When Power Becomes the Bottleneck
For most commercial building types, utility service is a line item. For data centers it is the project. Developers now pick sites by asking where they can get power soonest, and contractors are increasingly building substations, on-site generation, and utility upgrades alongside the buildings themselves.
The best public baseline comes from the Department of Energy. Lawrence Berkeley National Laboratory's report on U.S. data center energy use, released by DOE on December 20, 2024, found that data centers used about 176 terawatt-hours in 2023, or about 4.4% of total U.S. electricity, up from 58 TWh in 2014. The report projects 325 to 580 TWh by 2028, which would be roughly 6.7% to 12% of U.S. electricity. The wide range reflects real uncertainty about how fast AI workloads grow and how efficient the hardware gets.
Construction spending has followed. The Census Bureau puts private data center construction at a seasonally adjusted annual rate of $84.95 billion in August 2026 (preliminary), up 73.2% from a year earlier.
Which builders actually win this work? Our 2026 data center contractor rankings cover the 20 firms that do most of it.
The Grid Cannot Keep Up
JLL's 2026 Global Data Center Outlook, published in January 2026, says the average wait for a grid connection in primary data center markets now exceeds four years and names speed to power as the primary site selection criterion. A data center building can be built in well under that. The Virginia Joint Legislative Audit and Review Commission found in its 2024 study that a single data center building typically takes 12 to 18 months to construct. When the building takes a year and a half and the power takes four years, the power sets the schedule.
Northern Virginia
Dominion Energy, which serves most of Northern Virginia's data centers, reported more than 48 GW of contracted data center load as of December 2025 and has added more than 5 GW since, according to Baxtel's August 2026 summary of Dominion's quarterly reports. Contracted load at various stages is not the same as load that will actually connect, but it shows the scale of what the utility is being asked to serve.
CBRE's North America Data Center Trends report for H1 2026 says all Northern Virginia capacity scheduled to deliver in 2026 was already committed, vacancy was 0.2%, and Dominion's batching process for new requests is lengthening power delivery timelines. JLARC's study found that unconstrained demand for power in Virginia would double within the next 10 years, driven mainly by data centers, and estimated a typical Dominion residential customer could see generation and transmission costs rise by $14 to $37 a month by 2040 in constant dollars.
Texas and ERCOT
Texas has a different grid and a different problem: a flood of requests. On August 3, 2026, Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to audit the data center projects moving through ERCOT's interconnection process, citing more than 474 GW of requests, about 90% of them associated with data centers. For scale, the Texas Tribune reported in June 2026 that ERCOT's record peak demand was 85,508 MW in August 2023, and that ERCOT's board voted June 2, 2026 to run its first combined study of large loads, called "Batch Zero," for data center proposals that had already secured financing and land.
Most of that queue will not be built. The practical point for contractors is that a Texas data center without a clear place in ERCOT's process is not a firm project yet.
Equipment Is the Other Bottleneck
Even with a utility commitment, the electrical gear has to be built and shipped. POWER magazine's January 2026 review of transformer supply cited Wood Mackenzie's Q2 2025 survey showing average lead times of 128 weeks for power transformers and 144 weeks for generator step-up transformers, with switchgear averaging 44 weeks.
Cushman & Wakefield's 2026 Data Center Development Cost Guide, as summarized by CRE Daily in August 2026, lists pad-mounted transformer lead times of 68 to 113 weeks, generators at 60 to 100 weeks, and medium-voltage switchgear at 38 to 63 weeks. The same guide found switchgear costs climbed 60% between December 2021 and early 2026, and that power infrastructure is the single largest cost category in a greenfield build at 21%. Our electrical substation cost guide covers the utility side of that work.
On-Site Power Generation
As grid timelines stretch, more developers are putting generation on or next to the site. CBRE reports that behind-the-meter power is gaining acceptance in the Dallas-Fort Worth market as grid timelines lengthen.
Natural gas generation
Gas turbines and reciprocating engines are the most common on-site options because they provide firm power. The construction scope looks more like a small power plant than a building: heavy equipment foundations, gas supply piping and metering, exhaust and emissions equipment, step-up transformers, and switchgear to tie the plant into the facility. Air permits and gas supply agreements become schedule items. Contractors with industrial or power plant experience have an edge here.
Battery storage and solar
Battery energy storage systems are showing up on data center campuses, either to support the grid connection, to shave peaks, or to supplement UPS systems. Lithium-ion storage brings its own fire code requirements, including NFPA 855 for stationary energy storage systems, and local fire officials are still working out how to apply them to large installations. Engage the fire marshal early. On-site solar can offset energy use but does not provide the firm, round-the-clock supply a data center needs on its own.
Nuclear
Several hyperscalers have signed nuclear deals, though most of the construction is years away:
- Constellation announced on September 20, 2024 that it would restart Three Mile Island Unit 1 as the Crane Clean Energy Center, adding about 835 MW, backed by a 20-year power purchase agreement with Microsoft. The release said the plant was expected online in 2028.
- Google announced an agreement with Kairos Power on October 14, 2024 for up to 500 MW from small modular reactors, with the first reactor targeted by 2030 and more through 2035.
These deals mostly affect power plant contractors, not data center builders, but they show how far operators will go to secure supply.
How Power Density Changes the Building
AI hardware draws more power per rack than earlier cloud servers, and every watt that goes in comes out as heat. Higher density changes the building in predictable ways:
- More electrical gear per square foot: larger switchgear and UPS rooms, more busway, more copper.
- More cooling capacity, and a shift from air cooling toward liquid cooling loops, with the piping and coolant distribution equipment that come with them.
- Heavier floor loads in the white space and electrical rooms, which drives slab and structural design. See our article on data center foundations.
- Larger generator yards and fuel systems for backup power.
JLL's outlook reflects the cost of this shift. It puts the average global shell-and-core cost at $11.3 million per MW in 2026, up from $7.7 million in 2020, and says tenant fit-out for AI infrastructure can cost as much as $25 million per MW on top of that.
Transmission and Utility Work
The utility side of the boom is its own construction market: new transmission lines, substation expansions, and distribution upgrades. That work uses different crews and equipment than building construction, including line crews, substation electricians, and heavy civil contractors, and much of it is bid by the utilities rather than the data center developer. Firms that can work both sides of the meter will have more places to put their people.
Implications for Construction Firms
Electrical capacity is the scarcest capability. Medium-voltage and high-voltage experience, switchgear and transformer installation, and generator paralleling are where demand is tightest.
Procurement is part of the job. With transformer lead times measured in years, owners are buying gear early, sometimes before design is complete. Contractors who can manage owner-furnished equipment, track deliveries, and protect stored gear on site add real value.
Check the power status before you chase a bid. A project with a signed utility agreement and an energization date is a project. A project still in the queue may not be.
Expect more industrial scope. On-site generation, battery storage, and substations make data center campuses look more like industrial plants every year.
The Bottom Line
The LBNL numbers frame the challenge: data centers went from 58 TWh in 2014 to 176 TWh in 2023, and could reach 325 to 580 TWh by 2028. Utilities cannot add capacity that fast, so power now decides where data centers are built, how long they take, and what the construction scope includes. The firms that understand the power side, from utility timelines to transformer lead times to on-site generation, will be the ones getting the calls.
READ NEXT: Data Center Construction Timeline, Phase by Phase
FAQ
How much electricity do U.S. data centers use?
About 176 TWh in 2023, or about 4.4% of total U.S. electricity, according to the Lawrence Berkeley National Laboratory report DOE released in December 2024. LBNL projects 325 to 580 TWh by 2028, or about 6.7% to 12% of U.S. electricity.
How long does it take to get grid power for a new data center?
JLL's 2026 Global Data Center Outlook says the average wait for a grid connection in primary data center markets exceeds four years. Timelines vary a lot by utility and by how much capacity is requested, so confirm the specific project's interconnection status before bidding.
What are current lead times for transformers and switchgear?
Wood Mackenzie's Q2 2025 survey, as reported by POWER magazine, put power transformers at an average of 128 weeks and switchgear at 44 weeks. Cushman & Wakefield's 2026 cost guide lists pad-mounted transformers at 68 to 113 weeks, generators at 60 to 100 weeks, and medium-voltage switchgear at 38 to 63 weeks.
Why is Texas reviewing data center grid requests?
On August 3, 2026, Governor Abbott directed the PUC and ERCOT to audit data center projects in the interconnection process, citing more than 474 GW of requests, roughly 90% tied to data centers. That is several times ERCOT's record peak demand of 85,508 MW, so many requests will not be built.
What fire code applies to battery storage on a data center campus?
NFPA 855 covers stationary energy storage systems, and local fire officials apply it along with the adopted fire code. Requirements for large lithium-ion installations can affect spacing, detection, suppression, and enclosure design, so bring the fire marshal in during design rather than at permit review.



