ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
B
Buildermuse
Infrastructure

Tunnel Boring Projects: 5 Verified Active US TBMs in 2026

Lisa Chen·April 10, 2026·Updated October 18, 2026·16 min read

Share this with your estimator.

Tunnel Boring Projects: 5 Verified Active US TBMs in 2026

Counting active tunnel boring machines in the US is harder than it sounds. Machines finish drives and get pulled out, others sit in a factory for months before launch, and agency press releases lag the work underground. What we could verify from primary sources, as of mid-October 2026, is 5 TBMs that are boring, launched, or assembled and ready to dig, spread across 3 projects: the Hudson Tunnel Project in New Jersey, DC Water's Potomac River Tunnel in Washington, and the Ship Canal Water Quality Project in Seattle.

That is not a full national census. Smaller sewer, water and utility drives start and finish constantly, and some never get a press release. But it is a list where every entry traces back to a named source and a date, which is more useful to a contractor than a big round number nobody can check. Below we also cover the projects that are close to launching a machine (Second Avenue Subway Phase 2 and BART Silicon Valley Phase II) and several large drives that have finished tunneling in the last few years.

Active TBM Projects: City by City

New York / New Jersey: Hudson Tunnel Project, 2 TBMs launched. This is the highest-profile tunnel job in the country. Two Herrenknecht single-shield hard-rock machines with 28-foot, 8-inch cutterheads were ceremonially launched on September 28, 2026 for the Palisades section, according to 6sqft (Sept. 28, 2026), which puts the overall Hudson Tunnel Project at $16 billion and names the Palisades contractor as Schiavone Dragados Lane JV. Each machine trails roughly 500 feet of gantry and weighs more than 1,680 tons.

The first machine started boring the northern tube on October 8, 2026, and the Gateway Development Commission said the second would start the southern tube "in the coming weeks," per NJBIZ (Oct. 9, 2026). Each drive is about 5,100 feet from the North Bergen portal to the Hudson County Access Shaft on the Weehawken/Hoboken line, at a planned pace of roughly 30 feet per day, and is expected to take about a year. After that, the hard-rock machines come out and a different set designed for mixed ground under the Hudson River takes over.

New York: Second Avenue Subway Phase 2, TBM under construction (not counted). The MTA awarded the $1.972 billion tunneling contract to Connect Plus Partners, a joint venture of Halmar International and FCC Construction, in 2025, according to Underground Infrastructure (Aug. 18, 2025). The total Phase 2 budget is $6.968 billion, and as of the governor's September 14, 2026 update, the TBM "is currently under construction" while crews prepare the launch site. Tunnel boring is expected to begin in 2027, the tunneling contract is forecast to reach substantial completion in September 2029, and full completion is targeted for fall 2032. The extension runs about 1.5 miles from 96th Street to 125th Street with three new stations at 106th, 116th and 125th Streets.

Washington, DC: Potomac River Tunnel, 2 TBMs. DC Water's 5.5-mile, 18-foot-diameter tunnel runs about 100 feet down and carries a tunnel cost of $819 million, per the DC Water project page (accessed Oct. 18, 2026). TBM Mary was fully assembled at 706 feet long and tunneling north as of DC Water's August 27, 2026 update, heading for a 2.4-mile drive from West Potomac Park to Georgetown University after a planned changeover of more than two months from soft ground to bedrock. The second machine, Emily, was christened on September 19, 2026 and will drive about 3.1 miles south toward Joint Base Anacostia-Bolling, per DC Water (Sept. 19, 2026). The tunnel is expected to begin operating in 2030.

Seattle: Ship Canal Water Quality Project, 1 TBM boring. The big storage tunnel here is done. Seattle Public Utilities says the roughly 18-foot TBM MudHoney finished the 2.7-mile storage tunnel (18 feet 10 inches inside diameter) in June 2023. What is still boring is a 7-foot-1-inch slurry pressurized-face TBM, manufactured in Germany in 2026, cutting about 2,000 feet of conveyance tunnel in Ballard in two runs of 643 and 1,276 feet. SPU expects that tunneling to last until late 2026, with the storage tunnel operational in 2027. The overall project costs about $710 million, per the SPU project page (latest update dated Sept. 16, 2026). Once in service, the storage tunnel captures more than 30 million gallons during a heavy storm, per SPU.

Large drives that have finished boring

  • Delaware Aqueduct bypass (New York). Tunneling on the 2.5-mile Rondout-West Branch bypass under the Hudson finished in 2019, according to Wikipedia's Delaware Aqueduct entry, which cites NYC DEP's estimate of about $1.5 billion for the full repair program. No TBM is active there.
  • LA Metro D Line (Purple Line) Extension. Metro reports all tunneling for the project was complete as of April 2024. Section 2 machines Harriet and Ruth finished in January 2023, and Section 3 machines Aura and Iris broke through at Century City in October 2023. Section 1 opened May 8, 2026, per the Metro project page (accessed Oct. 18, 2026).
  • Northeast Boundary Tunnel (DC). The 27,000-foot, 23-foot-diameter tunnel was placed in operation on September 15, 2023, per DC Water.

Two other large Herrenknecht drives in Virginia also wrapped up recently. On the Hampton Roads Bridge-Tunnel expansion ($3.9 billion, per VDOT, page updated Oct. 13, 2026), TBM Mary made its final breakthrough on September 24, 2025. On the Parallel Thimble Shoal Tunnel, the 43.5-foot TBM Chessie broke through on January 27, 2025, per the Chesapeake Bay Bridge-Tunnel District; the design-builder is Chesapeake Tunnel Joint Venture (Dragados USA and Schiavone Construction), and the tunnel is forecast to open in early 2028.

TBM Technology and Costs

The machines on this list cover the three main families of TBM, and the choice comes down to ground and water.

Hard-rock and single-shield machines use disc cutters to break competent rock. That is what the Hudson Tunnel Project is running through the Palisades: dry, hard rock where the main risks are cutter wear and advance rate rather than face stability. The plan to swap in a different machine set once the drives reach the river shows how tightly TBM selection is tied to geology. One machine rarely suits every reach of a long alignment.

Slurry machines pressurize the face with a bentonite suspension, which suits water-bearing ground. The 7-foot Ballard machine in Seattle is a slurry pressurized-face unit, run remotely from a surface crew of 6 to 10 people according to SPU. Slurry setups need a separation plant at the surface, which affects site size on cramped urban jobs.

Earth pressure balance machines use the excavated soil itself, conditioned and held under pressure in the cutterhead chamber, to support the face in soft ground. They are the common choice for urban transit tunnels in clays and sands.

Some machines switch between modes. DC Water's Mary is built to stop for a planned changeover of more than two months when the drive moves from softer soil into bedrock.

Diameter drives cost and logistics. The machines on this list run from about 7 feet (Seattle conveyance) to 18 feet (Potomac River Tunnel) to nearly 29 feet (Hudson Tunnel). The largest US machine in the pipeline is BART Silicon Valley Phase II's, which the FTA's project management oversight contractor describes as a single bore about 53 feet in diameter.

Machine prices are rarely published on their own. On most jobs the TBM is bought by the tunneling contractor and its cost is buried in the bid, along with assembly, launch, refurbishment and eventual removal or resale. When an owner buys the machine directly, as VTA did on BART Phase II, the purchase shows up in owner procurement records instead. If you are pricing work around a drive, ask the prime or the owner who holds the machine, who carries its performance risk, and what the contract says about downtime for cutterhead interventions or mode changes. Those terms move more money than the sticker price of the machine.

Why US Tunneling Costs Are So High

US transit tunneling is expensive by international standards, and that is no longer a fringe claim. The Transit Costs Project, a research group that has built a database covering 59 countries and more than 20,000 km of urban rail, frames its work around why US projects "cost more and take longer to construct than similar projects in Italy, Sweden, Turkey, Korea, Chile, and Spain" (transitcosts.com, accessed Oct. 18, 2026).

The usual suspects are station design (big mezzanines and deep cut-and-cover boxes), long environmental review periods that stretch schedules and expose budgets to escalation, utility relocation in old, crowded streets, risk allocation in contracts that pushes contractors to price in large contingencies, and thin competition for the largest packages. The projects on this list show several of these in action. Second Avenue Subway Phase 2 split the work into four contracts, with a utility relocation contract awarded in January 2024 before any tunnel work. BART Silicon Valley Phase II's cost estimate has grown from $9.148 billion at an early baseline to $12.746 billion, and its revenue service date has moved to February 2039, according to the FTA project monitoring report for status as of February 28, 2026.

Contractor Landscape and Workforce

The firms that show up on verified projects are a short list, and the same names recur. Dragados and Schiavone, both part of Spain's ACS group, are in the Palisades JV on the Hudson Tunnel (Schiavone Dragados Lane JV) and in the Chesapeake Tunnel Joint Venture on Thimble Shoal. Halmar International and Spain's FCC Construction make up Connect Plus Partners on Second Avenue Subway Phase 2. On BART Silicon Valley Phase II, VTA's progressive design-builder was Kiewit Shea Traylor (KST), until the VTA board authorized an off-ramp from that tunnel and trackwork contract on June 27, 2025 after nearly a year of failed cost and schedule negotiations, per the FTA monitoring report. VTA bought the 53-foot machine itself and is repackaging the work, which means it now carries the TBM performance risk.

That last point matters for bidders. The FTA's oversight contractor noted that qualified tunnel contractors able to run a large-diameter machine are scarce, and that outreach would be needed if a firm other than Kiewit, Shea or Traylor is to compete for the tunneling package. For a mid-sized heavy civil firm, the realistic entry point is usually a subcontract (shafts, precast segment supply, muck haul, utilities, instrumentation) rather than a prime role on the drive.

On staffing, the same federal report notes that US TBM operations typically run two 10-hour shifts, five days a week, and that running a 53-foot machine more continuously raises labor and maintenance demands. We did not find a published national count of workers on US TBM drives. If you are bidding work tied to a drive, ask the prime and the local building trades councils about available crews and wage packages for miners, segment erectors, operators and electricians before you price labor.

The Future TBM Pipeline

Several large machines are close to launch, and these are the ones contractors should be tracking for 2027 and beyond.

Second Avenue Subway Phase 2 (New York). TBM under construction as of September 14, 2026, with boring expected to start in 2027. Contract 4 (station fit-out, systems and finishes) is at the RFQ stage, with a request for proposals planned by year-end 2026 and contractor selection expected in mid-2027, per the governor's office.

BART Silicon Valley Phase II (San Jose). The Herrenknecht machine has completed factory acceptance testing, and work on the West Portal launch structure at Newhall Yard continues, per the FTA project monitoring report (status as of Feb. 28, 2026). Total project cost is $12.746 billion with a revenue service date of February 2039. VTA's roadmap targets a Full Funding Grant Agreement in July 2027. The PMOC's baseline assumed a TBM advance rate of 29 feet per day.

Hudson Tunnel river section. Once the Palisades drives reach the Hudson County Access Shaft, roughly a year after launch, a second set of machines built for mixed ground under the river is due to take over.

Sepulveda Transit Corridor (Los Angeles). Per Metro's project page as of October 2026, the Metro Board selected a locally preferred alternative in January 2026: underground heavy rail between the Van Nuys Metrolink Station and the E Line Expo/Sepulveda Station, with an initial operating segment of about 8.4 miles. Scoping comments are due November 18, 2026. Metro has not yet published a cost estimate or construction timeline, so this one is a watch item rather than a bid target for now.

Chicago's Red Line Extension sometimes gets lumped in with tunnel work, but CTA's Red Line Extension page describes a 5.5-mile extension from 95th/Dan Ryan to 130th Street but does not describe it as a bored tunnel.

Safety Considerations in Tunnel Construction

Tunneling carries hazards most surface trades never see: ground collapse during cutterhead interventions and cross-passage work, hyperbaric exposure for crews entering a pressurized face chamber, fires in a confined space packed with hydraulics and electrical gear, water inrush in saturated ground, and naturally occurring gases. The crews who work these drives need training well beyond what most construction workers get on a surface job.

What is consistent across modern US drives is the toolkit: continuous gas monitoring along the tunnel, medical surveillance for any compressed-air work, refuge chambers that move forward with the machine, fire suppression on the TBM and at the portal, and strict rules for interventions. Remote operation also changes exposure. SPU's Ballard machine is steered from an aboveground control room, so the crew is not working inside the bore.

Cost Reduction Strategies

Owners are trying a few different levers to bring tunnel costs down, and the verified projects show them being tested in practice.

Standardized station designs. Much of the cost on transit tunnels sits in the stations rather than the bore. Simpler, repeatable station boxes with fewer custom finishes are the change most often pointed to by cost researchers comparing US projects with those in Italy, Spain or Korea. For a sense of how per-square-foot costs behave on simpler public buildings, see our look at station construction costs for fire stations.

Large single-bore tunnels. VTA confirmed one large bore for BART Silicon Valley Phase II after a peer review by tunneling and transit experts from other agencies, saying it avoids the cost, complexity and downtown disruption of an option that used two machines running at once plus cut-and-cover excavation, per Mass Transit (Oct. 21, 2025). The trade-off is the biggest US machine on order and concentrated schedule risk on a single drive, which the FTA monitoring report flags directly. Logistics on a job like this look more like the construction of a heavy industrial plant than a typical transit line.

Owner-procured machines and contract repackaging. VTA now owns its TBM outright and has broken BART Phase II into six construction packages. The MTA split Second Avenue Subway Phase 2 into four contracts, separating utility relocation, tunneling, the 106th Street shell and station fit-out. Whether either approach saves money will not be known for years, but both are deliberate attempts to reduce the risk premium bidders build into one giant contract.

Progressive design-build, with off-ramps. BART Phase II is the cautionary case. Early contractor involvement through a progressive design-build is supposed to produce a negotiated price with fewer surprises. In that case the owner and the KST joint venture could not agree on Stage 2 cost and schedule, and VTA exercised the off-ramp in June 2025.

Environmental and Community Impact Management

Urban tunneling is as much a neighborhood logistics job as an engineering one. Vibration and ground-borne noise from the machine are monitored with instruments in nearby buildings, and operators adjust advance rate and face pressure to stay below limits. Settlement monitoring with automated total stations and prisms catches ground movement early enough to grout or change TBM parameters before buildings are damaged. Muck haul is the other daily pressure point: every foot of advance produces spoil that has to be trucked or barged out, and haul routes, truck counts and work hours are usually written into permits and community agreements.

The verified projects show how this plays out on the ground. SPU limits Ballard tunneling to Monday through Saturday, 6 a.m. to 6 p.m. DC Water brought the public underground at the Potomac River Tunnel site when it christened Emily in September 2026. The Hudson Tunnel Project's one-year Palisades drive ends at an access shaft on the Weehawken/Hoboken border, where muck removal and machine swaps will be visible to residents for years. Community acceptance is part of the schedule on every one of these jobs, not an afterthought.

Frequently Asked Questions

How many tunnel boring machines are active in the US right now?

We verified 5 TBMs launched, boring or assembled on 3 US projects as of October 2026: 2 on the Hudson Tunnel Project (first machine boring since Oct. 8, 2026, second due to start within weeks), 2 on DC Water's Potomac River Tunnel (Mary tunneling, Emily christened Sept. 19, 2026), and 1 small conveyance TBM on Seattle's Ship Canal project. This is not a full census. Smaller utility drives are often not publicized.

Which tunnel boring construction projects in the US are the most expensive?

Among the projects here, the Hudson Tunnel Project is about $16 billion overall (6sqft, Sept. 28, 2026), BART Silicon Valley Phase II is $12.746 billion (FTA monitoring report, status Feb. 28, 2026), and Second Avenue Subway Phase 2 is budgeted at $6.968 billion (New York governor's office, Sept. 14, 2026). Those are whole-project costs, not tunnel-only costs.

When will the next big TBMs start boring?

Second Avenue Subway Phase 2 expects to start boring in 2027. The Hudson Tunnel Project will bring in river-section machines after the Palisades drives finish, roughly a year after the October 2026 start. BART Silicon Valley Phase II's machine has passed factory testing, but the latest federal monitoring report we found (status as of Feb. 28, 2026) did not give a launch date. Watch VTA's board materials and the next FTA report for one.

Which contractors are building US tunnel projects?

On the verified projects: Schiavone Dragados Lane JV (Hudson Tunnel, Palisades section), Connect Plus Partners, a Halmar International and FCC Construction JV (Second Avenue Subway Phase 2 tunneling), and Chesapeake Tunnel Joint Venture, made up of Dragados USA and Schiavone (Parallel Thimble Shoal Tunnel). Herrenknecht built the Hudson, Thimble Shoal and BART Phase II machines.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
map

See infrastructure spending data for your state

Federal contract awards, top contractors, and spending trends — all 50 states.

View your state