The Map Has Shifted
Five years ago the answer to "where are data centers being built" was mostly Northern Virginia, with a handful of other metros behind it. In 2026 the map is wider, and for the first time Northern Virginia is not the busiest construction market in the country.
Start with the national number. The Census Bureau's construction spending release puts private data center construction at a seasonally adjusted annual rate of $84.95 billion in August 2026 (preliminary), up 73.2% from August 2025. In August 2021 the same series was $10.5 billion.
CBRE's North America Data Center Trends report for the first half of 2026, released August 27, 2026, counted a record 7,481 megawatts under construction in its primary markets, up 24.8% from a year earlier. More than 80% of that capacity was already preleased, and primary-market vacancy sat at 1.4%. In other words, most of what is being built already has a tenant, and there is very little empty space to absorb new demand. That is why construction keeps moving into new places.
This tracker covers the markets and named projects we could verify from published sources as of October 2026. It is not a complete list of every project, and we have left out announcements we could not confirm. For a running list of permits and major filings, see our data center permit tracker.
Subcontractors chasing this market usually start with the GCs' approved vendor lists, and the top 20 data center builders are where those lists live.
Georgia: Atlanta Takes the Construction Lead
CBRE's H1 2026 report shows Atlanta with nearly 2,900 MW under construction, which made it the most active construction market in North America for the first time. Data Center Frontier's August 28, 2026 summary of the report puts the exact figure at 2,882 MW, up 52.3% year over year. Atlanta's existing inventory was 1,803.2 MW in Q2 2026, with 29.5 MW available.
CBRE also noted that gigawatt-scale campuses have been announced across South Georgia and other rural parts of the state, outside the metro core, and that build-to-suit projects in Atlanta are being preleased about two and a half years ahead of completion.
For contractors, that preleasing lead time is useful. A build-to-suit campus that is leased two and a half years out has a known owner, tenant, and schedule well before the GC starts buying out trade packages.
Virginia: Still the Largest Market, Now Power-Bound
Northern Virginia remains the largest data center market by inventory. CBRE counted 4,496.5 MW of inventory there in Q2 2026, with just 10.8 MW available and vacancy at 0.2%. Under-construction capacity was 2,420.2 MW, up 16.5% year over year, according to Data Center Frontier's summary. CBRE reported that all Northern Virginia capacity scheduled to deliver in 2026 had already been committed.
Virginia's Joint Legislative Audit and Review Commission (JLARC) found in its 2024 study that Northern Virginia accounts for 13% of reported data center operational capacity worldwide and 25% of capacity in the Americas.
The constraint is power. Dominion Energy reported more than 48 GW of contracted data center load as of December 2025 and has added more than 5 GW since, according to Baxtel's August 2026 summary of Dominion's earnings reports. CBRE notes that Dominion's batching process for new requests is lengthening power delivery timelines. Growth is spreading outward within the state too: CBRE flagged a 1-GW STACK campus in Stafford County.
Texas: Dallas, West Texas, and a Huge Power Queue
Dallas-Fort Worth had 1,432.8 MW of inventory and 39.6 MW available in Q2 2026, per CBRE. Data Center Frontier reports more than 765 MW under construction in the market, about 95% preleased, with another 3.7 GW planned but not yet under construction. CBRE notes that behind-the-meter power is gaining acceptance in Dallas as grid timelines stretch.
Outside the metro, CBRE reports projects in seven West Texas counties reaching energization milestones and expects West Texas to become a top-five colocation market by 2028. The best-known example is the Stargate campus in Abilene; see our Stargate Abilene construction breakdown for the project details.
Houston is also active. Pit & Quarry reported in August 2026 that CTX2, a 60-MW AI-ready facility in Houston, used about 45,000 cubic yards of concrete supplied by Cemex.
The statewide power queue is the number to watch. On August 3, 2026, Governor Greg Abbott directed the Public Utility Commission of Texas and ERCOT to audit the data center projects in the interconnection process, noting that ERCOT was considering more than 474 GW of requests to connect, roughly 90% of them tied to data centers. Most of that will never be built, but it shows how many developers are chasing Texas sites.
Louisiana: One Very Large Project
Meta's data center in Richland Parish is one of the largest single projects in the country. The December 2024 announcement, as reported by Biz New Orleans, describes a $10 billion AI data center on the 2,250-acre former Franklin Farm megasite between Rayville and Delhi, with an estimated 5,000 construction workers at peak and construction expected to run through 2030. Meta projected 500 or more direct jobs once operating. See our Meta Hyperion project page for more on the build.
A project that needs 5,000 workers at peak in a rural parish draws labor from a wide radius. Expect travel crews, per diem, and temporary housing to be part of the cost story on jobs like this.
Indiana, Ohio, and the Midwest
CBRE's report singles out growth around New Carlisle and Lebanon, Indiana, including a 430-MW campus fully leased to Fluidstack. Indiana's sales tax exemption for qualified data centers runs up to 25 years, or up to 50 years for investments over $750 million, according to the Indiana Economic Development Corporation; our state data center incentives guide covers the program.
Mortenson's project page describes an 880-MW data center campus at a confidential rural Midwest site where crews moved nearly 11 million cubic yards of soil, with completion estimated in 2028. That is a good illustration of how much civil work a greenfield hyperscale campus carries before any building goes up.
Ohio's Columbus area remains an active market, and Ohio's data center sales tax exemption under Ohio Revised Code 122.175 requires $100 million of capital investment and $1.5 million in annual site payroll.
Illinois: Big Plans, Paused Incentives
Chicago had 910.6 MW of inventory and 20.0 MW available in Q2 2026, per CBRE, which reported no contiguous 5 MW+ space expected in 2026 and said the next large projects are not expected until late 2027 at the earliest. CBRE also noted 1-GW campuses planned in Coal City and Morris.
Policy is the wild card. Illinois paused new agreements under its Data Center Investment Program from July 1, 2026. The state Department of Commerce and Economic Opportunity says it will no longer process applications as of that date, following a June 5, 2026 directive from the Governor.
Arizona, Oregon, and the West
Phoenix had 1,069.2 MW of inventory and 12.1 MW available in Q2 2026. Data Center Frontier's summary of CBRE notes three colocation projects due for delivery in Phoenix in the second half of the year. Hillsboro, Oregon had 491.4 MW of inventory, just 1.1 MW available, and 170.3 MW under construction that was more than 90% preleased. Silicon Valley had 509.2 MW of inventory and 21.2 MW available.
New York and Canada
New York/Tri-State had 190.0 MW of inventory in Q2 2026. Data Center Frontier reports that New York imposed a one-year pause on state environmental permits for new data centers requiring 50 MW or more.
North of the border, CBRE's report points to Meta's $13 billion development north of Edmonton and Amazon's $4.3 billion campus near Calgary in Alberta.
Why Power Decides the Map
JLL's 2026 Global Data Center Outlook says the average wait for a grid connection in primary data center markets now exceeds four years and names speed to power as the primary site selection criterion. That explains most of the shifts above: Atlanta and its rural periphery, West Texas, Louisiana, Indiana, and Alberta all offered power on a faster timeline than the most constrained markets.
Policy is a second filter. Incentive pauses in Illinois and New York's permit pause show that states can slow a market quickly. Before you commit crews or open an office for a single campus, check both the utility's commitment to the project and the state's current incentive and permitting posture.
What This Means for Contractors
The busiest construction markets are not always the biggest operating markets. Atlanta now leads on construction while Northern Virginia leads on inventory. Bid where the building is happening, not where the headlines were three years ago.
Rural megaprojects need travel crews. Projects like Richland Parish and the Midwest campus Mortenson describes are far from established labor pools. Price per diem, housing, and travel time honestly.
Preleasing tells you which projects are real. CBRE reports more than 80% of capacity under construction is preleased. A project with a signed tenant and a utility commitment is a far safer bid than a speculative campus still waiting on power.
The civil and electrical work starts earlier than you think. Grading programs measured in millions of cubic yards and long utility timelines mean site, utility, and substation contractors are often on these sites a year or more before the building trades. Our substation construction cost guide covers that side of the work.
FAQ
Which state has the most data center construction underway in 2026?
By CBRE's H1 2026 count for primary markets, Atlanta, Georgia led with about 2,882 MW under construction, ahead of Northern Virginia at about 2,420 MW. Northern Virginia remains the largest market by existing inventory, at 4,496.5 MW.
How much is being spent on data center construction nationally?
The Census Bureau puts private data center construction at a seasonally adjusted annual rate of $84.95 billion for August 2026 (preliminary), up 73.2% from a year earlier.
Why is construction moving away from Northern Virginia?
Mainly power. Dominion Energy has reported more than 48 GW of contracted data center load, and CBRE says Dominion's batching process is lengthening power delivery timelines. JLL reports average grid connection waits in primary markets now exceed four years, so developers are going where power is available sooner.
How many construction workers does a large data center project need?
It varies a lot by size. Virginia's JLARC study found about 1,500 workers on site at peak for a typical data center build, while Meta estimated 5,000 construction workers at peak for its $10 billion Richland Parish, Louisiana campus.
Are any states pulling back on data centers?
Yes. Illinois stopped processing new applications for its Data Center Investment Program as of July 1, 2026, and New York imposed a one-year pause on state environmental permits for new data centers needing 50 MW or more, according to Data Center Frontier's summary of the CBRE report.



