Part of "How It Gets Built", Buildermuse's series on the machinery behind modern construction.
A large data center is, by budget, an electrical project with a building wrapped around it. Cushman & Wakefield's 2026 Data Center Development Cost Guide, as summarized by CRE Daily on August 27, 2026, names power infrastructure as the single largest cost category in a greenfield build, and the equipment in that category is the slowest to arrive. The guide puts medium-voltage switchgear at 38 to 63 weeks from order to delivery, pad-mounted transformers at 68 to 113 weeks and generators at 60 to 100 weeks, and says some equipment now stretches past two years. For the biggest units at the utility end, Wood Mackenzie's second-quarter 2025 survey, reported by POWER magazine on January 2, 2026, put power transformers at an average of 128 weeks and generator step-up units at 144 weeks.
The practical effect is that the schedule for a data center no longer starts with a shovel. It starts with a purchase order, often signed before the general contractor is selected. This article walks through what the power gear is, the order it gets bought and installed, who carries the risk when it arrives late, and what the trades do while the building waits for its equipment.
What "Power Gear" Means on a Large Campus
The electrical scope on a hyperscale or large colocation campus follows one path from the utility fence to the server rack. Each step has its own equipment, its own lead time and its own trade.
The utility interconnection and substation
Power arrives at transmission voltage, and the first stop is a substation that the owner increasingly builds and pays for itself. A dedicated substation carries large power transformers, high-voltage breakers, and a control house. The transformers are the longest-lead equipment on the campus, and the 128-week average in Wood Mackenzie's survey means a transformer ordered today arrives roughly two and a half years later.
The interconnection approval itself can take longer than any piece of equipment. JLL reports grid connection waits of more than four years in primary data center markets. Regulators have noticed. On June 18, 2026, the Federal Energy Regulatory Commission issued six show-cause orders directing PJM, the Southwest Power Pool, the New York ISO, ISO New England, the California ISO and MISO to justify their existing large-load interconnection rules or propose reforms, per a National Law Review summary of the orders.
Medium-voltage distribution
From the substation, power moves at medium voltage through switchgear into the building's electrical rooms. A large facility needs many switchgear lineups, each a factory-assembled steel enclosure of breakers, bus, relays and metering. Cushman's 38 to 63 week range applies here, and Wood Mackenzie's survey put the switchgear average at 44 weeks in Q2 2025, per POWER. Prices have moved with demand: POWER, citing Wood Mackenzie, reports medium-voltage switchgear prices up 50% since 2021, and Cushman's guide reports switchgear costs up 60% between December 2021 and early 2026.
Transformers, more than once
Voltage steps down from transmission to medium voltage at the substation, then from medium to low voltage at unit substations or pad-mounted transformers beside or inside the building. The pad-mounted units are the 68 to 113 week item in Cushman's guide. A large campus needs a lot of them, so a delay on one model can hold up many electrical rooms at once.
UPS, batteries and generators
Every critical load sits behind an uninterruptible power supply with batteries sized to carry the load for the short interval it takes the generators to start and synchronize. The generators, large diesel units in weatherproof enclosures, are the 60 to 100 week item in Cushman's guide. How many a campus needs depends on its redundancy design: N+1 means one spare unit beyond what the load requires, and 2N means a full duplicate set.
The Procurement Sequence: Buy Before You Design
On a conventional commercial project, the general contractor buys equipment after the design is complete and the subcontracts are let. Lead times like these make that sequence impossible for a data center. The order of operations on most large campuses now looks like this.
Step 1: Reserve manufacturing capacity
The largest owners place orders, or reserve production slots, with switchgear, transformer, UPS and generator manufacturers before specific buildings are designed. Owners without those commitments buy from distributor stock, from brokers or from other owners' cancelled orders, usually at a premium and with less choice.
Step 2: Owner-furnished, contractor-installed
Because the equipment is bought before the contractor is on board, much of the major electrical gear on a large data center is owner-furnished and contractor-installed, or OFCI. The owner carries the purchase order, the delivery risk and the warranty. The electrical contractor receives, sets, terminates and commissions. That changes how the job is bid: the electrical sub's price is mostly labor, cable, conduit and commissioning, and the equipment value sits on the owner's books.
Step 3: Design to the equipment you can get
Engineers used to size switchgear to the load. On a constrained market they also size the design to the gear that can actually be delivered. If one manufacturer can ship a configuration months sooner than another, the specification follows the shorter line, and approving more than one manufacturer during design gives procurement room to move. Submittals and shop drawings run in parallel with permitting instead of after it.
Step 4: Build the shell to receive the gear
The building, electrical rooms, generator yard, fuel system and underground duct bank proceed while the equipment is in production. A Virginia legislative study (JLARC, 2024) put construction of a single data center building at 12 to 18 months, which is shorter than the lead time on most of the gear that goes inside it. On many schedules the shell is ready before the switchgear is.
Step 5: Set, terminate and commission
When the gear lands, it sets fast. Switchgear lineups arrive in shipping splits, roll onto their pads and are bolted together. Generators are craned onto their pads. The slow part is terminations: thousands of medium- and low-voltage cable terminations, each torqued, labeled and tested. Commissioning then runs in levels, from factory witness testing through the integrated systems test, where the facility is taken off utility power under load to prove the generators and UPS carry it.
Where the Money Goes
JLL's 2026 Global Data Center Outlook forecasts the average global shell-and-core cost at $11.3 million per megawatt in 2026, up from $10.7 million in 2025, and says the tenant's technology fit-out can add up to $25 million per MW for AI infrastructure. Cushman & Wakefield's broader all-in greenfield range is $8.9 million to $23.3 million per MW in the U.S. and Canada, excluding chips and GPUs, with costs up an average of 21% per MW since late 2024.
Cushman's guide identifies power infrastructure as the largest single category at 21% of a greenfield build, per CRE Daily. Equipment price increases explain much of the recent climb. The guide lists switchgear up 60% since December 2021, with copper up 46%, generators and motors 33%, cooling equipment 32% and transformers 29%. On the shorter view, BLS producer price indexes on FRED show switchgear, switchboard and industrial controls equipment (WPU1175) up 12.4% and transformers and power regulators (WPU1174) up 7.6% in the year to September 2026, while copper wire and cable (WPU10260314) rose 30.8%.
That is why the equipment problem dominates everything else. A change in structural steel prices moves one line of the budget. A long slip on switchgear delivery moves the date the owner starts earning revenue.
For square-foot benchmarks and metro-level costs, see our data center construction cost guide.
Who Carries the Risk
The owner
Under OFCI the owner holds the purchase orders and absorbs the delay. That is why the biggest operators have become equipment buyers first and builders second, and why general contractors have added procurement to what they sell. EverOn Data Center Services, the construction business that spun out of T5 Data Centers in September 2026, says it grew from $87 million in revenue in 2021 to $1.7 billion in 2025, and lists long-lead equipment procurement among its services alongside ground-up construction and commissioning oversight, per the company's launch announcement.
The general contractor
GCs on these campuses are paid to manage a schedule they do not fully control. Read the contract closely for how it treats owner-furnished equipment delays, both in liquidated damages and in the milestone definitions that trigger payment. The GC's real leverage is in sequencing: keeping crews productive on one building while another waits for gear, and making sure the rooms, pads, conduit stubs and grounding are complete so that when a switchgear lineup arrives, it sets in days rather than weeks.
The electrical contractor
The electrical sub is where the labor constraint lives. The work is unlike commercial wiring: medium-voltage cable splicing and termination, generator paralleling, UPS commissioning and arc-flash coordination at scale. A Virginia legislative study (JLARC, 2024) estimated about 1,500 workers at peak on a data center building project, and electricians are a large share of the late-stage crew. Our electrician wages by state data shows where pay is highest.
The manufacturer
Switchgear, transformer and generator makers are expanding. POWER reports that manufacturers have committed nearly $2 billion to new or expanded transformer capacity since 2023, citing Wood Mackenzie. New factory lines take years to come online, though, and demand has been growing faster. Wood Mackenzie data cited by POWER shows demand for generator step-up units up 274% since 2019 and substation power transformers up 116%.
What Happens While the Gear Is in Production
The stretch between a finished shell and delivered equipment is where campuses either stay on budget or fall apart. Three strategies have become common.
Phased buildings
Campuses are designed as several buildings so that crews roll from one to the next. Building one's equipment, ordered first, lands while building two's shell is going up. The campus reaches full capacity over several years, but the first revenue arrives earlier.
Prefabricated power modules
Skid-mounted and containerized power modules, sometimes a complete electrical room on a steel frame, are built in a factory while the site is graded, then set with a crane. The equipment lead time does not change, but the on-site labor to install it falls and the work moves into a controlled shop environment.
Bridging power
Where the utility interconnection, not the equipment, is the pacing item, some owners install temporary on-site generation, such as natural gas engines, turbines or large battery systems, to carry the first phase until the substation is energized. That creates a second power-gear procurement with its own lead times and its own permits.
Frequently Asked Questions
How long does it take to get switchgear for a data center in 2026?
Cushman & Wakefield's 2026 Data Center Development Cost Guide, as reported by CRE Daily in August 2026, puts medium-voltage switchgear at 38 to 63 weeks. Wood Mackenzie's Q2 2025 survey, reported by POWER magazine, put the switchgear average at 44 weeks.
What is the longest-lead item on a data center project?
The large power transformers at the substation. Wood Mackenzie's Q2 2025 survey, reported by POWER on January 2, 2026, put power transformers at an average of 128 weeks and generator step-up units at 144 weeks. The utility interconnection approval can take longer than any equipment; JLL reports grid waits of more than four years in primary markets.
What are generator and transformer lead times for data centers?
Cushman & Wakefield's 2026 guide, per CRE Daily, reports generators at 60 to 100 weeks and pad-mounted transformers at 68 to 113 weeks, with some equipment past two years.
How much does a data center cost per megawatt?
JLL forecasts the 2026 global average shell-and-core cost at $11.3 million per MW, with AI tenant fit-out adding up to $25 million per MW. Cushman & Wakefield's all-in greenfield range for the U.S. and Canada is $8.9 million to $23.3 million per MW, excluding chips and GPUs.
What does owner-furnished, contractor-installed mean on a data center?
The owner buys the switchgear, UPS, generators and transformers directly, often well before construction, and the electrical contractor installs and commissions them. The owner carries the delivery risk and the warranty; the contractor prices labor, cable, conduit and commissioning.
Why are data center owners building their own substations?
Because waiting for the utility to build one can take longer than building the campus. A dedicated substation lets the owner order the transformers and control the sequence, with the utility providing the interconnection point. It also puts the owner into the same transformer market where utilities are already competing for factory slots.
Your Action Item for This Week
If you are an electrical, mechanical or civil contractor near a data center cluster, pull the current lead times for the equipment on your next bid before you price labor, and write your schedule around equipment delivery dates rather than notice to proceed. Then check the top 20 data center construction contractors for the general contractors active in your state and find out which ones run OFCI scopes, because those are the jobs where your bid is labor and know-how, not equipment markup. Campuses awarded this year will be setting switchgear one to two years from now.
More from the How It Gets Built desk
Edited by Ray Kowalski, Methods & Machines desk. New teardowns weekly.



