The Scale of the Boom
Data center construction is the fastest-growing private building category the Census Bureau tracks. In its construction spending release covering August 2026 (preliminary), Census put private data center construction at a seasonally adjusted annual rate of $84.95 billion, up 73.2% from August 2025. No other major nonresidential category is close to that pace.
That growth is happening inside a flat overall market. Census put total U.S. construction spending at about $2.20 trillion at an annual rate in August 2026, down 1.7% from a year earlier, and manufacturing construction was down 19.8% year over year. For contractors, that means data center work is pulling crews, equipment and attention away from a market that is otherwise cooling.
An earlier version of this article said $28.5 billion was invested in U.S. data center construction in 2025, attributed it to JLL, and quoted a CBRE projection of $32 billion to $36 billion for 2026. We could not find either figure in JLL or CBRE publications, and both are far below what the Census series shows, so they have been removed. Our longer breakdown of the Census numbers is in the $85 billion data center construction boom.
Two points to keep in mind about the Census figure. It counts construction put in place each month, so it lags announcements and does not include servers, chips or most IT equipment. And the latest month is preliminary and gets revised.
For the general contractors behind most of these campuses, see our ranked list of the top 20 data center contractors.
Where the Work Is
Brokers track this market in megawatts under construction rather than dollars. CBRE's North America Data Center Trends report for the first half of 2026 counted 7,481 MW under construction across its primary markets. Atlanta led with 2,882 MW, and Northern Virginia was second with 2,420 MW. Together those two markets accounted for a little over 70% of the primary-market pipeline.
Northern Virginia
Loudoun and Prince William counties are still the largest existing data center market in the world, but construction there is now limited by power more than by land or demand. Dominion Energy's contracted data center load was above 48 GW and reached roughly 53.8 GW by July 2026, which gives a sense of how much capacity is queued behind the utility's transmission and generation build-out. Earlier versions of this article said new Northern Virginia projects face 36- to 48-month interconnection timelines; we could not source that specific range and removed it. JLL reports more generally that grid connection waits in primary markets now exceed four years.
Atlanta
Atlanta overtook Northern Virginia on construction activity in CBRE's first-half 2026 count. For subcontractors in the Southeast, that is the market with the most megawatts in the ground right now.
Texas, Ohio, Arizona and the Midwest
Dallas-Fort Worth, central Ohio and Phoenix remain active markets, and the Midwest has added several large campuses in a short time. Indiana is the clearest example. Confirmed projects there include Amazon Web Services' $11 billion campus in New Carlisle, Google's $2 billion campus in Fort Wayne, Microsoft's $1 billion project in La Porte, and Meta's $800 million facility in Jeffersonville. We cover those in the Midwest data center surprise in Indiana. For a national map, see where every major data center is being built.
An earlier version of this article described Texas as "the second-largest data center market" and credited Phoenix's workforce to nearby semiconductor plants. Neither claim was sourced and both have been removed. The common thread across all of these markets is simple: projects go where a utility can deliver large amounts of power on a schedule the owner can live with.
What a Data Center Project Looks Like
The original version of this article gave typical per-building specifications: 200,000 to 400,000 square feet of white space, 50 to 100 MW, $500 million to $1.2 billion per building, 18 to 24 months, and 1,500 to 3,000 workers. Those ranges were not sourced. Here is what the public record does support.
Virginia's Joint Legislative Audit and Review Commission (JLARC) studied the industry in 2024 and found that a single data center building usually takes 12 to 18 months to construct, with about 1,500 construction workers on site at peak. Large campuses are built in phases, one or two buildings at a time, so a campus can keep a workforce busy for years.
On cost, the Buildermuse cost benchmark file, which draws on Gordian's RSMeans data as published in early 2026, puts a one-story data center building at about $505 per square foot at the national average. Hyperscale owners budget per megawatt of IT capacity instead, and that number depends heavily on whether it covers just the shell and core or the full power and cooling plant. Our data center construction cost guide walks through both approaches.
Whatever the size, the cost is weighted toward mechanical and electrical systems. The shell is relatively simple. The value is in medium-voltage distribution, switchgear, UPS systems, generators, busway, chillers, cooling towers, piping, and more and more often liquid cooling distribution to the racks. That is the reverse of a warehouse or office building, where structure and envelope dominate.
Trades in Highest Demand
Electrical
Electrical is the trade that carries the most value on a data center and the one owners worry about most. The work runs from utility switchyards and medium-voltage gear down to rack-level power distribution, and every system has to be tested under load during commissioning.
On wages, the defensible national baseline is government data. The BLS Occupational Employment and Wage Statistics survey put the national median wage for electricians at $30.38 per hour in May 2025. BLS payroll data put average hourly earnings for all construction employees at $41.69 in September 2026. Earlier versions of this article claimed Northern Virginia data center journeymen earn $45 to $55 per hour, that data center electrical work pays 15% to 25% above prevailing commercial rates, and that NECA had estimated demand outpacing supply by 20% to 30%. We could not find a source for any of those figures, and they have been removed. Data center jobs in tight markets do pay above the median through overtime, per diem and union scale, but the premium varies by local and by project. For trade-by-trade detail, see our data center construction wages guide.
Mechanical
Cooling is the other large cost package. Traditional designs use computer room air handlers and chilled water plants. Higher rack densities for AI hardware are pushing owners toward direct liquid cooling, which adds piping, coolant distribution units and tighter commissioning requirements. Mechanical contractors who have installed and started up liquid cooling systems are in a strong position.
Fire protection
Data halls typically use pre-action sprinkler systems, and some owners specify clean-agent systems in particular rooms. Both are more involved than standard commercial wet systems and require contractors who can coordinate closely with the controls and commissioning teams.
Concrete and structural
Concrete crews pour heavy slabs, generator and transformer pads, and duct banks. The original article gave specific floor load requirements, which we could not source and have removed; loads vary by design and are set in the structural drawings for each project.
The Power Grid Problem
Power is the constraint that decides which projects move. The Lawrence Berkeley National Laboratory report prepared for the Department of Energy and released December 20, 2024 estimated that data centers used about 176 terawatt-hours in 2023, or 4.4% of U.S. electricity, and projected 6.7% to 12% by 2028. An earlier version of this article attributed a 4.4% figure for 2025 to EPRI and gave an 8% to 10% share by 2030; those attributions did not match the published reports and have been replaced with the LBNL numbers.
For contractors, power delays ripple straight into the schedule. When an energization date slips, mechanical and electrical crews can face stop-and-start work while the site waits for the utility. Long-lead equipment such as generators, transformers and switchgear is another bottleneck, and many owners now buy that gear directly and hand it to the contractor as owner-furnished equipment.
Some owners are working around the grid. Google's October 2024 agreement with Kairos Power for small modular reactor capacity is one example, and some rural campuses are being designed to run entirely on on-site gas generation. Our profile of the Prometheus Hyperscale campus in Wyoming covers one of those off-grid designs. On-site generation adds a power plant's worth of mechanical, electrical and civil scope to the job, which is a real opportunity for contractors with power experience. More on grid timelines is in our piece on data center power demands.
Prefabrication
Owners and builders are shifting more power and cooling equipment into factory-built skids and modules: electrical rooms, generator enclosures, pump skids and, on some projects, whole prefabricated power blocks. That moves labor hours from the field to the shop and changes what field crews do. They spend more time setting, connecting and commissioning modules and less time on ground-up installation.
The earlier version of this article said Turner, Holder and others report 20% to 30% schedule savings from modular methods. We could not find that claim in any published source and removed it. The trade-off that is clear is logistics: factory slots and transport become part of the critical path, and factory locations may be far from the job.
What This Means for Contractors
The opportunity
At an $85 billion annual rate, data center construction is large enough to support a lot of contractor capacity. The owners are generally well capitalized, and the work is concentrated in markets you can identify from the CBRE and JLL reports.
The barriers
Hyperscale owners and their general contractors keep approved subcontractor lists and want to see experience on similar projects. Quality and commissioning standards are strict. Firms without data center experience usually come in through a single scope, such as site work, concrete, steel or low-voltage, or through colocation and enterprise projects, and build references from there. An earlier version of this article put bonding requirements for electrical and mechanical packages above $20 million; that figure was unsourced and has been removed. Bonding needs depend on the package size and the owner.
The risks
Concentration risk is real. A contractor that builds its book around one market or one owner is exposed to a pause in that owner's program or a utility delay. Labor competition is the other risk: when data center jobs in a metro are paying overtime and per diem, other commercial projects in the same market have a harder time keeping electricians and pipefitters.
What to track
- The Census Bureau's monthly construction spending release for the data center line (released around the first business day of each month).
- CBRE and JLL data center market reports for megawatts under construction by market.
- State utility commission filings on large-load interconnection in your target markets.
- Owners' quarterly earnings calls for capital spending direction, keeping in mind that those totals include equipment, not just buildings.
Frequently Asked Questions
How large is the US data center construction market in 2026?
The Census Bureau put private data center construction at a seasonally adjusted annual rate of $84.95 billion in August 2026 (preliminary), up 73.2% from August 2025. That counts construction put in place, not servers or IT equipment. The $28.5 billion figure that circulated in earlier coverage, including an earlier version of this article, does not match the Census data.
Which markets have the most data center construction?
In CBRE's first-half 2026 report, Atlanta had about 2,882 MW under construction and Northern Virginia about 2,420 MW, out of 7,481 MW across primary North American markets. Indiana, Texas, Ohio and Arizona are among the other active areas.
How long does it take to build a data center, and how many workers does it need?
Virginia's JLARC found in 2024 that a single data center building usually takes 12 to 18 months to construct, with about 1,500 construction workers on site at peak. Campuses are built in phases over several years.
What makes data center construction different from other commercial work?
The value is in the electrical and mechanical systems rather than the structure, power availability drives the schedule, and every system has to pass load testing during commissioning before the owner accepts the building.
How much electricity do data centers use?
The LBNL report for the Department of Energy, released December 2024, estimated data centers used 4.4% of U.S. electricity in 2023 and projected 6.7% to 12% by 2028.



