Why Data Center Owners Went Looking for Reactors
Data centers have become a large enough electricity customer that the biggest operators now sign contracts for the output of whole power plants. The Department of Energy, releasing a Lawrence Berkeley National Laboratory study on December 20, 2024, put U.S. data center consumption at 176 TWh in 2023, about 4.4% of national electricity use, and projected 6.7% to 12% by 2028 (325 to 580 TWh). Our data center power demand analysis covers what that does to site selection.
Hyperscalers want power that runs around the clock and carries no carbon emissions. Wind and solar alone can't deliver both, and gas doesn't meet the carbon goals. Nuclear can, which is why Microsoft, Google and Amazon have each signed nuclear deals since 2024.
For contractors, nuclear-powered data centers are not one kind of project. There are three separate kinds of work, on different schedules and under different rules:
- Restarting or uprating existing reactors, which is outage-style mechanical and electrical work at an operating nuclear site.
- Building new advanced reactors, mostly first-of-a-kind plants with long licensing tails.
- Building the data center campuses, substations and transmission that sit next to or near those plants, which is ordinary data center construction with an unusual neighbor.
The rest of this article goes through the projects that are actually under contract, then what each means for the people bidding the work. If you're looking for the firms that build most of these campuses, see our ranked list of data center contractors.
Microsoft and the Crane Clean Energy Center
The best-known deal is Microsoft's agreement to buy power from the restarted Three Mile Island Unit 1 in Middletown, Pennsylvania. Constellation announced it on September 20, 2024. Unit 1 is not the reactor that partially melted down in 1979 (that was Unit 2). Unit 1 was retired early for economic reasons in 2019.
Constellation's release set out the basics:
- The plant will be renamed the Crane Clean Energy Center.
- It will supply about 835 MW under a 20-year power purchase agreement with Microsoft, Constellation's largest PPA ever.
- The restart needs Nuclear Regulatory Commission approval after a safety and environmental review, plus state and local permits.
- A study commissioned by the Pennsylvania Building & Construction Trades Council estimated 3,400 direct and indirect jobs. The release does not say how many of those are construction jobs.
The original target was 2028. World Nuclear News reported on April 1, 2026 that Constellation had moved the target to 2027 and was asking FERC to transfer capacity injection rights from its Eddystone plant to Crane. PJM studies suggest full grid deliverability could slip into the 2030s. CEO Joseph Dominguez said the company "continue[s] to expect to start this unit in 2027." The project also has federal support through the DOE loan program, though that article gives no dollar figure.
What the restart work looks like
A restart is not new construction. It looks like a very long refueling outage combined with a plant recommissioning. Expect inspection and refurbishment of the turbine-generator, the main condenser and cooling systems, pumps, valves and instrumentation, along with whatever digital controls, security and emergency planning upgrades the NRC review requires. Constellation hasn't published a line-item scope, so treat that list as the typical work for a reactor that sat idle for five years, not as a confirmed bid package.
The craft labor is mostly the same pipefitters, millwrights, boilermakers, electricians and laborers who staff nuclear outages. They work under the owner's nuclear quality assurance program and site access rules. That means unescorted access screening, fitness-for-duty testing, and paperwork for every weld and torque value, which a commercial crew may not be used to.
Google and Kairos Power
Google went a different direction. On October 14, 2024, Google announced an agreement with Kairos Power for up to 500 MW of new nuclear capacity from small modular reactors. Google said it aims to have the first reactor online by 2030, with more deployments through 2035.
The Kairos design uses a molten fluoride salt coolant and pebble-type fuel. It runs at low pressure and sends heat to a steam turbine. Google describes it as passively safe.
Hermes, the Oak Ridge test reactor
Before any commercial unit, Kairos has to build and run Hermes, a test reactor at the Heritage Center industrial park in Oak Ridge, Tennessee. World Nuclear News reported on December 13, 2023 that the NRC had voted to issue the construction permit. Hermes is rated 35 MW thermal and will not generate electricity. It is meant to produce operating data for the commercial design. It was the first non-water-cooled reactor approved for construction in the U.S. in more than 50 years.
The Google agreement is a capacity commitment of up to 500 MW across several future units. It is not a priced construction contract, and Kairos has not published construction costs for its commercial units.
What it means for builders
Because Hermes is a first-of-a-kind non-power reactor, its construction workforce is small compared with a data center campus, and the work is tightly controlled. For most GCs and subs the bigger opportunity is a few years out, if the commercial units get licensed and sited. Even then, most of the labor dollars on a site like that go to ordinary heavy civil, structural, mechanical and electrical work, all built under a nuclear quality program.
Amazon: Susquehanna and X-energy
Amazon has made two kinds of bets.
Talen and the Susquehanna campus
In 2024 Talen Energy sold its 960 MW Cumulus data center campus, next to the Susquehanna nuclear plant in Pennsylvania, to AWS. Late in 2024 FERC rejected a proposed amendment to the interconnection agreement among PJM, PPL Electric Utilities and Talen. That amendment would have let more of the plant's output feed the campus directly.
The parties then restructured. On June 12, 2025 World Nuclear News reported a new agreement for Talen to supply 1,920 MW from Susquehanna to Amazon through 2042, reaching full volume no later than 2032. The co-located setup moves to a "front-of-the-meter" arrangement. Power flows through the PJM grid, PPL handles transmission and delivery, and Talen acts as retail supplier. The transmission reconfiguration was expected in spring 2026, timed with the plant's refueling outage. Talen and Amazon also said they would look at building SMRs in Talen's Pennsylvania footprint and at uprates to raise Susquehanna's output.
For contractors, the Susquehanna story is mostly about transmission and substation work, and about data center buildings on a campus with an unusual power arrangement. Our substation construction cost guide covers that side.
X-energy and the Cascade project
On October 16, 2024 Amazon anchored a $500 million financing round for X-energy and said it aims to deploy up to 5 GW of X-energy's small modular reactors in the U.S. by 2039. The first project is with Energy Northwest, a consortium of public utilities, near the Columbia Generating Station in central Washington. It starts with four Xe-100 units totaling about 320 MWe, and Energy Northwest has an option to add eight more modules for 960 MWe. The Xe-100 comes in 80 MWe units. Dominion Energy signed a separate memorandum of understanding to study an SMR near its North Anna station in Virginia. That is a study, not a commitment to build.
Other Advanced Reactors Builders Should Track
Some designs have cleared NRC milestones, and those are the ones most likely to turn into construction work this decade.
| Design | Developer | Size | NRC status (as reported) |
|---|---|---|---|
| US460 | NuScale | 77 MWe per module, up to 6 modules (462 MWe) | Standard design approval, reported by DOE May 30, 2025 |
| Natrium | TerraPower | 345 MW, storage can boost to 500 MW | Construction permit for Kemmerer Unit 1, March 4, 2026 |
| Hermes | Kairos Power | 35 MWt, non-power test reactor | Construction permit, December 2023 |
| Xe-100 | X-energy | 80 MWe per unit | Cascade project in development with Energy Northwest |
A few notes on the table:
- NuScale's 77 MWe US460 is the second SMR design the NRC has approved. It builds on the company's earlier 50 MWe design. A design approval lets a utility reference the design in a license application. It doesn't license a specific site.
- TerraPower announced on March 4, 2026 that the NRC Commissioners had voted to grant the Kemmerer, Wyoming construction permit. The company calls it the first commercial-scale advanced nuclear plant to receive one. The review took 18 months against an initial 27-month schedule, and TerraPower expects completion in 2030 under DOE's Advanced Reactor Demonstration Program. It still needs a separate operating license.
What This Means for Contractors
Two quality systems on one site
A nuclear plant is licensed under 10 CFR Part 50 or Part 52, and its safety-related work runs under a nuclear quality assurance program. A data center is permitted under local building codes. If a campus sits next to a reactor, the contractors on each side answer to different rulebooks. A firm that wants work on both sides needs people who know both.
Long lead, long schedule
Data center owners are used to buildings going up in 18 to 24 months. Every reactor project above has a timeline of several years. Crane is a restart and still went from a September 2024 announcement to a 2027 target. Hermes got its permit in December 2023. Kemmerer got its permit in March 2026 and is aiming for 2030. If you're planning hiring or equipment around nuclear work, plan on these schedules, not on hyperscale build schedules.
The workforce is the bottleneck
Nuclear work uses the same crafts that data centers are already short of, especially electricians and pipefitters. The Bureau of Labor Statistics put the national median wage for electricians at $30.38 an hour and pipefitters, plumbers and steamfitters at $30.67 in May 2025 (OEWS). Those are medians across all sectors, not nuclear-site rates. In its January 15, 2026 release, Associated Builders and Contractors estimated the industry needs 349,000 net new workers in 2026 and said data center construction has driven up demand for electricians. Our workforce gap analysis covers the shortage across the whole industry.
Where the near-term dollars are
For the next few years, most of the construction money tied to nuclear-powered data centers will go into:
- Restart and uprate work at existing plants (Crane, and the uprates Talen mentioned for Susquehanna).
- Transmission, switchyard and substation work connecting plants to campuses.
- The data center buildings themselves.
- Site preparation and early civil work for the first advanced reactor projects.
There's no reliable public estimate yet of how many reactors will end up powering data centers or what they will cost to build. For now, the work to bid on comes from the signed deals described above.
FAQ
How much power will the Crane restart supply to Microsoft, and when?
Constellation's September 20, 2024 announcement put it at about 835 MW under a 20-year PPA with Microsoft. The original target was 2028. As of an April 2026 World Nuclear News report, Constellation was aiming for 2027, though PJM transmission studies point to possible delays in full grid deliverability.
Is the Kairos Hermes reactor powering a Google data center?
No. Hermes is a 35 MW thermal non-power test reactor in Oak Ridge, Tennessee. Its NRC construction permit was approved in December 2023. Google's agreement with Kairos is for up to 500 MW from future commercial units. The first is targeted for 2030, with more through 2035.
What is Amazon doing with nuclear power?
Two things. It bought Talen's Cumulus campus next to Susquehanna in 2024 and in June 2025 signed a 1,920 MW supply deal through 2042, restructured as a front-of-the-meter arrangement. Separately, it anchored a $500 million X-energy financing round in October 2024 and is backing a first four-unit, roughly 320 MWe Xe-100 plant with Energy Northwest in Washington.
Which advanced reactor has an NRC construction permit for a commercial-scale plant?
TerraPower's Natrium plant at Kemmerer, Wyoming. TerraPower announced on March 4, 2026 that the NRC had voted to grant the construction permit. It is a 345 MW sodium-cooled reactor with storage that can raise output to 500 MW, and completion is targeted for 2030. It still needs an operating license.
What do data centers use in electricity today?
The LBNL study released by DOE on December 20, 2024 put U.S. data center use at 176 TWh in 2023, about 4.4% of national electricity, rising to 6.7% to 12% by 2028.
READ NEXT: What It's Actually Like Building a Hyperscale Data Center — A GC's Perspective



