ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Construction Projects

Meta Hyperion Data Center, Louisiana: Cost, Contractors, and the 5 GW Power Build

Danny Reeves·August 27, 2026·Updated October 29, 2026·10 min read

Share this with your estimator.

A large data center. Representative image, not Meta's Hyperion campus.
A large data center. Representative image, not Meta's Hyperion campus. Photo: Peter Xie / Pexels

Project Facts

constructionUnder Construction
Project
Meta Richland Parish Data Center (Hyperion)
Location
Richland Parish, Louisiana
Project Type
Hyperscale AI data center campus
Estimated Cost
More than $50 billion invested in the Richland Parish region (Meta, July 13, 2026), up from $10 billion at announcement in 2024 and $27 billion in October 2025
Size / Scope
Nearly 10 million sq ft (Construction Dive, July 2026) and 5 GW of compute capacity (Meta)
Owner / Developer
Meta Platforms, Inc.
General Contractor / CM
DPR Construction, Turner Construction Company and Mortenson, all three named by Meta. Accounts differ on which firm is delivering which phase.
Architect
Not publicly announced
Engineer of Record
Not publicly announced
Construction Start
December 2024
Expected Completion
Not publicly announced
Published Aug 28, 2026Last updated Oct 29, 20267 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

Most megaprojects in this country are fighting to hold scope. Meta's Richland Parish campus in northeast Louisiana has done the opposite twice.

Meta's 2024 plan was a $10 billion data center. In October 2025 that became $27 billion. On July 13, 2026, Meta announced an investment of more than $50 billion in the Richland Parish region and 5 gigawatts of compute capacity, with over 7,500 jobs at peak construction. Construction Dive's July 15, 2026 report puts the campus at nearly 10 million square feet at full build. Meta's project page says the site will deliver over two gigawatts of compute capacity for training its open-source language models.

For contractors, a project that grows fivefold in under two years is a different animal from one that holds a fixed budget. Bid lists reopen, trade packages get re-scoped, and the labor draw keeps climbing.

How the Number Got Here

Date Committed investment Source
2024 (ground broken December 2024) $10 billion Construction Dive, July 2026
October 2025 $27 billion Construction Dive, July 2026
July 2026 More than $50 billion Meta, July 13, 2026

Meta's July 2026 statement puts peak construction at over 7,500 jobs and says the campus will support 1,000 operational jobs once complete. Do not read the $50 billion as a building cost. Meta says it will pay the full costs of the energy, water, and related infrastructure, and the figure covers generation, transmission, and IT hardware alongside the shells. Dividing $50 billion by 10 million square feet produces a number no estimator should carry into a bid.

For a building-only benchmark, Gordian's RSMeans data, reported by Building Design+Construction on April 24, 2026, puts a one-story data center building at $505 per square foot at the Q1 2026 national average. JLL's 2026 Global Data Center Outlook forecasts the 2026 global average shell-and-core cost at $11.3 million per megawatt. Our data center construction cost per square foot and per MW guide explains both, and the data center cost guide adjusts them by state.

There is no published completion date for the full campus. An earlier version of this article cited a 2026 to 2031 construction window from Entergy. We could not find that in Entergy's materials or the reporting we checked, so it has been removed.

Three General Contractors on One Campus

Meta's project page names three general contractors: Mortenson, DPR Construction, and Turner Construction Company.

Who is doing which phase is less clear than earlier coverage suggested. Construction Dive reported on July 15, 2026 that, according to Meta, DPR is building the first part of the project and Turner and Mortenson are the general contractors for the expansion. Turner told Construction Dive that Turner and Mortenson are delivering the first phase. Construction Dive reported both accounts without settling them. If you are chasing a package, ask each GC directly what scope it holds.

Running three national GCs on one campus is uncommon even at hyperscale. The likely reason is capacity. No single builder has the staff, bonding, and subcontractor bench to absorb a fivefold scope increase without becoming the constraint. Splitting the work buys parallel capacity and three separate subcontractor networks.

The cost is coordination. Three GCs on one site means three logistics plans, three badging and safety programs, three laydown and crane strategies, and three sets of demands on the same regional concrete supply, aggregate haul routes, and craft labor pool. Someone on the owner's side has to referee all of it. Our piece on data center foundations and concrete supply covers why batch plant capacity is often the first thing to bind on a rural campus.

For a subcontractor, there are three front doors. Prequalifying with DPR does not put you on Turner's or Mortenson's list. If you want work on this campus, chase all three.

The Power Project Inside the Building Project

The construction story people miss is that Meta is also funding what amounts to a utility program around the campus, delivered by Entergy Louisiana.

According to Construction Dive (July 2026) and ENR (April 2, 2026), the agreement with Entergy Louisiana covers:

  • Seven new natural gas-fueled power plants totaling more than 5.2 GW, per ENR
  • About 240 miles of new 500 kV transmission lines
  • Battery storage at three locations

ENR reported that those seven plants come on top of three previously approved units, for 10 in total. The first three were approved by the Louisiana Public Service Commission on a 4-1 vote on August 20, 2025, as three 754 MW combustion-turbine plants totaling 2,262 MW and about $3.2 billion, according to KNOE (Aug. 20, 2025). The seven new plants are still an application. WRKF (April 21, 2026) reported that the commission voted on April 15, 2026 to expedite the filing, that the application puts the gas plants alone at more than $16 billion and the full package at more than $21 billion, and that the final vote is scheduled for November 18, 2026. Meta says it will help fund up to 2.5 GW of clean and renewable energy and will match 100% of the site's energy use with clean and renewable energy.

Separately, Switchgear Magazine reported on August 7, 2025 that Entergy is building a $1.2 billion, 100-mile 500 kV transmission line for the project, expected to be operational by December 2026. An earlier version of this article attached the $1.2 billion to the 240-mile program. That was wrong. The $1.2 billion line is a separate, earlier item.

On customer costs, Meta's project page says it expects $2.65 billion in customer savings over 20 years through the Entergy partnership and has contributed $215 million to Entergy's low- and fixed-income bill assistance and energy efficiency programs. ENR's April 2026 report describes that total as about $2 billion in new savings from the second agreement, plus $650 million in previously announced benefits.

Read that list as a construction scope rather than a policy announcement. Seven gas plants are seven industrial projects with their own boilermaker, millwright, and pipefitter demand. Two hundred forty miles of 500 kV means transmission structures, foundations, right-of-way clearing, access roads, stringing crews, and substation work at both ends. Three battery sites mean civil pads, containerized equipment, and medium-voltage collection. None of that is data center work, and all of it competes for the same crews and crane fleet in the same part of the state.

The conductor content on hundreds of miles of high-voltage line and the switchgear content on a 5 GW campus put real exposure on metals pricing over a multiyear build. Track it against the copper index rather than a one-time bid assumption.

Cooling and What It Does to Mechanical Scope

Meta's project page describes a closed-loop system that circulates a glycol mixture through the data halls, with heat removed mainly through dry cooling for most of the year (datacenters.atmeta.com, accessed Oct. 29, 2026).

For mechanical contractors, closed-loop glycol with dry cooling shifts scope away from evaporative equipment, cooling towers, and heavy make-up water systems. It shifts toward glycol piping distribution, dry cooler arrays, pumping, and controls. It also avoids a water-use fight that has slowed comparable projects elsewhere. The trade-off is more electrical load and more heat rejection surface area in exchange for less water.

Where 7,500 Craft Workers Come From

In a rural parish, most of a 7,500-person peak workforce has to travel in. Meta has put money into the gap:

  • Louisiana is one of four pilot locations for Meta's $115 million America's Workforce Academy, according to Construction Dive.
  • Meta gave $5 million to Louisiana Delta Community College, which Meta describes as the largest gift in the college's history.
  • All graduates of Richland Parish high schools, starting with the class of 2026, are eligible for full scholarships for any data center-related trade certificate or course, per Meta.
  • Turner and DPR co-launched a Richland Parish Workforce Development Cohort with Louisiana Delta Community College, according to Meta.
  • Meta reports that enrollment at the University of Louisiana Monroe's construction management school is up 37% year over year.

Whether short training programs can produce enough qualified craft workers is a fair question, and contractors on the ground will answer it before the trade press does. What is not in question is that a 7,500-worker peak in a parish this rural has to produce part of its own labor supply. Our guide to data center trades in demand covers which crafts are tightest, and regional labor effects show up in our state construction dashboards.

Local Spend and the Front Door for Subcontractors

Meta reports more than $1.6 billion contracted with local Louisiana businesses since construction began. It has made Source Louisiana the default platform for companies looking to work at the site. For a Louisiana sub, that platform is the most useful fact in this article, because it is where work surfaces.

Meta also reports more than $1 billion in local infrastructure improvements. Where public agencies procure that work, it is competitively bid heavy-civil and utility scope, not private hyperscale scope. Firms that will never win a data center package can still win road and utility work around the campus, and public solicitations show up on our bid board.

What to Watch

Whether another GC gets added. Meta went from one named builder to three as the investment grew. If the campus expands again, construction capacity, not money, is the constraint.

The transmission schedule. The campus cannot run past its interconnection. If the 500 kV program slips, energization dates slip with it, and building shells finish ahead of power.

Regulatory decisions. Meta's cost share, the customer-savings forecast, and the gas plant approvals all run through the Louisiana Public Service Commission. The commission's final vote on the seven-plant expansion is scheduled for November 18, 2026, per WRKF. Until that vote, the 5 GW figure is a plan, not a permitted scope. A regulatory reversal is a schedule event for contractors, not just a headline for ratepayers.

FAQ

How much is Meta investing in the Richland Parish data center?

More than $50 billion in the Richland Parish region, according to Meta's July 13, 2026 announcement. The plan was $10 billion in 2024 and $27 billion in October 2025, per Construction Dive. The total covers energy and related infrastructure and IT equipment, not just buildings.

Who are the general contractors on Meta Hyperion?

Meta names DPR Construction, Turner Construction Company, and Mortenson. Construction Dive reported in July 2026 that Meta says DPR is building the first part and Turner and Mortenson the expansion, while Turner says Turner and Mortenson are delivering the first phase.

How many construction workers will the Meta Louisiana campus need?

Meta says over 7,500 jobs at peak construction and 1,000 operational jobs once the campus is complete.

What power infrastructure is being built for the campus?

Three gas plants totaling 2,262 MW were approved in August 2025 (KNOE). Seven more totaling more than 5.2 GW (ENR, April 2026), about 240 miles of new 500 kV transmission lines, and battery storage at three locations are in an application the Louisiana Public Service Commission is scheduled to vote on November 18, 2026 (WRKF). Separately, Entergy is building a $1.2 billion, 100-mile 500 kV line expected online by December 2026, per Switchgear Magazine.

How do subcontractors get work on the Meta Richland Parish project?

Meta has made Source Louisiana the default platform for companies looking to work at the site, and reports more than $1.6 billion contracted with Louisiana businesses so far. Prequalify separately with each of the three GCs.

How is the Meta Hyperion campus cooled?

Meta describes a closed-loop system circulating a glycol mixture through the data halls, with heat removed mainly through dry cooling for most of the year.

DR

Danny Reeves

Master Plumber & Shop Owner

More from Danny Reeves→
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free