ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Construction Projects

O'Hare Concourse D Construction: $1.455B GMP, Contractors

Sarah Torres·August 26, 2026·Updated October 18, 2026·9 min read

Share this with your estimator.

An airport concourse. Representative image, not O'Hare Concourse D.
An airport concourse. Representative image, not O'Hare Concourse D. Photo: Zak Chapman / Pexels

Project Facts

constructionUnder Construction
Project
The New Concourse D (Satellite Concourse 1), O'Hare International Airport
Location
Chicago, IL
Project Type
New satellite airport concourse, construction manager at risk
Estimated Cost
$1.455 billion guaranteed maximum price, at least $21 million under the approved budget (City of Chicago, June 26, 2026). Reported at groundbreaking as about $1.3 billion for the concourse plus about $300 million in related infrastructure (Construction Dive, August 2025). Part of the City's $8.78 billion ORDNext program.
Size / Scope
About 580,000 sq ft (590,000 in 2025 groundbreaking coverage); 73 ft tall over three levels; 19 narrowbody gates, 18 of which can combine into nine widebody positions; 20,000+ sq ft of lounges; 30,000 sq ft of retail and dining
Owner / Developer
City of Chicago, Chicago Department of Aviation
General Contractor / CM
AECOM Hunt Clayco Bowa joint venture (construction manager at risk)
Architect
Skidmore, Owings & Merrill, with Ross Barney Architects and Juan Gabriel Moreno Architects (JGMA)
Engineer of Record
Arup (named on the design team)
Construction Start
August 18, 2025 (site preparation began in 2023)
Expected Completion
Late 2028
Published Aug 27, 2026Last updated Oct 18, 20266 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

O'Hare's new Concourse D has a price ceiling. On June 26, 2026, the City of Chicago announced that the Chicago Department of Aviation had finalized a guaranteed maximum price of $1.455 billion with AECOM Hunt Clayco Bowa, the joint venture building the 19-gate concourse, and that the number is at least $21 million below the approved budget.

The city calls Concourse D the largest new passenger facility at O'Hare in more than 30 years. It is the first major phase of ORDNext, the city's $8.78 billion modernization of the airport's core terminal facilities, and it is the part of that program that is actually in the ground. A 14-story tower crane topped out over the site in mid-July 2026, steel for the Midfield Cooling Plant was scheduled to start at the end of July, and Concourse D steel erection was scheduled to begin in August.

An earlier version of this article dated the GMP announcement to May 2026 and linked to a "record $28 billion" airport spending figure we could not source. The GMP date has been corrected to June 26, 2026 from the city's release, and the spending link now points to sourced Census data.

What Is Being Built

Concourse D, also called Satellite Concourse 1, is a three-level building of about 580,000 square feet, according to a June 4, 2026 report in the Daily Commercial News (ConstructConnect). Groundbreaking coverage in August 2025 used 590,000 square feet. The building is 73 feet tall and has a 40-foot atrium at its north end that connects the three levels.

The gate layout is the detail contractors should notice. Construction Dive reported at groundbreaking that the concourse has 19 narrowbody gates, and 18 of them can be combined into nine widebody positions. Swing gates like that drive apron geometry, boarding bridge placement and reach, and the utility and fuel systems under the pavement, so the flexibility has to be built in from the start.

Passenger space includes more than 20,000 square feet of lounges, 30,000 square feet of retail and dining, and a 450-square-foot children's play area, according to Construction Dive. The city's June release says the design uses a series of tree-like columns that branch out to carry a 150-foot-wide long-span roof, a reference to O'Hare's original name, Orchard Field.

The scope reaches beyond the building. Groundbreaking materials described about $300 million in related infrastructure, including a new central cooling facility in the middle of the airfield and pavement and utility work sized for a future second satellite concourse. The city's June release says the Midfield Cooling Plant will provide air conditioning and chilled water to Concourse D and future facilities across the campus. The Chicago Department of Aviation's July 15, 2026 release says Concourse D will initially operate as an extension of Concourse C. For how airfield pavement is priced, as opposed to a concourse building, our piece on what a runway costs to build covers that side of airport work.

Who Is Building It

  • Owner: City of Chicago, through the Chicago Department of Aviation
  • Construction manager at risk: AECOM Hunt Clayco Bowa joint venture
  • Design: Skidmore, Owings & Merrill, with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA) and Arup
  • Program manager: Connect Chicago Alliance, named in the city's June 2026 release

The GMP and Why the Delivery Method Matters

Under construction manager at risk, the builder joins during design, prices the work as the drawings develop, and eventually commits to a guaranteed maximum price. Costs above the GMP are generally the CM's problem, subject to the contract's change and contingency terms.

The city's release says the GMP "reflects more than a year of collaborative planning" and that the builder was engaged during design "to identify constructability improvements, refine sequencing, optimize means and methods, and advance value-engineering opportunities before the final price was set." It was reached less than a year after construction officially started on August 18, 2025.

For contractors deciding whether to chase CMAR work or hard-bid public jobs, Concourse D is a useful case. The CM had input while the documents could still change and locked a number after foundations were well along, which limits how much unknown ground condition risk is left in the price. That is a different risk profile from a lump-sum bid on 100% documents. Our commercial construction cost per square foot guide has the broader cost context.

How the work is paid for matters too. The city says Concourse D and ORDNext are funded through airline rates and charges, landing fees and other airport revenues, with no state or local taxpayer dollars. That is the usual model for large hub terminals, and it ties the program's pace to agreements with the airlines. Our airport terminal spending breakdown explains how bonds, passenger facility charges and federal grants fit together.

Foundations, Then Steel

ConstructConnect reported on June 4, 2026 that more than 90% of the caissons were complete and about 35% of total foundation work was done as vertical construction began. The same report said a 195-foot tower crane was being prepared for installation; the aviation department's July 15 release said the 14-story crane had topped out the previous Sunday night and is visible across O'Hare's 7,200-acre campus.

The city's June release laid out the next steps: tower crane in July, Midfield Cooling Plant steel starting at the end of July, Concourse D steel erection in August, and steel and enclosure work continuing through the fall. It said work will continue into 2027 on foundations, steel, tunnel work and building systems.

From a trade perspective, that sequence means the ironworker curve is climbing now, with curtain wall, roofing, mechanical, electrical and fire protection ramping behind it. Steel prices matter on a job this size. The BLS producer price index for structural steel shapes was up 15.0% year over year in September 2026; that is an index change, not a dollar price. Our steel price outlook tracks the market.

Building Inside the Airfield

Concourse D is going up on the airfield, not on a landside parcel. Site preparation began in 2023, according to groundbreaking coverage, and three temporary gates were added to Concourse C ahead of the main work to hold capacity.

That location shapes how the job runs:

  • Access control. Workers who need unescorted access to secure areas must be badged and background checked, so crew ramp-ups have to account for processing time.
  • Crane coordination. A tower crane near active runways and taxiways requires coordination with the aviation department and air traffic control on height and operating limits.
  • Deliveries and laydown. Material moves through controlled access points, with tighter staging space than a typical commercial site.
  • Tie-ins. Connecting to an operating concourse pushes some work into overnight or low-traffic windows.

None of that shows up as a single line item. It shows up as lower productivity per shift and more general conditions cost, and it is why experienced airport subcontractors price differently from landside commercial work.

Labor and Participation

Construction Dive reported at groundbreaking that Concourse D is expected to create more than 3,800 construction jobs. Groundbreaking materials also said the wider O'Hare 21 capital program had reached 37% combined minority- and women-owned business participation as of May 2025. The city's June 2026 release said ORDNext is expected to create opportunities for W/MBE firms through prime contracts, lower-tier packages and mentorship relationships.

For electrical and mechanical subs, the competition for crews is real. Data center construction was running at an $84.95 billion annual rate in August 2026, up 73.2% from a year earlier, according to the Census Bureau, and it draws from the same pool of electricians and pipefitters. BLS put the national median wage for electricians at $30.38 an hour in May 2025.

Where Concourse D Fits in ORDNext

The order of work at O'Hare changed after a May 2024 agreement between Mayor Brandon Johnson and the airlines. Urbanize Chicago reported on September 10, 2024 that the new sequence is Satellite Concourse 1 first, then the O'Hare Global Terminal, then Satellite Concourse 2, with the Global Terminal expected in 2032 and the second satellite pushed to 2034. Those dates come from 2024 reporting and could move again.

The city's June 2026 release describes ORDNext as two new satellite concourses plus replacing Terminal 2 with the O'Hare Global Terminal. ConstructConnect reported that the second satellite, Concourse E, is planned as a 460,000-square-foot domestic facility west of Concourse D, linked by an underground tunnel.

Because Concourse D opens years ahead of the Global Terminal, it has to carry real gate capacity on its own from late 2028. That is part of why the swing-gate design matters.

For the bigger national picture, including JFK's privately financed New Terminal One, see our overview of ACI-NA's airport needs estimate and the largest terminal programs.

What to Watch

  1. Steel topping out and building enclosure, which the city said would continue through fall 2026.
  2. The Midfield Cooling Plant, which has to be running before the concourse's mechanical systems can be commissioned.
  3. Global Terminal procurement. That is the next large package in ORDNext, and the subcontract pipeline behind Concourse D.
  4. Public solicitations tied to ORDNext, which show up on Buildermuse's bid board.

FAQ

How much does O'Hare Concourse D cost?

The City of Chicago set a guaranteed maximum price of $1.455 billion on June 26, 2026, at least $21 million under the approved budget. At groundbreaking in August 2025 the project was described as about $1.3 billion for the concourse plus about $300 million in related infrastructure.

Who is building O'Hare Concourse D?

AECOM Hunt Clayco Bowa, a joint venture, is the construction manager at risk. Skidmore, Owings & Merrill leads design with Ross Barney Architects, JGMA and Arup. Connect Chicago Alliance is the ORDNext program manager.

When will Concourse D open?

The city says the project is on track for completion in late 2028.

How many gates does Concourse D have?

19 narrowbody gates, 18 of which can be combined into nine widebody positions.

What is ORDNext?

ORDNext is the City of Chicago's $8.78 billion modernization of O'Hare's core terminal facilities, as described in its June 2026 release. It includes two new satellite concourses and a new O'Hare Global Terminal replacing Terminal 2. Earlier city materials and press coverage used the name O'Hare 21 for the capital program.

How is Concourse D funded?

Through airline rates and charges, landing fees and other airport revenues, according to the city, with no state or local taxpayer dollars.

ST

Sarah Torres

Licensed Electrician & Safety Consultant

More from Sarah Torres→
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free