A data center costs about $505 per square foot to build in 2026: that is the Q1 2026 national average for a one-story computer data center in Gordian's RSMeans data published by Building Design+Construction (April 24, 2026), with metros running from $398 in Austin to $688 in Palo Alto. Large campuses are priced per megawatt instead: JLL's 2026 Global Data Center Outlook (January 5, 2026) forecasts a 2026 global average of $11.3 million per MW for shell and core, and says tenants can spend up to $25 million more per MW on AI fit-out. The square-foot figure is nearly double a four- to seven-story apartment building ($268) in the same model series. Below is how to read those two numbers, what drives them, and where a contractor's exposure sits.
| Measure | 2026 figure | What it covers | Source |
|---|---|---|---|
| Building cost per square foot, national average | $505 | One-story computer data center model, Q1 2026 | Gordian RSMeans via BD+C, April 24, 2026 |
| Building cost per square foot, lowest and highest metro | $398 (Austin) to $688 (Palo Alto) | Same model, Q1 2026 | Gordian RSMeans via BD+C, April 24, 2026 |
| Shell and core per MW | $11.3 million | Global average, 2026 forecast | JLL 2026 Global Data Center Outlook, January 5, 2026 |
| AI tenant fit-out per MW | Up to $25 million | Tenant technology fit-out, on top of shell and core | JLL 2026 Global Data Center Outlook, January 5, 2026 |
| All-in greenfield development per MW | $8.9 million to $23.3 million | U.S. and Canadian markets, excluding chips and GPUs | Cushman & Wakefield 2026 guide via CRE Daily, August 27, 2026 |
As of November 15, 2026, Q1 2026 is still the latest quarter Gordian has published for this model, and the JLL and Cushman & Wakefield figures are each firm's current edition.
Two Numbers That Measure Different Things
The per-square-foot figure describes a building. The per-megawatt figure describes capacity. Mixing them up is the most common mistake in early data center budgets.
RSMeans square-foot models are built for planning and conceptual estimates. Gordian says so directly in the BD+C release: the models "are not meant for detailed estimates." The $505 figure is a one-story computer data center model, a building with an enclosure, structure, interior partitions and the base mechanical and electrical systems that model assumes. It is a useful number for an enterprise data room, a small colocation building, or a corporate facility where floor area is still the natural unit.
On a hyperscale or AI campus, the owner thinks in megawatts of IT load, because that is what generates revenue. Power, cooling and redundancy drive the budget, and a building that holds twice the power on the same footprint costs far more than its square footage suggests. That is why JLL, Cushman & Wakefield and the other brokerages report per MW.
JLL's outlook puts the trend in context: between 2020 and 2025 the average global data center construction cost rose from $7.7 million to $10.7 million per MW, about 7% a year, and JLL forecasts another 6% increase to $11.3 million in 2026. Note what is excluded. JLL's figure is shell and core. The tenant's technology fit-out, which JLL says can reach $25 million per MW for AI infrastructure, sits on top.
Cushman & Wakefield's 2026 Data Center Development Cost Guide, as summarized by CRE Daily on August 27, 2026, uses a broader all-in greenfield definition and lands on a range of $8.9 million to $23.3 million per MW across U.S. and Canadian markets, excluding the chips and GPUs. Cushman reports that costs rose an average of 21% per MW since its late-2024 edition.
If someone quotes you a single "data center cost," ask which of these three things it is: a square-foot building model, a shell-and-core cost per MW, or an all-in development cost per MW.
The RSMeans Numbers by Metro
Gordian's table covers twelve locations plus the national average. The Q1 2026 figures and the year-over-year change, from the BD+C release and Gordian's own RSMeans summary (June 25, 2026), which labels the Austin row Austin/Dallas:
| Location | Q1 2026 $/SF | Change vs. Q1 2025 |
|---|---|---|
| National average | $504.76 | 3.1% |
| Austin, Texas | $397.80 | 3.9% |
| Charlottesville, Va. | $423.39 | 3.8% |
| Nashville, Tenn. | $431.32 | 3.9% |
| Atlanta, Ga. | $433.34 | 3.3% |
| Tempe, Ariz. | $445.18 | 6.9% |
| Denver, Colo. | $454.34 | 5.0% |
| Ann Arbor, Mich. | $493.75 | 7.6% |
| Anchorage, Alaska | $561.11 | 6.3% |
| Boston | $592.92 | 4.5% |
| Jersey City, N.J. | $600.15 | 3.6% |
| Chicago | $613.38 | 3.5% |
| Palo Alto, Calif. | $688.26 | 4.3% |
Source: Gordian RSMeans data via Building Design+Construction, April 24, 2026, and RSMeans, June 25, 2026. The Anchorage change is calculated from Gordian's Q1 2025 figure of $527.98.
Gordian's summary also shows the quarterly path: the national average was $489.52 in Q1 2025, $496.81 in Q2, $500.49 in Q3 and $503.95 in Q4 before reaching $504.76 in Q1 2026.
The spread from Austin to Palo Alto is about 73%, and it is mostly labor and local market conditions, not design. Two things stand out. First, the year-over-year changes in the model, 3% to 8%, are modest compared with what brokerages report per MW. The square-foot model tracks a fixed building; the per-MW numbers capture a market where equipment prices and densities are both rising. Second, Northern Virginia, the largest market, is not in the table at all (the only Virginia location is Charlottesville, at $423), so do not assume the national average applies there.
Our data center cost guide adjusts the national figure for each state's construction labor rates.
How Data Centers Compare With Other Buildings
Gordian's RSMeans models for other building types, as published by BD+C, put the data center in context:
| Building type (RSMeans model) | National average $/SF | As of |
|---|---|---|
| Hotel, 15 stories | $262 | 2025 |
| Apartment building, 4-7 stories | $268 | Q3 2026 |
| Hospital, 3 stories | $482 | Q2 2026 |
| Data center, 1 story | $505 | Q1 2026 |
A one-story data center model costs more per square foot than a three-story hospital. That tells you where the money is: not in floors and walls, which a single-story building has fewer of, but in the electrical and mechanical systems packed into each square foot.
Semiconductor fabs are the other building type where systems dwarf the shell, which we covered in our semiconductor fab construction piece.
Where the Money Goes
Cushman & Wakefield's guide, per CRE Daily, identifies power infrastructure as the single largest cost category at 21% of a greenfield build. Beyond that, the split depends heavily on the design, the redundancy level and the density, so treat any fixed percentage you see quoted with suspicion unless you know what building it came from.
Shell and structure
Most data centers are windowless single-story or low-rise structures, often tilt-up or precast. The shell is not exotic, but it is heavier than a warehouse: floors and roofs carry heavy equipment, electrical rooms and generator yards need housekeeping pads and equipment foundations, and the site carries extensive underground duct bank, drainage and fuel piping. Tolerances for floor flatness and the number of sealed penetrations through the envelope are tighter than in typical commercial work.
The shell is also the part of the job a conventional general contractor already knows how to price. That is the trap. A contractor who prices the shell well and carries the systems as allowances is guessing on the part of the budget that matters most.
Electrical
Utility interconnection, medium-voltage switchgear, transformers, uninterruptible power supplies, generators, paralleling gear and distribution make up the electrical scope. Redundancy is the cost multiplier. A "2N" design builds two independent power paths, each able to carry the full load, which means buying roughly twice the gear a non-redundant design would need. "N+1" adds one spare unit to each system. The redundancy tier, set by the owner's uptime target, drives the electrical budget more than the building size.
Electrical equipment prices are climbing faster than general construction costs. The BLS producer price index for switchgear, switchboard and industrial controls equipment (FRED series WPU1175) was up 12.7% from October 2025 to October 2026, and the index for transformers and power regulators (WPU1174) was up 5.6%. Cushman's guide, per CRE Daily, reports switchgear costs up 60% between December 2021 and early 2026, and lists copper up 46%, generators and motors 33%, cooling equipment 32% and transformers 29%.
Mechanical
Cooling is the second big system. Air-cooled designs use computer room air handlers, chillers and cooling towers; high-density AI halls increasingly add liquid cooling, with coolant distribution units and piping run to the rack. Liquid cooling shifts cost from air handling into piping, pumps and controls, and it pulls plumbing and pipefitting trades into the white space.
Efficiency is measured as power usage effectiveness, or PUE: total facility power divided by IT equipment power. A PUE closer to 1.0 means less energy spent on cooling and losses. Owners care because cooling energy is an operating cost for the life of the building, and they will pay for mechanical designs that bring it down.
Fit-out and commissioning
Fit-out covers containment, overhead cable tray, structured cabling, security, monitoring and building management systems. Commissioning on a data center is far more involved than on a standard commercial job. It runs from factory witness tests through integrated systems testing, where the facility is pulled off utility power under load to prove the generators and UPS carry it. Budget the time and the re-test cycles, not just the commissioning agent's fee.
Lead Times Are a Cost Line
Long-lead equipment turns schedule risk into money. Cushman & Wakefield's guide, per CRE Daily, reports medium-voltage switchgear at 38 to 63 weeks, pad-mounted transformers at 68 to 113 weeks and generators at 60 to 100 weeks, with some equipment stretching past two years. Wood Mackenzie's second-quarter 2025 survey, reported by POWER magazine on January 2, 2026, put large power transformers at an average of 128 weeks and generator step-up units at 144.
Our companion piece on how a data center gets its power gear walks through the procurement sequence. The short version for estimators: if equipment will be bought a year or more after your bid, the price you carry today is not the price the owner or the sub will pay. Either the owner buys the gear directly, or your contract needs an escalation mechanism tied to a published index.
Costs Most Early Estimates Miss
When a data center estimate comes in low, it is usually missing one of these:
- Utility infrastructure. Bringing power to the site, whether through a new or upgraded substation, transmission work or utility contribution charges, is often excluded from per-square-foot and even per-MW figures. In some markets the utility builds it and recovers the cost through rates; in others the owner pays up front.
- Site work. Grading, stormwater management and duct bank on a large campus can be a project in itself, especially on former agricultural or industrial land.
- Entitlement. Noise studies, water use reviews, traffic studies and public hearings are increasingly common for data centers, and they take time that the schedule has to carry.
- Escalation. On a multi-year build, pricing equipment and copper at bid-day rates is a bet. The BLS construction materials PPI (WPUSI012011) was up 12.1% in the year to October 2026, and the copper wire and cable index (WPU10260314) was up 25.5%.
- Temporary power and commissioning re-tests. Both are routinely carried as small allowances and routinely overrun.
What the Numbers Mean for Contractors
Demand is not the question. The Census Bureau's construction spending survey (November 2, 2026 release) put private data center construction at a $96.5 billion seasonally adjusted annual rate in September 2026, up 90.3% from $50.7 billion a year earlier. CBRE counted 7,481 MW under construction in primary North American markets in the first half of 2026.
The question is which part of that spending your firm can capture without taking risks it cannot price. A few practical points:
- The electrical scope is the critical path and the largest cost center. A general contractor new to data centers should treat the electrical subcontractor's experience as the first qualification, not an afterthought.
- Ask early whether major equipment is owner-furnished. If the owner buys switchgear, transformers, UPS and generators directly, your scope is installation, coordination and commissioning, and your risk profile changes accordingly.
- Tie material escalation to named BLS PPI series. Our copper price analysis shows why copper-heavy scopes need it.
- Use the RSMeans figures for conceptual budgets on smaller buildings and the per-MW ranges for campuses, and say which one you are using in your proposal.
Data centers built in Europe are priced per MW of IT load as well. The comparison is in US vs. Europe data center construction costs.
Before you price a data center shell or fit-out package, run your own numbers with our free construction cost estimator and check slab quantities with the concrete calculator. To see how data centers compare with other building types, see The 2026 Construction Cost Index.
Frequently Asked Questions
What does a data center cost per square foot in 2026?
Gordian's RSMeans data puts a one-story data center building at $505 per square foot at the national average in Q1 2026, from $398 in Austin to $688 in Palo Alto, per Building Design+Construction (April 24, 2026). Large campuses are priced per megawatt instead: JLL's 2026 Global Data Center Outlook (January 5, 2026) forecasts shell and core at $11.3 million per MW, with AI tenant fit-out adding up to $25 million per MW.
What does a data center cost per megawatt?
JLL forecasts a 2026 global average of $11.3 million per MW for shell and core, up from $10.7 million in 2025. Cushman & Wakefield's 2026 Data Center Development Cost Guide, as reported by CRE Daily in August 2026, puts all-in greenfield costs at $8.9 million to $23.3 million per MW in the U.S. and Canada, excluding chips and GPUs, and says costs rose an average of 21% per MW since late 2024.
Why is electrical work so expensive in data centers?
Redundancy and density. Data centers build duplicate or spare power paths so the IT load never loses power, and they pack far more power per square foot than an office. Cushman & Wakefield identifies power infrastructure as the largest single cost category at 21% of a greenfield build, and switchgear prices alone rose 60% between December 2021 and early 2026, per the guide as summarized by CRE Daily.
Which region has the highest data center construction costs?
Among the metros in Gordian's Q1 2026 RSMeans table, Palo Alto is highest at $688 per square foot, followed by Chicago ($613), Jersey City ($600) and Boston ($593); Austin is lowest at $398. Cushman & Wakefield's guide also ranks Silicon Valley and Chicago among the priciest development markets.
How long are equipment lead times on a data center?
Cushman & Wakefield's 2026 guide, per CRE Daily, reports medium-voltage switchgear at 38 to 63 weeks, pad-mounted transformers at 68 to 113 weeks and generators at 60 to 100 weeks. Wood Mackenzie's Q2 2025 survey, reported by POWER, put large power transformers at an average of 128 weeks.
READ NEXT: Data Center Electrical Systems — Why Every Electrician Should Learn This



