The Second Avenue Subway extension into East Harlem is a live heavy civil job. Gov. Kathy Hochul's office marked the groundbreaking of the major construction stage on June 8, 2026 at the 120th Street and Second Avenue launch site. By mid-September, crews had started excavating the 125th Street entrance shaft and were preparing the launch site while the tunnel boring machine was still being built, according to the governor's office (Sept. 14, 2026). Tunnel boring is expected to start in 2027, and the MTA is targeting revenue service in September 2032.
Two of the three big construction contracts are signed, the utility package is more than half done, and the largest contract, the systems and finishes package, is in procurement now. This profile covers the cost, the contracts, the machine and what is left to bid.
Two Answers to "What Does It Cost?"
Phase 2 is quoted at about $7 billion and at $7.7 billion, and both numbers are real.
The MTA's figure is the capital budget. The governor's office used $6.968 billion in its June and September 2026 releases. The MTA's August 2025 tunneling-award release rounded to $6.99 billion. The federal figure is higher. Gothamist (Aug. 21, 2026) quoted an MTA financial disclosure stating that the revised FTA cost estimate of $7.699 billion "also includes $731 million in finance costs," meaning interest and fees on borrowing. Gothamist reported that the MTA pays those from its operating budget, not its capital budget, and an MTA spokesman said there is no guarantee the full amount will be paid.
The federal share is $3.4 billion under a Full Funding Grant Agreement. Mass Transit (Oct. 26, 2023) reported that the grant equals 44.2 percent of the estimated $7.7 billion capital cost. The governor's office says the local share comes from congestion relief revenue.
The distinction matters for anyone building comparables. Cost-per-mile figures for transit projects often mix capital cost on one job with financed cost on another. Using the MTA's 1.5-mile length, Phase 2 works out to roughly $4.6 billion per mile on the $6.968 billion budget and about $5.1 billion per mile on the $7.7 billion figure. Note that some sources, including ENR, describe the extension as about 1.8 miles, which lowers the per-mile number. State the basis before you quote one. Our explainer on why U.S. tunnel construction costs so much walks through how Phase 1 compares internationally, and our transit station cost guide covers station-level benchmarks.
The MTA's August 2025 release projected about 110,000 additional daily riders and claimed the lowest cost per rider of any active U.S. heavy rail project, without publishing a dollar figure.
Three Stations, Three Approaches
Phase 2 extends the Q train from the 96th Street terminal to 125th Street and Lexington Avenue, with new stations at 106th, 116th and 125th Streets. The MTA put tunnel depth at 35 to 120 feet below Second Avenue.
116th Street reuses 1970s tunnel. The governor's office says the tunnel segment from 110th to 120th Street, built during the city's abandoned 1970s attempt (construction began in 1972 and stopped in 1975), is being reused, with sections adapted for the 116th Street station. The MTA's August 2025 release credited that reuse with $500 million in savings. The work starts with asbestos and lead abatement in the old tunnels, per the governor's June 2026 release, before any tie-ins to new structure. Matching new work to a 50-year-old bore with uncertain as-builts is slow work and a common source of change orders when the pre-construction survey is thin.
106th Street is a new station shell. Contract 3 builds the structural shell between 105th and 110th Streets. ENR describes the scope as excavation, tunneling and the structural shell, plus tie-ins to existing tunnels, excavation support, roadway decking to keep traffic moving, station entrance structures and utility support and reconstruction. Decking a residential avenue over an open dig is mostly a surface-logistics problem: noise limits, utility support, and keeping building access open.
125th Street is the deep terminal. Contract 2 covers boring twin tunnels north from 120th Street to 125th Street and Malcolm X Boulevard and excavating the 125th Street station, which ENR describes as a cavern. This is the piece with the least schedule float.
The Contracts
Contract 1, utility relocation. Awarded in January 2024, it covers utility relocation for the future 106th Street station. The governor's office said in September 2026 that it was about 60 percent complete and expected to finish by summer 2027.
Contract 2, tunneling: Connect Plus Partners. The MTA board approved this design-build contract with a joint venture of Halmar International and FCC Construction at a special meeting on Aug. 18, 2025, according to ENR. ENR and the governor's office put the value at $1.97 billion; the MTA's own August 2025 release said $1.9 billion. The contract runs 1,471 days. Scope includes the twin tunnels, rehabilitation of the 1970s tunnel south of 120th Street, seven shafts, and the station shells at 116th and 125th Streets. The governor's office said final design was more than 50 percent complete as of September 2026 and forecast substantial completion in September 2029.
Two procurement details from ENR are worth studying. More than 30 alternative technical concepts were approved during procurement, and Connect Plus's bid came in nearly $200 million below the competing Skanska Walsh Traylor team, which received a $4 million stipend. ATCs let a bidder price its own means and methods before award instead of carrying contingency against someone else's design. The bid spread suggests that is where the money moved.
Contract 3, 106th Street station: Skanska / Traylor Bros. / Walsh Construction. ENR reported the $1.02 billion design-build award on June 1, 2026, with Mott MacDonald named as lead designer for the team and substantial completion due by August 2030 under a 50-month term. Skanska said its share is $498 million, that work was to begin in May 2026, and that completion is expected in the third quarter of 2030. The governor's office dates the award to April 2026. The same three firms make up the joint venture on the Hudson River Tunnel Section of Gateway's Hudson Tunnel Project, which shows how short the bench of U.S. firms able to carry billion-dollar urban tunneling really is. Our Hudson Tunnel Project profile covers that contract stack.
Contract 4, systems and finishes. The governor's office calls it the largest contract on Phase 2. It covers station infrastructure, track and signals for all three stations, 22 elevators, 20 escalators, six above-ground ancillary buildings, communications and security systems, a connection from the new 125th Street station to the existing 4/5/6 station, and a Park Avenue entrance. The MTA issued a Request for Qualifications in September 2026, plans to issue the RFP by the end of 2026, and expects to pick a contractor in mid-2027. No value had been published as of October 29, 2026, and the governor's release lists both the contract value and term as to be determined.
On savings, the MTA's August 2025 release claimed more than $1.3 billion across its cost-containment efforts, with the $500 million tunnel reuse as the largest piece. The governor's 2026 releases use a more conservative "more than $1 billion."
The Machine
The published TBM specs are inconsistent, so here are both versions. The MTA's August 2025 release described "750-ton machines equipped with 22-foot diamond-studded drill heads." The governor's June 8, 2026 release described a variable-density machine weighing more than 1.5 million pounds (about 750 tons) with a 23-foot tungsten carbide cutterhead, able to switch between hard-rock and soft-ground methods, to be lowered into the ground in early 2027 and bore from 120th Street to 125th Street.
ENR reported a labor detail that matters to estimators. The newer variable-density machine installs the precast concrete lining as it advances. On Phase 1, a separate lining crew of 10 to 12 workers followed a TBM crew of 26. Folding the lining into the machine cycle takes that second crew off the payroll.
A 22- to 23-foot bore is modest next to the 28-foot 8-inch cutterheads now boring the Palisades for the Hudson Tunnel. Diameter is not the hard part here. On a drive this short, the launch shaft, muck handling, segment logistics and the removal shaft drive cost, and the machine may be productive for only a fraction of the contract term. Price urban tunneling around the shafts and logistics first and treat linear advance as the easier part.
Federal Funding Interruption
Phase 2 had its own federal payment fight. ENR (April 17, 2026) reported that federal payments stopped on Sept. 30, 2025, and that the MTA sued in the U.S. Court of Federal Claims on March 17, 2026, alleging breach of the grant agreement over $58.6 million in withheld reimbursements. The U.S. Department of Transportation reversed course on April 16, 2026, hours before oral arguments. The MTA certified that it had stopped using contractor diversity track records in bid evaluations for DOT-funded work and agreed to reevaluate DBE certifications with state partners by August 2026.
For subcontractors, that episode is a reason to read pay-when-paid language closely on federally funded transit work, and to watch how DBE certification changes affect teaming on Contract 4.
What Happens Next
- Contract 1 utility work finishing by summer 2027.
- TBM delivery, assembly and launch at 120th Street, expected in 2027.
- Contract 4 RFP by the end of 2026 and selection in mid-2027.
- Contract 3 substantial completion in the third quarter of 2030 and Contract 2 in September 2029.
- Revenue service targeted for September 2032.
The subcontract tier behind the primes is where most firms will find work: support of excavation, decking, utility relocation, precast segments, waterproofing, and, once Contract 4 is awarded, elevators, escalators, station finishes, traction power, signals, communications and ventilation. Federally funded scopes that are advertised publicly show up on our bid board.
FAQ
How much does Second Avenue Subway Phase 2 cost?
The MTA budget is $6.968 billion (governor's office, 2026). The FTA estimate is $7.699 billion, which includes $731 million in finance costs, per an MTA disclosure quoted by Gothamist on Aug. 21, 2026.
Who is building Second Avenue Subway Phase 2?
Connect Plus Partners (Halmar International and FCC Construction) holds the $1.97 billion tunneling contract. A Skanska, Traylor Bros. and Walsh Construction joint venture holds the $1.02 billion 106th Street station contract. The systems and finishes contract is in procurement, with selection expected in mid-2027.
When will the tunnel boring machine start?
Tunnel boring is expected to begin in 2027 from the 120th Street launch site. As of Sept. 14, 2026, the governor's office said the machine was still under construction.
When will Phase 2 open?
The MTA targets revenue service in September 2032.
How much federal money is in the project?
$3.4 billion under an FTA Full Funding Grant Agreement, about 44.2 percent of the $7.7 billion estimated capital cost. Payments were halted from Sept. 30, 2025 until the U.S. DOT reversed course on April 16, 2026.
Why is the 116th Street station cheaper to build?
It reuses a tunnel segment between 110th and 120th Streets built in the 1970s. The MTA credited the reuse with $500 million in savings in its August 2025 tunneling-award release.



