Las Vegas Athletics Ballpark: Three Arches Up, Roof Next
On Wednesday, October 7, 2026, crews on the Las Vegas Strip finished the third steel truss arch over the Athletics' new ballpark. According to the Las Vegas Review-Journal's report that day, the arch was built from five truss pieces fabricated on site, the last of which weighed about 500,000 pounds. The finished arch spans about 700 feet and stands about 290 feet tall, the highest point on the building.
A's president Marc Badain told the paper the job was "in month 17 of construction" and still on the schedule the joint venture had laid out eight or nine months earlier. The previous arch, the center truss, went in during the week of August 18. Mortenson-McCarthy project director Tyler Van Eeckhaut told KTNV at the time: "We set the center truss, which kicks off with a tremendous amount of work for the next upcoming months."
The center arch matters because it sets the geometry for everything else on the roof. The megapanels, the connector trusses and the outfield glass wall all get set and surveyed against it.
What it costs, and why you see three numbers
The ballpark's price depends on who is talking and when.
- $1.5 billion was the original budget. The Nevada Independent reported in December 2024 that the A's added $250 million for extra construction costs and about 70,000 square feet of added fan space, and the Las Vegas Stadium Authority approved the project at $1.75 billion.
- $1.75 billion is still the construction value on Mortenson's project page.
- $2 billion and up is the figure used once construction was moving. The Nevada Independent reported in February 2026 that owner John Fisher had said in July 2025 that the cost had risen above $2 billion. By September 29, 2026, the Review-Journal was calling it a "now $2.1B" stadium, and its October 7 arch story used $2.1 billion.
The public share is fixed. Senate Bill 1, passed in a 2023 special session, allows up to $380 million in public financing for the stadium. In December 2024 the Nevada Independent described the main pieces as $145 million in bond and tax proceeds, $180 million in transferable tax credits and a $25 million county credit, totaling $350 million of the $380 million that the A's still needed Clark County to sign off on. Because the public number doesn't change, every dollar of escalation lands on the team.
Spending is how you can tell the job is moving. The figures come from the team's regular briefings to the Stadium Authority:
| Date reported | Spent to date | Source |
|---|---|---|
| February 2026 | About $300 million | Nevada Independent, Feb. 20, 2026 |
| May 2026 | About $400 million | Ballpark Digest, May 23, 2026 |
| August 2026 | About $600 million | Las Vegas Review-Journal, Aug. 20, 2026 |
| Late September 2026 | Nearly $700 million | Las Vegas Review-Journal, Sept. 29, 2026 |
About $200 million went in between the May and August briefings. That fits a job moving out of foundations and lower-bowl concrete and into heavy steel while interior trades start below. At each update the team said the project was on schedule and on budget, measured against its own revised number.
On the private side, the Nevada Independent reported that the stadium authority took comfort from at least $1.1 billion committed by the Fisher family and a $300 million loan from U.S. Bank and Goldman Sachs. Aramark also agreed to a $175 million equity investment in the team along with its food service deal. In February 2026 the A's said they would sell a limited personal seat license program, covering less than 20 percent of seats, to help fund their share.
For comparison, the Stadium Authority's chairman pointed to Allegiant Stadium, the Raiders' venue, whose price also grew, from $1.4 billion to $1.9 billion.
The roof is closer to a bridge job than a stadium job
Thornton Tomasetti's project page describes a roof made of five overlapping curved panels shaped like baseball pennants, "supported on 700-foot span arch trusses." Mortenson's page calls them "nearly 700-foot free-standing steel trusses." The first 200-ton roof truss segment went up on June 3, 2026, according to Thornton Tomasetti.
Free-standing arches of that span are unusual in American stadium work. Most long-span stadium roofs are trusses resting on a compression ring that the bowl structure carries. An arch carries itself, but only after it closes. Until then each half is a cantilever with none of the stiffness the finished shape will have. The usual way to handle that is to assemble big segments at grade and then make a small number of very heavy picks, and this project has followed that pattern. The Review-Journal's October story described each arch as five truss pieces fabricated on site.
Behind the outfield, Thornton Tomasetti describes "one of the world's largest cable-net glass façades." A cable-net wall is a tension structure. It only works once the steel around it is set and stiff, so the arches control when the glass can start, and the glass controls when the interior finishes behind it can start. Badain said the remaining roof trusses would culminate in "the cable net window truss," followed by connector trusses, exterior megapanels and the "dragon scale" exterior skin.
This is heavy steel work. Fabricators and erectors watching input costs can follow the producer price indexes on our steel price page and read the 2026 steel price outlook. For plate takeoffs, use the steel plate calculator.
Nine acres on the Strip is the real constraint
The ballpark sits on about nine acres where the Tropicana Las Vegas stood. The Tropicana was imploded on October 9, 2024. A 963,000-square-foot ballpark with 700-foot arches on nine acres leaves very little laydown space for that much steel, and the site is surrounded by operating resorts and some of the busiest road frontage in Nevada.
That changes the usual order of problems. On most stadium jobs the structure is the hard part and logistics work around it. Here, crane placement, delivery windows and assembly space come first, and the erection plan has to fit inside them. Mortenson's project page lists the tools it is using: Synchro 4D for schedule communication, Revizto+ for coordination across the team, drone imagery for logistics and 360-degree site photos. With one place to assemble a segment and one window to pick it, the sequence needs to be worked out in the model before anyone rigs it.
Workforce is the other local factor. Mortenson says more than half of the project workforce is expected to come from the Las Vegas area. In October, Badain told the Review-Journal the crew would grow to between 1,200 and 1,500 workers over the next 12 months. Contractors looking at the Nevada market can check federal spending on our state dashboards and find public solicitations on the bid board.
The bowl, level by level
The roof gets the photos, but most of the labor is in the bowl. Here is where it stood according to the team's August 2026 update, as reported by the Review-Journal and Ballpark Digest:
- ESPN reported on February 19, 2026, that the team said foundation work was complete.
- Concrete on the first two levels was complete by May 2026, according to Ballpark Digest.
- Precast seat risers were installed up to the upper deck across the south half of the bowl.
- Primary steel and bowl construction continued in the upper deck and around the northwest side.
- Escalators were in at the south main entry.
- Interior framing, drywall, masonry and fireproofing were underway.
Setting precast to the upper deck on half the bowl while the roof arches are still going up is a deliberate overlap. Erecting steel overhead while crews set precast and run interior trades below takes strict zoning and overhead protection, but it is how a ballpark schedule gets compressed. The thing to watch is whether riser work moves cleanly from the south half to the north half as the remaining arches go up over the same airspace.
The team's look-ahead from August through the November Stadium Authority meeting listed four more roof trusses, roof megapanel assembly, completion of bowl and perimeter steel, more precast riser installation for the main concourse, upper suites, upper concourse and upper deck, and interior work on all five levels. Badain said in October that seat installation for the roughly 30,000 seats would start sometime in 2027.
The neighbor on the same block
Bally's Corp. owns the rest of the former Tropicana land and is building next to the ballpark. In August 2026 Bally's confirmed it would build the northwest plaza podium that connects to the ballpark. Project plans filed with Clark County put that podium above $200 million, and Bally's full multi-phase project is expected to cost $1.19 billion, according to the Review-Journal. The KTNV report said Bally's plans include restaurants, shopping, entertainment, a hotel-casino and a 2,500-seat theater.
For subs, this means a second owner, a second schedule and a shared interface on a block that is already crowded. Earlier in 2026 the Stadium Authority had worried that the A's might need a temporary plaza if Bally's financing lagged. Bally's said in August that it was close to securing financing for its first phase, so the original plan stands for now.
What happens next
Closing the roof structure over the winter opens the way for the cable-net facade, the enclosure and the finish trades that fill 2027. Mortenson's target is completion in February 2028, ahead of the 2028 MLB season. Until then the A's are playing at a Triple-A ballpark in West Sacramento, the second of three planned seasons there in 2026, according to KTNV.
The stretch between structural completion and opening day is where systems commissioning, the broadcast and media fit-out, the operational shakedown and the playing surface all have to come together. Playing surfaces need their own grow-in and testing time, and adding crews won't speed that up.
For a wider look at stadium and arena work, including the NFL projects in Nashville, Jacksonville and Cleveland, see our report on sports stadium construction spending.
Frequently Asked Questions
How much is the Las Vegas A's ballpark costing? Mortenson lists the construction value at $1.75 billion, the figure the Las Vegas Stadium Authority approved in December 2024. The team has since said the total rose above $2 billion, and the Las Vegas Review-Journal put it at about $2.1 billion in late September and early October 2026. Public financing is capped at up to $380 million under Nevada's 2023 SB1.
How much has been spent so far? Nearly $700 million as of late September 2026, according to the Review-Journal, up from about $300 million in February and $600 million in August.
Who is building it? A joint venture of Mortenson and McCarthy Building Companies is the construction manager at risk. Bjarke Ingels Group and HNTB are the architects. Thornton Tomasetti is the structural engineer and also handles construction engineering, facade engineering, waterproofing and facade access.
Does the ballpark have a retractable roof? No. It has a fixed roof of five overlapping pennant-shaped panels carried on arch trusses spanning about 700 feet, plus a large cable-net glass wall in the outfield.
How many seats? Mortenson lists 33,000 capacity and 122 suites and boxes. The Stadium Authority described it as about 30,000 seats plus standing room for another 3,000 fans.
When does it open? Completion is targeted for February 2028, in time for the 2028 MLB season. In October 2026 the team said the job was still on schedule.