ProBuildermuse Pro is liveMatched bid alerts from $10.99/mo.Get Pro
B
Buildermuse
Construction Projects

Harris Health John M. O'Quinn Hospital: $1.6B Houston Build, Contractors and Schedule

Mike Callahan·August 30, 2026·8 min read
Hospital construction. Representative image — not the Harris Health O'Quinn hospital.
Hospital construction. Representative image — not the Harris Health O'Quinn hospital. Photo: Arman / Pexels

Project Facts

constructionUnder Construction
Project
Harris Health John M. O'Quinn Hospital (LBJ campus replacement hospital)
Location
Houston, Harris County, Texas — Lyndon B. Johnson Hospital campus, northeast Houston
Project Type
Acute care replacement hospital — Level I trauma capable
Estimated Cost
$1.6 billion for the hospital, within Harris Health's larger $2.5 billion to $2.9 billion bond-funded facilities plan
Size / Scope
12 stories; approximately 1.2 million sq ft per Harris Health's project status page, reported at approximately 1.3 million sq ft in the groundbreaking announcement and subcontract filings; 390 private beds expandable to 450; 15 operating rooms plus a hybrid OR; rooftop helipad
Owner / Developer
Harris Health System (Harris County public hospital district)
General Contractor / CM
McCarthy Building Companies, Inc. (construction manager at risk)
Architect
HKS
Engineer of Record
Not publicly announced
Construction Start
May 9, 2024
Expected Completion
Certificate of Occupancy July 2028; first patients January 15, 2029
Published Aug 31, 2026Last updated Aug 24, 20266 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

Harris Health John M. O'Quinn Hospital: What a $1.6 Billion Trauma Center Build Looks Like at the Halfway Mark

There is a line on Harris Health's published schedule that tells you everything about how hospitals differ from every other kind of vertical construction. Certificate of Occupancy is July 2028. First patient is January 15, 2029.

Six months between a legally occupiable building and a patient in a bed. On an office tower or a stadium, CO is close to the finish line. On an acute care hospital, CO is when medical equipment installation, clinical validation, staff training, licensure and accreditation surveys begin. McCarthy Building Companies is not building a building here. It is building a machine that has to be commissioned before anybody trusts it with a trauma patient.

What is going up

The John M. O'Quinn Hospital is a 12-story acute care replacement for the aging Lyndon B. Johnson Hospital on the same northeast Houston campus. It carries 390 private beds with shell space to flex to 450, 15 dedicated operating rooms plus a hybrid OR, a rooftop helipad, and a full complement of emergency, diagnostics, lab, pharmacy, nuclear medicine, cardiology, and labor and delivery services. When it opens it becomes Harris County's third Level I trauma center.

Square footage is reported two ways in the public record. Harris Health's own project status page lists approximately 1.2 million square feet; the May 2024 groundbreaking announcement and the electrical subcontract filing both say approximately 1.3 million. The difference likely comes down to whether the podium, garage or central utility plant are counted. It matters if you are benchmarking, because $1.6 billion across 1.2 million square feet works out to roughly $1,330 per square foot, and across 1.3 million to roughly $1,230 — a $100 per square foot swing on nothing but a definition. Either way, both figures land in the range large urban acute care runs today, and both are a long way from the commercial cost benchmarks most contractors carry in their heads.

Per bed, $1.6 billion across 390 beds is about $4.1 million. That is the number hospital boards actually argue about.

The money

The hospital is $1.6 billion, funded inside Harris Health's larger bond-backed facilities plan, reported between $2.5 billion and $2.9 billion depending on which scope is counted. That plan also carries renovation of the existing LBJ facility, added capacity at Ben Taub Hospital, and three new health centers in northwest, southwest and eastern Harris County — meaning a substantial amount of work in this program is still in front of the bidding market.

The hospital picked up its name in January 2026 when the John M. O'Quinn Foundation committed $40 million to Harris Health's capital campaign, the largest gift the system has received.

Because Harris Health is a public hospital district, follow-on packages surface through public procurement rather than private negotiation. Contractors who want to see that work early should be watching public solicitation feeds — our bid board and public works coverage track that category — and can size up the Houston competitive field through the contractor directory.

Building next to a trauma center that never closes

The existing LBJ Hospital stays fully operational for the entire build, and the new tower connects back to it by an overhead pedestrian bridge that is under construction now. That single connection is the hardest coordination item on the job. You are tying a new 12-story structure into an occupied acute care facility whose emergency department cannot lose access, power, medical gas or ambulance routing for a shift, let alone a day.

Work is organized in three phases — H1 for site and structure, H2 for core and shell, H3 for interior build-out — with the central utility plant delivered on its own separate schedule, completing in Q4 2027. Splitting the CUP out is standard practice on large healthcare, and for good reason: the plant has to be online, tested and stable well before the hospital needs it for commissioning, and it usually feeds temporary services during construction. Tie it to the tower schedule and you have created a dependency that will cost you the whole project float.

The parking garage runs a third schedule again: construction use starting in 2027, public opening Q1 2029 alongside first patients.

Where the job stands in August 2026

The structure topped out on January 23, 2026 with the final steel beam set atop the 12-story frame. In April 2026, the campus marked completion of the exterior enclosure phase. As of this month:

  • More than 3.5 million construction man-hours logged across the hospital, garage and central utility plant.
  • Roughly 1,700 workers on site daily.
  • Lost time incident rate of 0.10, against a national construction benchmark in the 0.8 to 1.8 range.
  • Building envelope substantially complete; interior wall construction and MEP installation underway.
  • Elevator systems being installed.
  • Helipad and main entrance canopy structures finished.
  • Bridge connection to the existing LBJ Hospital in progress.
  • Medical equipment vendors performing field verification.

Two of those deserve a second look. An LTIR of 0.10 at 3.5 million man-hours is genuinely unusual — that is not a rounding artifact, it reflects a safety program that is working at scale on a congested site with 1,700 people on it.

And medical equipment vendors doing field verification 30 months before first patient is not early. It is exactly on time. Imaging suites, linear accelerators, sterile processing and OR booms all drive structural, electrical and shielding requirements that have to be resolved before walls close. Miss a field verification and you are cutting a slab you already poured.

The MEP is the job

On a hospital of this class, mechanical, electrical and plumbing typically runs 40 to 50 percent of construction value — our hospital construction cost breakdown puts HVAC and medical gas alone at 16 to 24 percent — and the O'Quinn packages reflect that. McCarthy awarded Fisk Electric, a Tutor Perini subsidiary, an electrical contract on a guaranteed maximum price basis valued at approximately $147 million, with the first phase at roughly $29 million. Fisk's scope covers core and shell plus tenant finish-out electrical and fire alarm for both the hospital tower and the podium. Work began in Q4 2024, with substantial completion of the entire electrical contract anticipated in Q4 2028 — three months after the building's CO date, which is precisely the kind of tail that healthcare commissioning generates.

Prefabricated bathroom pods are in the build, another common healthcare play: 390 private rooms means 390 near-identical wet stacks, and moving that repetition into a controlled shop takes labor off a crowded site and takes variability out of a scope where a leak behind a wall is a patient safety event.

The envelope has to meet Gulf Coast requirements — wind-borne debris and hurricane loading on a 12-story frame, with a rooftop helipad structure adding its own loading and vibration considerations above the topmost occupied floor.

The road to January 2029

The published milestones run:

  • October 2027 — building substantial dry-in.
  • Q4 2027 — central utility plant complete.
  • July 2028 — Certificate of Occupancy.
  • Q4 2028 — substantial completion of the electrical contract.
  • January 15, 2029 — first patient.
  • Q1 2029 — parking garage opens to the public.

Between now and dry-in, the work is interiors and systems: framing, in-wall rough-in, medical gas, headwalls, pod setting, ceiling coordination and the endless above-ceiling sequencing that makes hospital MEP its own discipline. After dry-in, the job turns into a commissioning exercise — air balance, pressure relationships between clinical zones, redundancy testing on emergency power, and the validation packages that regulators actually read.

If the schedule holds, LBJ's replacement opens 56 months after the May 2024 groundbreaking. For a 1.2-million-square-foot Level I trauma hospital built next to a working one, that is a competitive number.

Questions readers ask

Who is building the John M. O'Quinn Hospital? McCarthy Building Companies as construction manager at risk, with HKS as architect. Fisk Electric holds an electrical contract valued at approximately $147 million on a GMP basis.

How much does it cost? $1.6 billion for the hospital itself, inside a broader Harris Health facilities plan reported between $2.5 billion and $2.9 billion.

When does it open to patients? Certificate of Occupancy is targeted for July 2028 and first patients for January 15, 2029. The six-month gap covers medical equipment installation, clinical validation, staffing and licensure.

Does the existing LBJ Hospital close during construction? No. It remains fully operational throughout, and the new tower will connect to it by an overhead pedestrian bridge now under construction.

How many beds and operating rooms? 390 private beds with shell space to expand to 450, plus 15 operating rooms and a hybrid OR.

MC

Mike Callahan

20-Year General Contractor

More from Mike Callahan
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free