Part of "How It Gets Built" — Buildermuse's series on the machinery behind modern construction.
Every bridge pier, high-rise core, and 345 kV monopole in the country stands on something nobody will ever see again, and its price was set by a soil boring log drilled months before the contractor showed up. On Collin County, Texas bid tabulations, a 36-inch drilled shaft drew unit prices from $108 to $175 per linear foot on a 2018 letting and $155 to $250 per linear foot on a December 2020 letting, with 30-inch shafts at $195 to $245 and 48-inch signal-pole shafts at $302 to $452. The same diameter can double between two counties because one has rock at 20 feet and the other at 90. The spread between those numbers is the entire business of deep foundations.
An earlier version of this article carried unit prices for driven piles, CFA piles and micropiles attributed to Northeast and Northwest DOT tabulations, along with rig rental rates, mobilization costs and load-test prices. We could not re-verify those figures against the tabulations they cited, so they have been removed; what remains are the Texas numbers we could pull from the county's own bid sheets, and the engineering standards the industry actually builds to. This article covers how the four main systems get chosen, how a shaft and a pile get built, what the tests prove, and why the geotechnical report decides whether anyone makes money.
Four Ways to Reach Bearing
The choice among drilled shafts, driven piles, continuous flight auger (CFA) piles, and micropiles comes down to the soil profile, the load per element, whether the neighbors will tolerate vibration, how much room the rig has, and what the local contractor base builds cheaply.
Drilled shafts (caissons)
A drilled shaft is a hole bored with a rotary rig, filled with a rebar cage and concrete, and sized from 18 inches to 12 feet in diameter. FHWA's Drilled Shafts manual, Geotechnical Engineering Circular No. 10 (FHWA-NHI-18-024, 2018), is the reference the U.S. industry designs and inspects against. Shafts win when one element must carry a very large load, when bearing is on rock a driven pile would refuse against before design depth, and when vibration is unacceptable; a single 8-foot shaft socketed into rock replaces a dozen piles and their cap. The weakness is that a shaft is only as good as the hole, and the hole is invisible.
Driven piles
Driven piles — steel H-sections, steel pipe, and prestressed precast concrete — are manufactured off site and hammered in. The quality control is the driving record: every blow is counted, and capacity can be verified on the spot. Piles are the default in soft coastal soils and on highway bridges where DOTs hold decades of local driving data. They lose when rock is shallow, when overhead clearance is limited, and when anyone nearby owns a building with plaster walls.
CFA piles and micropiles
A CFA pile is drilled with a continuous hollow-stem auger and grouted through the stem as the auger withdraws, then a cage is pushed into the wet column. No open hole, no casing, no slurry, so production is fast, and CFA has become the workhorse of warehouse, mid-rise, and data center foundations in the Southeast and Mid-Atlantic. Its limits are diameter (rarely above 36 inches), depth (rig torque runs out near 100 feet), and quality that rests on automated grout-volume monitoring rather than anything an inspector can see. A micropile is a 5- to 12-inch drilled and grouted element with a high-strength bar at its center, built to FHWA's Micropile Design and Construction manual (FHWA-NHI-05-039). Micropiles are the tool for retrofit and underpinning work where a full-size rig cannot fit, and they are the most expensive per ton of capacity.
| System | Typical diameter | Typical depth | Best soil fit | Vibration | Capacity per element |
|---|---|---|---|---|---|
| Drilled shaft | 24 in to 12 ft | 30 to 250 ft | Rock socket, hard clay, mixed strata | Very low | 500 to 5,000+ tons |
| Driven H-pile / pipe pile | HP 10 to HP 14; 12 to 42 in pipe | 30 to 150 ft | Soft clay, sand, end bearing on dense layer | High | 50 to 300 tons |
| Precast concrete pile | 12 to 30 in square | 30 to 120 ft | Coastal sands, soft marine clay | High | 60 to 250 tons |
| CFA / auger cast | 12 to 36 in | 30 to 100 ft | Sand, silt, stiff clay without cobbles | Very low | 50 to 400 tons |
| Micropile | 5 to 12 in | 20 to 150 ft | Anything, including rubble and rock | Low | 30 to 200 tons |
Vibration often decides it in cities. Caltrans' Transportation and Construction Vibration Guidance Manual sets 0.5 inches per second peak particle velocity as the continuous-vibration threshold for modern industrial and commercial buildings, with tighter limits for older residential and historic structures. An impact hammer can exceed that within 50 to 100 feet in some soils, which is why Manhattan, Boston, and Seattle are shaft and CFA towns while rural interstate bridges remain pile-driving country.
How a Drilled Shaft Gets Built
Drilling and holding the hole
The rig — a Bauer BG, Soilmec, Liebherr, or Watson — advances with a soil auger, then a rock auger or core barrel as strata change. In dry cohesive soil the hole stands open. In anything else, the contractor oscillates temporary steel casing down ahead of the drilling or fills the hole with bentonite or polymer slurry to hold the walls. GEC 10 and most DOT specifications require slurry to test out before concrete — density, viscosity, pH and a sand content of no more than 4 percent sampled at the base — because sand settling on the bottom is the most common reason a shaft fails its load test.
Cleanout, cage, and tremie
The base is cleaned with a bucket or airlift until the owner's inspector confirms no more than about half an inch of sediment over half the base and no more than an inch and a half anywhere, the GEC 10 benchmark. The rebar cage — tens of tons of steel on a large bridge shaft, with CSL tubes tied inside — is set with the service crane, and concrete goes in through a tremie, an 8- to 12-inch pipe kept buried 5 to 10 feet in the rising concrete so the mix never touches slurry. A 7-foot by 150-foot shaft takes about 214 cubic yards, more than 20 trucks on a continuous schedule, because a tremie pour cannot stop.
Integrity testing
Crosshole sonic logging (CSL, ASTM D6760) sends an ultrasonic pulse between pairs of water-filled tubes; a delay flags a void or soil inclusion. Thermal integrity profiling (TIP, ASTM D7949) reads hydration heat through wires on the cage during the first 24 to 48 hours; cold spots mean missing concrete, and the method also shows cage position and cover, which CSL cannot. A growing number of state DOTs accept either method, and some specify TIP where they want cover verified.
How a Driven Pile Gets Built
Hammers, driving, refusal, and cutoff
Diesel impact hammers are ubiquitous on DOT bridge work; hydraulic hammers run quieter with controlled energy; vibratory hammers run a pile into sand quickly but cannot prove capacity, so an impact hammer finishes the drive. Before driving, a wave equation analysis (GRLWEAP is the industry standard) shows the hammer can reach the required capacity without overstressing the pile. The inspector then records blows per foot, and per inch near the end, against a driving criterion that names the hammer, stroke and required blow count for the nominal resistance. Practical refusal is typically 10 to 20 blows per inch over several consecutive inches; drive harder and you damage the pile. H-piles are shipped in mill lengths and spliced in the leads when the ground runs deeper, which is why DOT pay items separate "furnish" from "drive" and carry a splice item; when a pile makes capacity above planned cutoff, the extra is burned off.
Load testing
A pile driving analyzer (PDA, ASTM D4945) bolts strain gauges and accelerometers to the pile head and reads force and velocity on every blow; a CAPWAP analysis turns that into static capacity. Under the AASHTO LRFD Bridge Design Specifications, dynamic testing with signal matching lets the designer use a higher resistance factor than a driving formula alone, which means fewer or shorter piles. Static load tests (ASTM D1143), where a reaction frame and jacks load a pile to twice design, remain the gold standard and are priced as their own pay item. For big shafts, the Osterberg cell (ASTM D8169), a hydraulic jack cast into the shaft that pushes up and down against the shaft itself, is the only practical way to prove 3,000 or 5,000 tons.
What Deep Foundations Cost Per Foot
Public bid tabulations are the honest source for unit prices, and they are honest precisely because they vary. The drilled shaft figures below come from two Collin County, Texas tabulations for county road projects, with eight bidders each, under TxDOT Item 416. They are ranges across all bidders, not the low bid alone.
| Element | Unit price range, per linear foot | Source |
|---|---|---|
| Drilled shaft, 18 in | $47 to $80 (2018); $94 to $179 (Dec 2020) | Collin County bid tabs, projects 31595 (2018) and CCOL 3B (bid Dec 10, 2020) |
| Drilled shaft, 30 in | $195 to $245 | Collin County, CCOL 3B, Dec 2020 |
| Drilled shaft, 36 in | $108 to $175 (2018); $155 to $250 (Dec 2020) | Collin County bid tabs |
| Drilled shaft, 42 in | $180 to $241 | Collin County, 2018 |
| Drilled shaft, 48 in, traffic signal pole | $302 to $452 | Collin County, 2018 |
Those are North Texas prices in clay and shale, for short shafts under roadway and signal structures. Large bridge shafts socketed into rock, built under slurry or oscillated casing with CSL tubes and an O-cell, bid at multiples of those numbers; so do shafts on water or on sites where the rig has to be barged in. For driven piles, CFA and micropiles, the same rule applies: pull your own state DOT's bid tabulations for the items you are pricing, filter for similar scope and location, and read the spread between bidders. TxDOT's own estimating manual tells its engineers to treat average low-bid prices as a starting point adjusted for the project, not as a price, and that is good advice for a contractor too.
Three things to keep in mind when reading any such table. First, per foot is not per ton: a rock-socketed shaft carrying 3,000 tons can be cheaper per ton than an H-pile carrying 150, even at ten times the per-foot price. Second, mobilization is its own line: a large shaft rig with oscillator and a heavy service crane cost far more to move than a pile crane with leads and hammer, and a barge changes everything. Third, testing is its own budget: O-cell tests, CSL on every shaft, and a full-time third-party inspector are separate pay items on a bridge foundation line, and they are not small.
Production rates drive the price
The estimator's real question is not what the hole costs but how many days the rig sits. A crew on small shafts in dry clay finishes several a day; a crew on 8-foot slurry shafts into rock finishes one every couple of days, and a single bad hole can eat a week. Driven piles move faster when the ground cooperates: one crane and hammer can drive a string of H-piles in a shift, and CFA rigs place dozens of piles a day in sand and silt. Every one of those rates collapses when the ground differs from the borings, which is where the next section comes in.
The Geotechnical Report Is the Bid
Every number above is conditional on a report the owner commissioned from borings spaced 100 to 300 feet apart. The contractor bids on those borings, and what happens when the ground between them is different is the main thing a deep foundation contract is about.
Unit price versus lump sum
Public agencies bid deep foundations by the unit — dollars per linear foot of shaft or pile, with separate items for test piles, splices, rock sockets, obstructions, and load tests — and pay on measured quantity. If rock comes in 15 feet shallower than the borings suggested, the quantity underruns and the contractor spreads its fixed cost over fewer feet, which is why standard DOT specifications include a renegotiation trigger when a major item varies more than 25 percent from plan. Private owners and design-builders prefer lump sum, which pushes the risk onto the specialty sub, who responds by pricing a contingency, writing a geotechnical baseline into the proposal (the ASCE Geotechnical Baseline Report framework was built for tunnels and is increasingly borrowed for foundations), and demanding separate pay items for obstructions and rock.
Differing site conditions
On federal work, FAR 52.236-2 entitles the contractor to an equitable adjustment when subsurface conditions differ materially from what the contract indicated (Type I) or from what is normally encountered in that kind of work (Type II), provided notice is given before the condition is disturbed. Most state DOT and AIA-based contracts carry an equivalent clause. The practical rules are simple and often ignored: keep a daily log for every shaft or pile recording strata, water, and tooling changes, and send written notice the day the ground changes. The case law is full of contractors who hit a boulder field, kept drilling at a loss for a month, and lost on notice. Driven pile contracts manage the uncertainty with test piles driven ahead of production to set order lengths; shaft contracts use a technique shaft, built with the production method, to prove slurry, cleanout, and tremie procedure before the first real pour.
Who Does the Work, and Where It Is
The contractors and the labor
Keller North America, the U.S. arm of London-listed Keller Group, ranked first in ENR's deep foundations category on the 2025 Top 600 Specialty Contractors list, a position it has held since 2019 after folding Hayward Baker, Case Foundation, and McKinney Drilling into one name, per Keller's November 11, 2025 announcement. In its 2025 full-year results, Keller reported group revenue of £3.09 billion, North American revenue up about 5 percent against a roughly 2 percent decline in the broader U.S. construction market, and 120 data center projects completed in North America during the year. Malcolm Drilling, privately held in San Francisco, has held the second deep foundations spot on recent ENR lists, per its own announcements. Berkel & Company dominates auger cast work in the Southeast and Midwest; Nicholson Construction anchors the Northeast; Schnabel Foundation, Condon-Johnson, Anderson Drilling, and dozens of regional firms fill out the field. Heavy-civil generals such as Kiewit and Traylor often self-perform pile driving on bridges but subcontract large shafts.
Two union crafts split the field work. Pile drivers are chartered under the United Brotherhood of Carpenters — Pile Drivers Local 34 in the Bay Area, Local 56 in Boston, Local 2375 in Los Angeles — and handle rigging, setting, splicing, and cutting. Rig and crane operators belong to the Operating Engineers. The Bureau of Labor Statistics' May 2025 Occupational Employment and Wage Statistics, released May 2026, put pile driver operators (SOC 47-2072) at a national median of $35.24 per hour and a mean of $80,710 a year, with the 90th percentile at $124,600, and counted only 2,310 of them nationwide. Prevailing wage determinations for pile drivers in union markets run well above the BLS median once fringes are added; check the state or Davis-Bacon determination for the county before you price a crew.
Where the work is
Bridges are the steadiest demand: the IIJA replacement wave covered in our tracker of every major bridge project in the U.S. puts shafts or piles under nearly every pier. Data centers are the fastest-growing segment, as the concrete and foundation demands of hyperscale campuses push owners toward CFA piles and rammed aggregate piers by the thousand; Keller's 120 data center jobs in a single year is the clearest public measure of that. Transmission is the sleeper: a 345 kV or 500 kV monopole sits on a drilled pier several feet in diameter and tens of feet deep, and a single line carries thousands of them. Every substation dead-end structure sits on a drilled pier too.
Frequently Asked Questions
How much does a drilled shaft cost per foot?
On Collin County, Texas bid tabulations, 30-inch shafts drew $195 to $245 per linear foot and 36-inch shafts $155 to $250 on a December 2020 letting; a 2018 tab showed 36-inch shafts at $108 to $175, 42-inch at $180 to $241 and 48-inch signal-pole shafts at $302 to $452. Those are short shafts in North Texas clay. Large rock-socketed bridge shafts built under slurry or casing bid at multiples of those numbers, and your own state DOT's bid tabulations are the right source for your market.
Are driven piles cheaper than drilled shafts?
Per linear foot, usually: an H-pile is a manufactured section driven in minutes, while a shaft is a drilled, cased, caged and tremied hole. Per ton of capacity, often not, because one large shaft replaces many piles and their cap. Piles also lose where rock is shallow and where vibration limits such as Caltrans' 0.5 inch per second PPV threshold rule out an impact hammer.
What is the difference between CSL and TIP testing?
Crosshole sonic logging (ASTM D6760) sends ultrasonic pulses between access tubes after the concrete cures and finds anomalies inside the cage. Thermal integrity profiling (ASTM D7949) reads hydration heat during the first one to two days and evaluates the full cross-section, including cover outside the cage. Many agencies accept either.
How many drilled shafts can a crew build in a day?
Small shafts in dry cohesive soil run several per day per rig. Large slurry or oscillated shafts into rock run one every one to three days. The rate depends on diameter, depth, ground and whether casing or slurry is needed, which is why the geotechnical report, not the plan quantity, sets the bid.
What is a differing site conditions claim?
On federal contracts, FAR 52.236-2 gives an equitable adjustment when subsurface conditions differ materially from the contract documents (Type I) or from normal conditions for that work (Type II). Recovery depends on written notice before the condition is disturbed and on daily logs documenting what changed.
Who installs deep foundations?
Specialty contractors: Keller North America (ENR's top deep foundations firm in 2025), Malcolm Drilling, Berkel & Company, Nicholson, Schnabel Foundation, and a large regional field. Crews are union pile drivers from Carpenters locals and operating engineers on rigs and cranes; BLS counted 2,310 pile driver operators nationally in May 2025.
Your Action Item for This Week
Pull the last three bid tabulations your state DOT posted for bridge projects with drilled shaft or pile items and build a spreadsheet of unit prices by diameter and pay item. Compare the low bidder's foundation prices against the second and third; the spread tells you who read the boring logs. Then check live solicitations on Buildermuse for "drilled shaft," "pile," and "foundation" to see what is on the street now. The contractors winning this work price the geotech report, not the plan quantity.
More from the How It Gets Built desk
Edited by Ray Kowalski, Methods & Machines desk. New teardowns weekly.



