EverBank Stadium of the Future: Inside Jacksonville's $1.4 Billion Renovate-in-Place
Most big stadium jobs start with a cleared site and a calendar the contractor controls. The Stadium of the Future in Jacksonville has neither. The AECOM Hunt–Barton Malow joint venture is renovating and expanding EverBank Stadium, which opened in 1995, while the Jacksonville Jaguars keep playing in it through the 2026 season. Barton Malow puts the scope at 1,886,887 square feet of renovation and expansion, with construction that started in February 2025 and is scheduled to finish in August 2028.
That constraint shapes almost every decision on the job. The scope includes a shade canopy on new perimeter steel trusses, 360-degree concourses that Barton Malow says are four times wider than the existing circulation, a seating bowl that HOK says holds 63,000 and expands to 70,000, and rebuilt clubs, suites and back-of-house. On an empty site, that is a large but conventional stadium program. Delivered around an occupied building with gameday hand-backs, it is a phasing exercise first and a construction job second.
The money: $1.4 billion, and probably more
NFL owners approved the deal on October 15, 2024. Spectrum News 13's report that day laid out the split: a $1.25 billion construction budget shared between the city and the team, plus $150 million the city pays for deferred maintenance to get the building ready. That brings the city to about $775 million and the Jaguars to $625 million, roughly a 55/45 split of the $1.4 billion total. The city said it would not levy new taxes for its share. The agreement includes a 30-year lease and a non-relocation agreement, and the Jaguars agreed to cover construction cost overruns.
The Jacksonville Daily Record reported on March 1, 2026 that the City Council legislation (Ordinance 2024-0904, approved June 25, 2024) is a $1.45 billion package that also includes $56 million for riverfront parks and the adjacent flex field.
The overrun question is live. The Daily Record reported on January 9, 2026 that the city's chief administrative officer, Mike Weinstein, told council in December 2025 that the project had about $100 million in overruns since construction started. The Jaguars declined to confirm that figure. Team president Mark Lamping said on December 15, 2025 that the team is "generally responsible for cost overruns" but that overruns caused by a third party could be discussed, and that "the costs change literally every hour." By February 25, 2026, Lamping told the Daily Record plainly: "We will be over $1.4 billion." Under the deal as described by Weinstein, the team covers added costs that are not caused by city delays.
What the permit record shows
For contractors, Jacksonville's permit filings are more useful than the headline number, because they show construction value by package and date. According to the Jacksonville Daily Record (March 1, 2026):
- The foundation permit was issued December 10, 2024.
- The largest permit up to that point, IFC 3 at $532.14 million, was issued September 11, 2025.
- Permits issued before February 2026 totaled almost $640.14 million.
- IFC 4, described by the city as the final and largest permit, was issued February 27, 2026 at $696.5 million.
- A fire sprinkler package of almost $6.8 million was still under city review.
IFC 4 alone pushed permitted construction value past $1.33 billion. It covers eight levels and 652,735 square feet of renovation: field-level club spaces, more private suites, new mechanical, electrical, lighting and fire alarm systems, low-voltage systems including Wi-Fi and DAS, and renovated restrooms, concessions and front- and back-of-house spaces. The contractor named on it is the Hunt Construction–Barton Malow joint venture.
Permit value is not the same thing as total project cost. It leaves out soft costs, furniture and equipment, and owner-direct scope. But it is public, dated and checkable, and it tells subcontractors when the big MEP and interiors packages are moving. Anyone tracking similar public work can watch the same signals on our bid boards.
Who is on the team
Barton Malow's project page lists the AECOM Hunt–Barton Malow joint venture as construction manager, selected after the NFL's unanimous approval. HOK is the architect. Construction Review Online's February 2026 coverage reports that Impact Development Management serves as the Jaguars' development advisor and representative, and that Rider Levett Bucknall handles cost control and financial monitoring. None of the project releases we reviewed named the structural or MEP engineers, so we have not listed them.
The same Construction Review Online piece cites an August 2023 study commissioned by the Jaguars that estimated about 17,700 to 18,000 construction-related jobs over the life of the project. That is a cumulative study estimate, not a headcount, and officials have not published a daily on-site workforce figure.
For how this job compares with the Titans, Bills and Browns projects, see our sports stadium construction overview and the New Nissan Stadium project page.
What is standing today
On August 20, 2026, ahead of a preseason game against Carolina, the Jaguars gave the first public look at finished areas. News4JAX reported wider concourses with new gray topping over the old concourse slab, new entry gates and a new stairwell, and breezeways and a shroud designed to pull air through the corners and concourses, with heated air leaving through vents in the roof. The team says every seat will be shaded when the job is done.
Stadium lighting has moved from the risers above the bowl to the top rows, and the four existing banks of field lights will later be integrated into the roof. That is a prerequisite move. Upper-bowl work and truss erection can't proceed with fixtures and conduit in the way.
News4JAX reported more than 1.5 million work hours logged and about 20,000 seats removed. The Daily Record put 2026 capacity at 42,465; AP's preseason coverage rounded it to 42,500 for two preseason and six regular-season home games. Construction Review Online reported partial in-bowl demolition for corner scenic lookout decks, upper-bowl renovations and field-level seating, and HOK said Grand Staircase Two in the northwest quadrant was due early in the 2026 season. The Daily Record reported the first of four planned grand staircases opened in October 2025.
The canopy and roof steel
The signature system is a translucent shade canopy carried on steel trusses erected around the outside of the existing structure. HOK and Barton Malow both say the canopy and landscaped green space are designed to cut heat retention by more than 70 percent.
The Daily Record reported in March 2026 that 75 steel beams were to be completed by August 2026 and that roof installation would begin in the first half of 2027. News4JAX said in August that roof steel is targeted for completion in early 2027. AP reported that once the trusses are in place, a compression ring will be central to raising the roof slowly, a step it described as "a year to 18 months away."
Erecting perimeter trusses around a building that still hosts NFL crowds is a rigging and hand-back problem before it is a structural one. Crane positions have to clear egress routes that must be restored before gameday, and any steel set over public areas has to be complete or protected before fans return. News4JAX reported that crews pause work four to eight hours before kickoff, and up to 72 hours before some games. Contractors bidding remaining steel packages can follow the underlying index on our steel price page.
The season calendar is the schedule
The phasing follows the NFL calendar:
- 2026: reduced-capacity home games in Jacksonville plus back-to-back London games at Tottenham Hotspur Stadium and Wembley, which HOK says created a two-week in-season construction window.
- 2027: NFL owners unanimously approved a one-year move to Camping World Stadium in Orlando at the league's March 2026 annual meeting, per AP (March 31, 2026). The Jaguars have 10 home games in 2027 including a preseason game; up to three could be in London, so Orlando likely hosts seven or eight. Orlando approved a $10 million incentive package to land the team.
- 2028: completion targeted for August, ahead of the 2028 season.
The 2027 vacancy matters more to this schedule than crew size. A full year of uninterrupted site access is when the roof lift, the rest of the bowl and the heavy concourse work can run without weekly hand-backs.
Trades and packages to watch
The IFC 4 permit is essentially the interiors and systems permit: eight levels of clubs and suites plus the MEP, fire alarm and low-voltage backbone. That points the next phase toward mechanical, electrical, plumbing, fire protection, drywall, millwork and food service, the trades that carry the most manpower on any stadium and will draw on North Florida's commercial labor pool. Firms sizing up the Florida market can use our contractor directory and state pages.
Why the job matters beyond Jacksonville
Many owners of older NFL venues face the same choice between replacement and renovation in place. Jacksonville is a current test of whether a deep renovation can hold budget and schedule with the tenant in the building, and the early evidence is mixed: the schedule is holding by the team's account, while the cost has already moved past the $1.4 billion headline. For contractors, the lesson applies to any occupied-building job, including the broader commercial construction market. Margin is won or lost in the hand-backs.
Frequently asked questions
Is the Jaguars stadium being replaced or renovated?
Renovated and expanded. The existing 1995 structure stays; the bowl, concourses, clubs and back-of-house are rebuilt, and a shade canopy goes on new perimeter steel trusses.
How much does the Stadium of the Future cost, and who pays?
The approved budget is $1.4 billion: about $775 million from the City of Jacksonville, including $150 million for deferred maintenance, and $625 million from the Jaguars. The team agreed to cover construction overruns not caused by the city. City officials reported about $100 million in overruns in December 2025, and team president Mark Lamping said in February 2026 the cost will be over $1.4 billion.
Who is building it?
The AECOM Hunt–Barton Malow joint venture is construction manager and HOK is the architect. Impact Development Management is the Jaguars' development representative and Rider Levett Bucknall handles cost control.
Where do the Jaguars play during construction?
At EverBank Stadium at reduced capacity in 2026 (about 42,465 seats) plus two London games, then at Camping World Stadium in Orlando for 2027.
When does it reopen and how big will it be?
Completion is scheduled for August 2028. HOK says the bowl will seat 63,000 and expand to 70,000 for college football and larger events.