets you to the right order of magnitude.

Under the River and on the Manhattan Side

Package 1C flips the ground conditions. Gateway says the Hudson River Tunnel Section covers about 7,250 feet of each tube, from the Hudson County Access Shaft to the 12th Avenue Shaft in Manhattan, and includes nine cross passages. The scope also covers ground stabilization near the Hudson-Bergen Light Rail and a permanent support system for the Willow Avenue Bridge between Weehawken and Hoboken.

Gateway will use two new mixed-ground machines designed for both rock and soft soil, because this reach passes through a wide range of conditions. ENR reported that the machines will bore through a block of riverbed that has been pre-treated under the ground stabilization contract. Early works near the Weehawken shaft, including jet grouting and utility relocation, were expected to start in 2026. Construction Dive reported that tunnel boring under the river is planned to start in 2028.

The Manhattan Tunnel package is the short, awkward end. ENR reported it covers about 700 feet of twin 30-foot-diameter tunnels from the Manhattan bulkhead to Hudson Yards, an access shaft at 12th Avenue that later becomes a ventilation facility, and removal of obstructions that could damage the river machines. Gateway says historic fill along Manhattan's western shore led the contractor to propose a digger shield, keeping most of the work underground. ENR put completion of this package in 2029.

This is the reason the contract stack looks the way it does. Hard rock in New Jersey, mixed ground under the river, and historic fill in Manhattan call for three different machine types and three different risk profiles. For a broader view of where this sits among current U.S. drives, see our tally of active tunnel boring projects.

The $88 Million Change Order

Construction Dive reported on July 14, 2026 that Gateway approved an $88 million change order with Weeks Marine, a Kiewit subsidiary already mobilized on the Hudson River Ground Stabilization work. Gateway's Jim Starace discussed it at the July 8 board meeting.

The scope: remove about 500 submerged wooden piles left in the riverbed from the demolition of Pier 68, then mix lightweight concrete into the riverbed soil to fill voids and even out the ground. The change order extends the work area about 265 feet toward Manhattan. The original stabilization scope prepared a section of riverbed about 1,200 feet long by 100 feet wide. A small number of piles were already pulled in 2025, and some may break during extraction. The work runs inside a cofferdam because of river currents, and it is supposed to be finished before boring under the river starts in 2028.

Read this as an owner buying down risk. A machine that meets timber piles at the face can damage cutting tools and force an intervention under pressure deep below a working harbor, which costs far more in schedule than the change order does. Clearing the path on the owner's schedule is cheaper than paying for it later under a differing-site-conditions claim.

How the $16 Billion Was Assembled

The full funding package closed on July 8, 2024. According to Sen. Cory Booker's office (July 8, 2024), Gateway signed a $6.88 billion Full Funding Grant Agreement with the FTA under the Capital Investment Grant program, the largest in the program's history, and closed three federal Railroad Rehabilitation and Improvement Financing loans totaling $4.06 billion to cover the local share. The same release lists $3.8 billion from the Federal-State Partnership program, a $292 million Mega grant, a $25 million RAISE grant and $1 billion from Amtrak. Costs are split 70/30 between the federal government and the local partners (New York, New Jersey and the Port Authority).

Financing costs sit on top of the headline number. Gothamist reported on Aug. 21, 2026 that federal documents estimate about $1.4 billion in financing costs on Gateway.

Federal money did not flow smoothly. ENR reported on Feb. 6, 2026 that the U.S. Department of Transportation had halted disbursements in late 2025, citing a compliance review, and that Gateway said it would begin suspending work that afternoon. Judge Jeannette Vargas of the Southern District of New York issued a temporary restraining order the same day. Construction Dive reported in September 2026 that work resumed earlier in the year and that a federal judge later barred the department from withholding funds over its disadvantaged business enterprise program. For contractors, the practical lesson is that a signed federal grant agreement does not guarantee steady draws, and cash flow terms in subcontracts deserve a closer read on federally funded megaprojects.

Where the Remaining Work Is

With all three tunnel packages and the surface alignment awarded, the prime-level civil procurement is largely done. ENR reported that track and signal systems for the New Jersey approach will go out as future contracts, and the North River Tunnel rehabilitation is still ahead. The near-term opportunity is a tier down: precast segment supply, grout, ventilation, muck handling, survey and settlement monitoring, electrical and mechanical work, and marine support for the river drive.

Segment and grout demand ties this job to concrete and cement pricing for years. Contractors bidding those scopes should track concrete prices and build escalation language into multi-year supply agreements. Federally advertised work shows up on the bid board, and Gateway runs its own vendor portal for direct procurements.

What to Watch Next

  • The second Palisades machine starting the southern tube, which Gateway said would happen in the weeks after October 8, 2026. No start had been announced by October 29.
  • Advance rate in full-face rock. At Gateway's planned 30 feet per day, about 5,100 feet is roughly a year per tube. What probe-and-grout cycles do to that average will tell you whether 2035 holds.
  • Weeks Marine's pile removal and riverbed treatment, which has to finish before river boring starts in 2028.
  • Funding litigation. The federal dispute was still active as of the September 2026 launch coverage.

For more on federally funded heavy civil work, see our IIJA contractor guide and our explainer on why U.S. tunnels cost so much.

FAQ

How much does the Hudson Tunnel Project cost?

The Gateway Development Commission puts the program at $16 billion. That covers the new two-tube tunnel and the rehabilitation of the 1910 North River Tunnel. Federal documents also estimate about $1.4 billion in financing costs, per Gothamist (Aug. 21, 2026).

Who are the main contractors?

Schiavone Dragados Lane JV holds the Palisades Tunnel ($465.6 million). Frontier-Kemper/Tutor Perini JV holds the Manhattan Tunnel (about $1.2 billion, per ENR). Traylor Bros./Walsh/Skanska JV holds the Hudson River Tunnel Section ($1.29 billion). Skanska Creamer Sanzari NJSA JV holds the New Jersey Surface Alignment ($711.7 million). Weeks Marine is doing the river ground stabilization.

When did tunnel boring start?

The first Palisades machine was ceremonially launched Sept. 28, 2026, and Gateway announced on Oct. 8, 2026 that it had begun boring the northern tube. Boring under the Hudson River is planned to start in 2028.

When will the new tunnel open?

Gateway targets 2035 for the new tunnel to enter service and 2038 for the North River Tunnel rehabilitation to be complete.

How was the project funded?

A $6.88 billion FTA Capital Investment Grant signed July 8, 2024, $4.06 billion in federal RRIF loans for the local share, $3.8 billion from the Federal-State Partnership program, smaller federal grants, and $1 billion from Amtrak, with a 70/30 federal/local split.

How big are the Palisades tunnel boring machines?

Gateway says each has a 28-foot 8-inch cutterhead, weighs 1,680 tons and trails about 500 feet of gantries. Finished inside diameter is 25 feet 2 inches.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free