ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Construction Projects

Stargate Abilene: Data Center Construction Cost, Contractors, and Timeline

Danny Reeves·August 25, 2026·Updated October 18, 2026·11 min read

Share this with your estimator.

A data center facility. Representative image — not the Stargate Abilene campus.
A data center facility. Representative image — not the Stargate Abilene campus. Photo: panumas nikhomkhai / Pexels

Project Facts

constructionUnder Construction
Project
Stargate Site 1, Abilene (Lancium Clean Campus)
Location
Abilene, Taylor County, Texas
Project Type
Hyperscale AI data center campus
Estimated Cost
Funded through a $15 billion joint venture of Crusoe, Blue Owl Capital and Primary Digital Infrastructure (phase one alone was a $3.4 billion JV). Construction contract value is not public, and Oracle and NVIDIA IT hardware is not included.
Size / Scope
Eight buildings, approximately 4 million sq ft, 1.2 GW of total power capacity, on the Lancium Clean Campus
Owner / Developer
Crusoe Energy Systems develops and operates the campus on land owned by Lancium, leased to Oracle Cloud Infrastructure for OpenAI. Joint venture equity from Crusoe, Blue Owl Capital and Primary Digital Infrastructure.
General Contractor / CM
DPR Construction (lead), with Rosendin and Southland as multi-prime partners
Architect
HKS (master planning and architecture)
Engineer of Record
AlfaTech
Construction Start
June 2024
Expected Completion
First phase live September 30, 2025. Final building topped out November 2025. Crusoe told Abilene leaders in August 2026 that construction runs through the first quarter of 2027.
Published Aug 26, 2026Last updated Oct 18, 202611 primary sources

Figures are drawn from owner, agency, and contractor sources current as of the last update. Costs and schedules on active projects change — check the federal bid board for related open solicitations.

Crusoe started construction in Abilene in June 2024. On September 30, 2025, Crusoe announced the first phase was live, with Oracle having begun delivery of the first NVIDIA GB200 racks in June 2025. In November 2025 the eighth and final building of the core campus topped out, according to W.Media's November 18, 2025 report on Crusoe's announcement.

That pace is worth studying on its own. But the more useful story for contractors is what happened in March 2026, when a proposed 600 MW expansion fell apart and, three weeks later, Crusoe announced a separate 900 MW campus next door for a different customer. What that swap means for the trade base in a West Texas city of roughly 127,000 people (Census American Community Survey, 2019–2023 five-year estimate) is the part most AI-infrastructure coverage skips.

The build, in order

October 15, 2024. Crusoe, Blue Owl Capital and Primary Digital Infrastructure announce a $3.4 billion joint venture to fund a two-building, 206 MW, 998,000-square-foot build-to-suit data center at the Lancium Clean Campus, 100% leased long-term to a then-unnamed Fortune 100 hyperscale tenant (Crusoe release, Oct. 15, 2024). Construction on that first phase had started in June 2024.

March 2025. Phase two starts: six more buildings, taking the campus to eight buildings and 1.2 GW. On May 21, 2025, the same three partners described the combined effort as a $15 billion joint venture and said phase two was expected to energize in mid-2026 (Crusoe release, May 21, 2025).

June 2025. Oracle begins delivering the first NVIDIA GB200 racks.

September 30, 2025. Crusoe announces the flagship campus is live. Lancium owns the land and electrical infrastructure and has been in the area since 2020, according to Lancium's Michael McNamara in an August 2026 briefing reported by KTXS. Crusoe builds and operates the buildings, and Oracle Cloud Infrastructure is the customer serving OpenAI.

November 2025. The eighth and final building tops out.

March 6, 2026. Bloomberg reports, and Reuters relays, that Oracle and OpenAI abandoned a proposed 600 MW expansion near the flagship site after negotiations dragged over financing and OpenAI's changing needs. Reuters noted the existing eight-building campus was not part of that decision and that Oracle and OpenAI's plan for another 4.5 GW of capacity elsewhere "remains on track."

March 27, 2026. Crusoe announces a 900 MW campus adjacent to the existing site to support Microsoft: two buildings, each designed for 336 MW of critical IT load, a 900 MW behind-the-meter power plant paired with a medium-voltage battery energy storage system, and closed-loop, non-evaporative liquid cooling. Land clearing and site prep had already begun, with the first building targeted for energization in mid-2027. Crusoe put the full Abilene site at about 2.1 GW (Crusoe release, Mar. 27, 2026).

April 2026. Epoch AI, working from satellite imagery and Oracle statements, estimated four of the eight buildings were operational and about 0.3 GW of facility power was online as of April 22, 2026, against a 1.2 GW design (Epoch AI, updated Apr. 23, 2026).

August 2026. Crusoe SVP Jamie McGrath told Abilene leaders that construction on the eight buildings is expected to last through the first quarter of 2027 (KTXS, August 2026). That is later than the mid-2026 target in the May 2025 release and the end-of-2026 completion Crusoe cited in March 2026.

The contract structure and the money

DPR Construction is the lead construction partner, with Rosendin and Southland listed as multi-prime partners, HKS on master planning and architecture, and AlfaTech on engineering and design (Crusoe release on the 2025 DCD Global Awards, Dec. 22, 2025). Crusoe Industries, Crusoe's manufacturing arm, built electrical equipment and switchgear in-house. DPR's own project page adds that Digital Building Components fabricated 656 prefinished exterior panels for the job.

Beyond that, delivery detail is thin by design. This is a privately financed build-to-suit, not a public job: no bid tabs, no published schedule of values, no award notices. There is no public construction contract value.

What is public is the capital stack. The first phase was a $3.4 billion joint venture for two buildings and 998,000 square feet. The full eight-building campus sits inside the $15 billion joint venture announced in May 2025. Those are financing figures, not hard construction costs, and they likely include land and infrastructure payments, financing costs and developer margin alongside construction, so dividing them by square footage does not give you a meaningful $/SF number to bid against.

For a sanity check against market benchmarks, JLL's 2026 Global Data Center Outlook puts the global average shell-and-core cost at about $11.3 million per MW, with tenant AI fit-out able to add up to $25 million per MW. At 1.2 GW, shell-and-core alone at that average would be roughly $13.6 billion, which puts the $15 billion joint venture in a plausible range for the buildings and power infrastructure, before the Oracle and NVIDIA hardware. On a square-foot basis, Gordian's RSMeans data puts a conventional one-story data center building at $505/SF as of Q1 2026, but that is a poor proxy for a gigawatt AI campus; our data center construction cost per square foot and per MW guide explains why the per-megawatt view is the better yardstick, and the data center cost guide shows the state-by-state baseline.

Blue Owl's role matters for how the job runs. When a real assets manager takes the equity position on a build-to-suit with a long-term lease behind it, the project is managed to an energization date, because lease revenue does not start until racks are drawing power. Overtime, second shifts, premium freight and parallel-path procurement get approved fast when a month of delay costs more than the premium. Contractors who work these projects know the tradeoff: the schedule pressure is real, but so is the willingness to pay for it.

What the buildings actually are

Crusoe describes the buildings as optimized for both liquid and air cooling and built for high energy-density AI hardware. The May 2025 release specified direct-to-chip liquid cooling with closed-loop, zero-water-evaporation design, and said each building can operate up to 50,000 NVIDIA GB200 NVL72s. McGrath described the water system to Abilene leaders as filled once and reused.

DPR's project page describes each building as four data halls plus a central utility hall, each hall sized for up to 500 racks, and gives 100 MW per building. Crusoe's March 2026 release likewise refers to the first two buildings as 100 MW each.

Liquid-cooled GB200-class racks are heavier and denser than air-cooled equipment. Designing a hall to accept either means carrying the heavier slab loading, coolant distribution infrastructure and piping penetrations throughout, whether or not a given hall runs liquid on day one. Our piece on data center foundations covers what that does to slab design. Cooling has not been trouble-free: Unite.ai, summarizing Bloomberg's March 2026 reporting, said several Abilene buildings went offline for days when winter weather disrupted parts of the liquid cooling infrastructure.

The adjacent Microsoft campus goes further, with closed-loop non-evaporative liquid cooling and a 900 MW on-site plant tied to medium-voltage battery storage. For mechanical and electrical contractors that is the direction of travel: less evaporative cooling scope, more process piping, more medium-voltage work, more on-site generation and storage tie-in. The switchgear, busway and cable content per megawatt on these campuses is large, which is why anyone bidding the work needs a current view of copper pricing rather than a quarterly one.

The labor math, and the number nobody agrees on

Workforce figures for this site vary by source and by date:

  • Crusoe's May 21, 2025 release: about 3,000 people on site daily, expected to reach nearly 5,000 during phase two.
  • Crusoe's November 2025 topping-out post (via W.Media): 7,000 electricians, construction professionals and tradespeople coming to Abilene every day.
  • Crusoe's December 22, 2025 release: more than 7,000 construction workers on site daily.
  • KTXS, August 2026: McGrath said about 9,000 craft workers are on site daily.
  • KUT, August 12, 2026: Oracle representatives said the project created 9,000 immediate construction jobs, with 1,000 long-term jobs expected.

The later figures may include work on the adjacent Microsoft site, which was in site prep at the same time. Take the trend, not any single number: headcount roughly tripled between mid-2025 and mid-2026.

The effect on the town is less ambiguous. KUT reported on August 12, 2026 that Zillow puts Abilene's average rent at almost $2,600 a month, up nearly 50% from a year earlier, and that renting in Austin is now cheaper. A case manager told KUT his clients are capped at HUD's $1,020-a-month fair market rent and cannot find units at that level. Abilene Christian University said in June that more than 100 incoming students lacked fall housing, and placing a shelter client in permanent housing went from just over a month to as long as six months.

If you are pricing per diem and travel for a job in a small metro absorbing a workforce that size, that is the cost curve you are bidding into, and it moves faster than your labor burden spreadsheet. The state construction dashboards show where similar concentrations are forming. Nationally, Census put data center construction spending at a $84.95 billion seasonally adjusted annual rate in August 2026, up 73.2% year over year, so Abilene is not the only small market feeling this.

What the March swap actually tells you

The instinct is to read a scrapped 600 MW expansion as a demand signal. That is not quite what happened.

The 600 MW Oracle and OpenAI walked away from was never a construction contract. It was a proposed expansion that failed to close on financing and capacity terms, and Reuters' source said that capacity would be met at another Stargate campus. Three weeks later, Crusoe announced 900 MW on adjacent land for Microsoft, with site prep already underway. Net effect on the Abilene trade base: more work, not less, on nearby dirt, with crews already mobilized.

The lesson is about who carries the risk. On an unleased phase, the trade base's exposure is not to whether AI demand exists. It is to whether a specific lease closes with a specific counterparty on specific financing terms, a decision made in a credit committee, not a construction meeting.

Practical hedges: keep escalation and demobilization language tight on unleased phases, do not staff up on a phase with no signed offtake, and read the financing structure before you read the press release. We track that side of the market in our construction economy coverage.

What happens next

The eight-building core finishes construction and fit-out through Q1 2027, per Crusoe's August 2026 briefing. The Microsoft campus next door targets its first building for mid-2027, so foundations, structural steel and the on-site generation package are the near-term scopes on that side of the fence.

Crusoe's March 2026 release says the first eight buildings are expected to provide up to 32% of the City of Abilene's and up to 25% of Taylor County's FY2025 budgeted property tax revenue, and KUT reported the city granted an 85% tax abatement. For contractors, Abilene stops being one project and becomes a market. The question shifts from whether to chase the job to whether your firm can sustain a West Texas presence at this cost basis through 2027 and beyond.

FAQ

How much does Stargate Abilene cost to build?

No construction contract value has been published. The financing is public: phase one (two buildings, 206 MW, 998,000 SF) was a $3.4 billion joint venture announced October 15, 2024, and the full eight-building, 1.2 GW campus sits in a $15 billion joint venture of Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced May 21, 2025. Those figures exclude the Oracle and NVIDIA IT hardware.

Who is the general contractor on Stargate Abilene?

Crusoe names DPR Construction as lead construction partner, with Rosendin and Southland as multi-prime partners, HKS as master planner and architect, and AlfaTech for engineering and design.

How big is the Abilene campus?

Eight buildings, about 4 million square feet and 1.2 GW of total power capacity. Crusoe's adjacent 900 MW campus for Microsoft brings the full Abilene site to about 2.1 GW.

When will it be finished?

The first phase went live September 30, 2025, and the last building topped out in November 2025. In August 2026, Crusoe said construction on the eight buildings would run through the first quarter of 2027. The first Microsoft building next door targets mid-2027.

How many workers are on the site?

Crusoe cited about 3,000 daily in May 2025 and more than 7,000 by December 2025. In August 2026 a Crusoe executive put it at about 9,000 craft workers daily, and Oracle representatives cited 9,000 construction jobs.

What happened to the 600 MW expansion?

Bloomberg reported on March 6, 2026 that Oracle and OpenAI dropped a proposed 600 MW expansion after financing talks dragged and OpenAI's needs changed. The eight-building campus continued, and on March 27, 2026 Crusoe announced a separate 900 MW campus on adjacent land for Microsoft.

DR

Danny Reeves

Master Plumber & Shop Owner

More from Danny Reeves→
mail

Get construction intelligence in your inbox

Housing starts, material prices, contract awards, and original reporting — free, weekly.

Subscribe free