New Terminal One at JFK was supposed to open in 2026. It will not. The terminal company now expects first passengers in the first quarter of 2027, according to a September 15, 2026 report in The Points Guy, after earlier targets of June 2026 and then November 2026.
The building itself is largely up. What is left is the part of a terminal job that rarely makes the news: systems testing, operational readiness with airlines and concessionaires, and the sequencing that lets an operating airport hand passengers into a new building. This page covers what is being built, who is building it, how the money works, and what the delay means for the trades still on the job and the ones waiting for Phase B.
An earlier version of this article described the opening date as disputed between the Port Authority and a Bloomberg report, named a structural engineer and the terminal company's chief executive, and listed MWBE payment totals and monthly outreach sessions we could not trace to the sources we were able to retrieve. Those items have been removed or replaced with figures from the Port Authority, Carlyle, International Airport Review, Simple Flying and The Points Guy, each dated below.
What Is Being Built
The Port Authority of New York and New Jersey's project page describes New Terminal One as a 2.6 million-square-foot terminal, the largest standalone international terminal in the country, with 23 gates at completion, 22 of them sized for widebody aircraft. International Airport Review, reporting on the terminal's first ESG report on June 12, 2026, put the site at 134 acres and the design capacity at up to 23 million passengers a year.
The same Port Authority page lists:
- More than 300,000 square feet of retail, dining and lounge space at completion
- 13,000 rooftop solar panels, which the agency calls New York City's largest solar array
- 33,000 tons of structural steel in Phase A, which it compares to five Eiffel Towers
- 10,000 total jobs, including 6,000 union construction jobs
The size number has grown since the project was announced. Construction Dive's December 14, 2021 report and Carlyle's September 8, 2022 groundbreaking release both described a 2.4 million-square-foot terminal. Current Port Authority materials use 2.6 million.
The delivery is phased. The Port Authority page describes Phase 1 as the new arrivals and departures halls plus the first 14 gates. The Points Guy reported in September 2026 that the first phase will open with 13 gates plus one temporary gate, and that a second, nine-gate phase follows once the existing Terminal 1 is demolished. Simple Flying's June 15, 2026 report described the remaining gates arriving in two steps: five more in 2028 and the last four in 2030, when the terminal is fully complete.
Who Is Building It
This is not a Port Authority-built terminal. Carlyle's groundbreaking release names four project sponsors: Ferrovial, Carlyle, JLC Infrastructure and Ullico, with Ferrovial providing overall oversight. Anchor airlines named at the time were Air France-KLM, Etihad Airways and LOT Polish Airlines. Construction Dive reported in 2021 that the private partners would fully finance the terminal, with the Port Authority covering supporting infrastructure such as roads and utilities.
On the construction side, Carlyle's release says AECOM Tishman leads construction and design, and Gensler is the architect. Construction Dive described AECOM Tishman and Gensler as the design-build team. We could not confirm the names of the structural, MEP or specialty engineers from the sources reviewed, so they are not listed here.
Carlyle called the financial close "the largest private investment ever committed to a U.S. airport terminal," and the Port Authority describes the $9.5 billion capital commitment as the largest public-private partnership in the U.S.
How the Financing Changes the Pressure on Schedule
Most big U.S. terminals are paid for with airport revenue bonds backed by an airport system, plus passenger facility charges and federal grants. Our airport terminal construction spending breakdown walks through those sources. New Terminal One is different: it is a privately financed project carrying its own debt.
Simple Flying reported on June 15, 2026 that the terminal had about $5.9 billion in bonds outstanding and more than $6 billion in total borrowings, backed by a $500 million ramp-up reserve and $250 million in available credit lines. The same report said Moody's kept the rating at Baa3, the lowest investment-grade rating, but moved the outlook from stable to negative, citing construction delays and lower-than-expected demand at opening. International Airport Review reported that the terminal had issued more than $3.9 billion in green bonds across 2024 and 2025.
For a subcontractor, the takeaway is practical. Debt service does not wait for an opening day, and revenue from airline fees and concessions does not start until passengers do. That pressure tends to show up downstream as compressed testing windows, overtime requests and close scrutiny of any trade that is holding up turnover. If you are pricing late-stage or Phase B work on a privately financed terminal, read the schedule and liquidated damages language closely.
Why the Opening Slipped
The Points Guy quoted the terminal company as saying it is completing construction and preparing for operations with its airline partners and concessionaires, and that "we want to ensure that all systems and processes are well-tested and prepared to deliver on our commitment." The report did not point to a single construction problem.
That matches how large terminals usually finish. Once the shell is closed in, the critical path moves to systems that have to be installed, integrated and proven in order:
- Baggage handling. An in-line checked baggage system with explosive detection screening has to run under realistic loads, with controls and power stable, before it can be accepted.
- Passenger boarding bridges, preconditioned air and ground power. Each gate's equipment has to be set, energized and tested against aircraft on the apron, which needs airside access and coordination with live operations.
- Life safety and security. Fire alarm, smoke control, access control and CCTV have to work together and pass inspection. Newark's Terminal A, also a Port Authority airport, pushed its opening from December 8, 2022 to January 12, 2023 after last-minute issues with its fire alarm and security systems, The Points Guy reported on January 5, 2023.
- Concessions. More than 300,000 square feet of retail, food and lounge space means many separate fit-outs with their own designers, contractors and inspections, all competing for hoists, freight elevators and inspectors.
None of that is visible from the Van Wyck, and all of it can move an opening date.
Building Inside an Operating Airport
The New Terminal One site sits on the footprints of the former Terminals 2 and 3, next to a Terminal 1 that is still operating. The Points Guy reported that the old Terminal 1 is slated for demolition once the first phase opens, and the second phase of gates goes up in its place.
That sequence is the hard part of the back half of this job. After the first phase opens, passengers will be using one part of the complex while demolition and new construction continue next door. For trades, that means:
- Badging and background checks for every worker who needs access to secure areas, with lead time built into crew ramp-ups
- Restricted delivery windows and tight laydown, with material staged through airport-controlled access points
- Temporary partitions, egress and utilities that change as each zone is handed over
- Night work for tie-ins near active gates and baggage systems
The Port Authority says the project is being built with 6,000 union construction jobs, and Carlyle's release set a 30% goal for minority- and women-owned business participation. Bidders should expect project labor agreement terms and MWBE reporting in subcontract packages.
What It Means for Contractors
First, Phase B is still ahead. A nine-gate addition plus demolition of an operating terminal will generate demolition, foundation, steel, envelope, MEP, baggage and boarding bridge packages into the late 2020s. Full completion is targeted for 2030.
Second, material costs on the remaining work are higher than when the job was priced. The BLS producer price index for structural steel shapes was up 15.0% year over year in September 2026, and the index for copper wire and cable was up 30.8%. Those are index changes, not dollar prices, but they show the direction of the market. Our steel price outlook tracks the steel side in more detail.
Third, a union site of this size affects the regional labor market. BLS data for 2025 put the construction industry's union membership rate at 11.1% nationally, with median weekly earnings of $1,585 for union members versus $1,132 for nonunion workers. Our union vs. non-union wage comparison has the full breakdown.
JFK is also not the only large terminal program competing for the same specialty trades. Chicago's O'Hare Concourse D is in steel erection, and our overview of ACI-NA's airport needs estimate and the biggest terminal programs covers the rest of the national pipeline.
What to Watch
- A firm first-phase opening date. As of mid-September 2026 the terminal company was saying the first quarter of 2027, without a specific day.
- The start of Terminal 1 demolition, which unlocks the second phase of gates.
- Moody's outlook. The negative outlook reported in June 2026 will be reviewed against actual opening and traffic.
- Phase B procurement. Public solicitations tied to JFK redevelopment show up on Buildermuse's bid board; much of the subcontract work on a private terminal is let directly by the design-builder.
FAQ
How much does New Terminal One at JFK cost?
The Port Authority of New York and New Jersey describes a $9.5 billion capital commitment, the largest public-private partnership in the U.S. The terminal is privately financed. Simple Flying reported in June 2026 that it had about $5.9 billion in bonds outstanding and more than $6 billion in total borrowings.
Who is the contractor on JFK New Terminal One?
AECOM Tishman leads construction and design, with Gensler as architect, according to Carlyle's September 8, 2022 groundbreaking release. Construction Dive described the two as the design-build team. The project sponsors are Ferrovial, Carlyle, JLC Infrastructure and Ullico.
When will New Terminal One open?
The first phase was originally targeted for 2026, later reported as November 2026 at the earliest, and is now expected in the first quarter of 2027, according to The Points Guy's September 15, 2026 report. Full build-out is targeted for 2030.
How many gates will New Terminal One have?
23 gates at completion, 22 of them widebody, according to the Port Authority. The first phase opens with 13 gates plus one temporary gate, per The Points Guy, and the remaining gates are built after the existing Terminal 1 is demolished.
How big is New Terminal One?
About 2.6 million square feet on a 134-acre site, with more than 300,000 square feet of retail, dining and lounge space. Phase A used 33,000 tons of structural steel, according to the Port Authority.
How many construction jobs does the project support?
The Port Authority lists 10,000 total jobs, including 6,000 union construction jobs. The project set a 30% MWBE participation goal at groundbreaking.


