New Nissan Stadium: One Crane Left and Four Months to Substantial Completion
The Titans' own September construction update, posted October 6, 2026, gives the clearest read on where the new Nissan Stadium stands: one tower crane left on site, the roof and secondary steel systems complete, ETFE membrane cushions about 50 percent installed, and more than 19,000 seats in place after Irwin Seating Company started setting them at the beginning of September. The same update describes the building as four months from substantial completion.
That lines up with what Titans president and CEO Burke Nihill told the Associated Press in March 2026: "We're going to get keys to this building in February." The team plans to play its first season there in 2027. For a contractor reading the job from the outside, the pattern is the familiar one on a big enclosed venue. The structure and the roof drove the first two years; now the finish trades, seating, video boards and commissioning control the last few months.
The money: $2.1 billion and the public share
AP's March 2026 report put the stadium at $2.1 billion, with $1.2 billion of that coming from state and local bonds. Trade coverage has used a slightly higher figure: Engineering News-Record called it a $2.2 billion stadium in June 2025, and the Nashville Post used $2.2 billion in May 2026. The gap is most likely a question of what scope each outlet counts, and neither the team nor Metro has published a line-item budget we could check, so treat both numbers as headline figures rather than a contract value.
The funding structure is better documented. The Bond Buyer reported on April 26, 2023, that Nashville's Metropolitan Council approved the deal 26-12 the previous evening after a five-hour hearing. The pieces:
- $760 million in revenue bonds issued through the Metropolitan Sports Authority.
- $500 million in state general obligation bonds, allocated in the state budget contingent on local approval.
- $840 million from the Titans, backed by personal seat license sales and separate NFL funding.
That puts public money at about $1.26 billion, which the Bond Buyer described as the largest public commitment to a U.S. pro sports venue at the time. The Metro bonds are to be repaid from a new 1 percent citywide hotel tax plus sales tax collected inside the stadium and on its surrounding campus, according to the Bond Buyer and WSMV's July 21, 2023 coverage of the Sports Authority vote. As part of the deal, the Bond Buyer reported, the team also agreed to pay off $30 million of outstanding bonds on the old Nissan Stadium and waive claims to $32 million in capital spending reimbursement.
For context on how this fits the broader stadium pipeline, including the Bills, Jaguars and Browns projects, see our sports stadium construction overview.
Who is building it
Construction is being delivered by the Tennessee Builders Alliance, a joint venture of four firms. Construction Dive's November 21, 2025 topping-out coverage lists them as New York-based Turner Construction, Indianapolis-based AECOM Hunt, Brentwood, Tennessee-headquartered Polk & Associates Construction, and Nashville-based ICF Builders & Consultants. Two national sports builders paired with two Middle Tennessee firms is a common structure on publicly funded venues, where local participation goals are part of the political deal.
On the design side, the Titans announced the full architecture and engineering team on January 23, 2024: 24 firms, including nine local businesses and 13 disadvantaged business enterprises. MANICA is lead design architect. TVS of Atlanta is architect of record and holds all of the subconsultant contracts. Walter P Moore's listed scope is structural engineering, parking, secure design and blast, and enclosure engineering for the ETFE roof. ENR's June 2025 feature confirms the MANICA and TVS roles.
Contractors trying to break into the Middle Tennessee market can start with our contractor directory and the state dashboards.
The roof is the reason this building looks the way it does
ENR's June 2, 2025 feature describes a roughly 350,000-square-foot cable-net ETFE roof over a roof diameter of about 660 feet. Cables run nearly 700 feet and pass through box beams roughly six feet by six feet, and the net is tensioned from the back side to jack it into position.
That structural approach is different from a conventional long-span steel deck. A tensioned cable net carries load in tension rather than bending, and lightweight inflated ETFE cushions sit on top of it. The practical consequence on site is sequence. A cable net is not stable as a partial system; it has to be lifted and tensioned as a whole, which turns the roof erection into a synchronized, instrumented lift rather than a piece-by-piece set.
How the roof went up
The Titans' monthly updates on newnissanstadium.com give a dated record of the roof work:
- June 2025: the July 10, 2025 update reported 4 of the 50 ring beam box sections set to complete the circular frame.
- November 2025: the ring beam milestone post (November 10, 2025) said the circle was complete. Ring beam installation began in late June, took 20 weeks and involved 60 workers.
- January 2026: the update posted February 4, 2026 reported 42 of 68 stainless-steel roof cables unrolled and prepped for connection to the ring beam, with the big lift of the cable net scheduled for mid-spring.
- May 2026: the Nashville Post reported on May 8 that the ETFE roofing system was 65 percent complete, with 108 strand jacks in place lifting the top cable net grid. The Titans' May update (posted June 12) said the top layer of cables was locked onto the compression ring and 60 of 224 vertical roof posts were installed.
- June 2026: the June update said the lower net was fully secured to the compression ring.
- August 2026: WSMV reported on August 12 that the ETFE cable net system was complete and fully installed.
- September 2026: the roof and secondary steel were complete and membrane cushions were about 50 percent installed.
The strand-jack lift deserves a closer look for anyone who has never run one. It is a hydraulic operation in which every jack has to stay within tolerance of the others while the net picks up load. That lift was arguably the riskiest single activity on the schedule, and it is now behind the team.
The structure underneath
Construction Dive's November 21, 2025 topping-out coverage reported more than 12,400 beams and 18,000 tons of structural steel, about 98,000 cubic yards of concrete, and a building of about 1.8 million square feet. At that point about 1,800 workers were on site daily and the project had logged 3.6 million work hours. Estimators sizing similar pours can run volumes with our concrete calculator and track input pricing on the concrete and steel index pages.
Progress figures from the team's updates show how far the envelope and interiors ran ahead of the roof:
- End of January 2026: curtain wall 84 percent, interior masonry 80 percent, framing and drywall about 60 percent, and 21 of 27 passenger elevators with platforms installed.
- April 2026 (Nashville Post, May 8): framing and drywall at 80 percent, concrete 97 percent, 1,859 of 3,102 aisle steps complete, all 44 escalators set.
- May 2026 (Titans update): masonry 99 percent, concrete 96 percent, framing and drywall 85 percent, and 305 doors in place.
The minor disagreement between the Nashville Post's 97 percent concrete and the team's later 96 percent is in the sources themselves; we have reported both as published.
Running the envelope ahead of the roof is deliberate. It lets interior trades work in protected space on the lower levels while the net is still being lifted above them.
Where the job stands in fall 2026
WZTV/Fox 17 reported on August 24, 2026, from an update presented to the Metro Sports Authority, that the project was on schedule and that crews were working toward enclosing the stadium by mid-October. Seat installation was expected to run at about 10,000 seats a month. By the end of September, the Titans reported more than 19,000 seats installed, which is close to that pace.
Other items in the October 6 update:
- The Nissan Stadium letters are up on all four sides and have been electrically tested.
- Daktronics finished the LED ribbon boards on the Mezzanine and Club levels, and the video board wrapping the upper bowl is 80 percent complete.
- Floor and wall tile, glass handrails and partitions are going in across the bowl and suites, with millwork continuing in clubs, suites and operations areas.
- The first of seven concrete slab placements on the playing field was poured on the east end.
- A steel canopy went up on the North Plaza, and concrete on the north and south monumental stairs is approaching 50 percent.
Crane count has been a useful progress signal. WSMV reported two of four cranes removed in August; the team reported one left standing in early October. Contractors don't release a tower crane until the material it serves is in the building.
What is left
The remaining critical path is full enclosure, the last membrane cushions, the rest of the seating, field slab placements, finishes and then systems commissioning and turnover. Enclosure matters because tile, millwork, flooring, seating and LED assemblies all carry environmental requirements, and a building that isn't sealed can't hold temperature and humidity through a Nashville winter.
There is outside work too. Fox 17 reported that construction on the Seigenthaler Bridge connector, a new bridge and ramp linking the pedestrian bridge to the stadium area, was expected to start in November 2026 and finish by the end of 2027, with the existing bridge staying open.
The stadium has already started taking event bookings, per WSMV, and the Nashville Post reported that concerts and other events are expected before the Titans' first game there in fall 2027. NFL owners voted in May 2026 to award Nashville the 2030 Super Bowl, according to AP coverage on May 20, 2026, which gives the building a few full seasons of operation before that event.
Frequently asked questions
Who is building the new Nissan Stadium?
The Tennessee Builders Alliance, a joint venture of Turner Construction, AECOM Hunt, I.C.F. Builders & Consultants and Polk & Associates Construction. MANICA is the lead design architect, TVS is architect of record, and Walter P Moore is the structural engineer.
How much does the new Nissan Stadium cost and who is paying?
AP reported $2.1 billion in March 2026; ENR and the Nashville Post have used $2.2 billion. Public money totals about $1.26 billion, made up of $760 million in Metro Sports Authority bonds and $500 million in state bonds. The Titans, the NFL and seat-license sales cover $840 million.
What is the roof made of?
A tensioned stainless-steel cable net carrying translucent ETFE cushions. ENR reported it at about 350,000 square feet and roughly 660 feet in diameter. It is fixed, not retractable.
When does it open?
The Titans expect to get the keys in February 2027 and play the 2027 NFL season there. The team's October 2026 update described the building as four months from substantial completion.
How big is it?
About 1.8 million square feet per Construction Dive's November 2025 report, with about 60,000 seats.