Data center construction is the fastest-growing part of nonresidential building right now. Census Bureau data shows data center construction spending at a seasonally adjusted annual rate of $84.95 billion in August 2026, up 73.2% from a year earlier. Large campuses bring big crews: Virginia's Joint Legislative Audit and Review Commission (JLARC) reported in 2024 that a single data center building typically takes 12 to 18 months to build, with about 1,500 workers at peak.
An earlier version of this article said OSHA had designated data center construction as a focus area within a National Emphasis Program, that data center sites had a recordable injury rate of 3.2 per 100 workers, and that 80,000 to 100,000 people work on these sites at any given time. We couldn't verify any of that. OSHA's list of National Emphasis Programs, checked in October 2026, doesn't include data centers, and we found no OSHA directive, news release or Federal Register notice creating one. Those claims have been removed, along with outdated penalty amounts.
What is true is that the hazards on a data center job line up closely with programs OSHA already runs, and with the standards it cites most often. This article covers what actually applies.
What OSHA Is Actually Enforcing
The National Emphasis Programs that reach data center sites
As of October 2026, OSHA's directives page lists twelve National Emphasis Programs. None of them targets a building type like data centers, but several cover the hazards that show up on these jobs:
- Fall Prevention/Protection, CPL 03-00-025, dated May 1, 2023. It covers falls in all industries, including construction.
- Heat, CPL 03-00-024, revised April 10, 2026. It covers outdoor and indoor heat hazards.
- Silica, Crystalline, CPL 03-00-023, dated February 4, 2020. Concrete cutting, coring and grinding on large slab and foundation packages fall under it.
- Trenching and Excavation, CPL 02-00-161, dated October 1, 2018. Duct banks, utility tie-ins and underground electrical work on big campuses involve a lot of trenching.
The revised heat program
According to an April 16, 2026 summary by the law firm Littler, OSHA's revised heat NEP was issued April 10, 2026, took effect immediately, and runs five years. It targets 55 high-hazard industries, 33 carried over and 22 new. It sets up inspections at targeted establishments on days the National Weather Service issues a heat warning or advisory. On "heat priority days," meaning a heat index of 80°F or more, inspectors opened for other reasons are supposed to ask whether the employer has a heat illness prevention program. Inspectors can expand any inspection to cover heat when there's evidence of hazardous conditions, such as injury log entries, worker statements, or what they see.
OSHA's proposed heat injury and illness prevention rule was published August 30, 2024. Public hearings ran from June 16 to July 2, 2025, and the post-hearing comment period closed October 30, 2025. OSHA's rulemaking page shows no final rule. Until there is one, OSHA can cite heat hazards under the General Duty Clause, Section 5(a)(1) of the OSH Act, and a number of states have their own heat rules.
Data center shells are a particular heat problem. Once the building is closed in, but before permanent cooling is running, crews can be working in a sealed, poorly ventilated space, sometimes in arc-rated clothing. Plan for indoor heat the way you would for an August roof.
The most-cited standards
OSHA's preliminary FY2026 top 10 (October 1, 2025 through August 31, 2026) has fall protection at No. 1, scaffolding at No. 4, ladders at No. 5, and fall protection training at No. 8. A data center job has all of those exposures: cable tray and ladder rack overhead, mechanical yards, roof equipment, generator exhaust and steel platforms. Our breakdown of OSHA's top 10 construction citations for 2026 goes standard by standard.
The Hazards That Set Data Center Jobs Apart
Electrical work while parts of the building are live
Data center jobs often energize sections of the building, such as early data halls, switchgear lineups or temporary power, while construction continues around them. That changes the rules for everyone nearby. The core OSHA construction requirements:
- 29 CFR 1926.416(a)(1): no employee may work close enough to any part of an electric power circuit to contact it unless they're protected by deenergizing and grounding the circuit or by guarding it effectively with insulation or other means.
- 29 CFR 1926.417(b): deenergized equipment or circuits must be rendered inoperative and tagged at every point where they can be energized.
- 29 CFR 1926.404(b)(1): all 120-volt, single-phase, 15- and 20-amp receptacles on construction sites that aren't part of the permanent wiring and are in use by employees must have approved ground-fault circuit interrupters.
NFPA 70E, the electrical safety consensus standard, is the usual framework for arc flash risk assessment, approach boundaries and energized work permits. It isn't an OSHA regulation, but many owners and general contractors require it by contract, and it's a common way to show how you're meeting OSHA's electrical requirements. Our guide to data center electrical systems covers the gear electricians will be working on.
The practical point is boundary control. Every area that's been energized needs a clear line, signage and access control, and every trade foreman, not just the electrical foreman, needs to know where those lines are each day.
Confined spaces
Electrical vaults, underground duct bank manholes, some generator enclosures and battery rooms, and tanks can all be confined spaces. The construction confined space standard, 29 CFR 1926 Subpart AA, requires that before work begins at a worksite, a competent person identify all confined spaces where the employer's workers may work and identify which of them are permit spaces, with testing as necessary (1926.1203(a)). If there are permit spaces, workers have to be told where they are and what the danger is, for example with a danger sign.
Do that survey early and update it as the building changes. A space that was open air during the structure phase can become a confined space once it's closed in.
Work at height
Overhead cable tray and ladder rack in data halls, mechanical equipment on roofs and platforms, and generator exhaust work all put people at height. The rules are the standard ones: protection at 6 feet on walking and working surfaces (1926.501(b)(1)), protection above 10 feet on scaffolds (1926.451(g)(1)), and fall arrest anchorages that support 5,000 pounds per attached worker or are designed by a qualified person with a safety factor of at least two (1926.502(d)(15)). Schedule pressure is usually what defeats them, so the controls need to be planned and staged before the crews arrive.
Concrete and silica
Large slabs, equipment pads and core drilling for conduit and piping produce silica dust. The construction silica standard, 29 CFR 1926.1153, sets a permissible exposure limit of 50 micrograms per cubic meter over an 8-hour shift and an action level of 25. Our article on silica dust enforcement covers Table 1 and the controls it calls for.
What a Citation Costs
OSHA's penalties page lists these maximums for penalties assessed after January 15, 2026:
- Serious and other-than-serious violations: $16,550 per violation
- Failure to abate: $16,550 per day beyond the abatement date
- Willful or repeated violations: $165,514 per violation
The often-quoted $16,131 and $161,323 maximums are out of date.
Injury Rates in Context
BLS doesn't publish injury rates for data center construction specifically. Its Survey of Occupational Injuries and Illnesses for 2024 (released January 22, 2026) gives rates for the industries that build them, per 100 full-time workers:
| Industry (2024) | Total recordable case rate |
|---|---|
| All private industry | 2.3 |
| Construction | 2.2 |
| Nonresidential building construction | 1.9 |
| Electrical contractors | 1.8 |
| Plumbing, heating and air-conditioning contractors | 3.0 |
Owners and general contractors on large data center programs commonly screen subcontractors on their recordable rates and experience modifiers. Requirements vary by owner, so get them in writing at prequalification rather than assuming a number.
A Safety Plan Built for a Data Center Job
Electrical
- Write an energization plan with the owner, the GC and the electrical contractor that shows when each area goes live, and update it weekly.
- Use lockout/tagout procedures that cover multiple sources. Redundant power paths mean one disconnect is rarely enough.
- Require energized work permits and an arc flash risk assessment before anyone works on or near live gear, and supply PPE rated for the assessed hazard.
- Mark and control access to every energized area, and brief all trades on the boundaries daily.
- GFCI-protect all temporary receptacles and test them.
Confined space
- Have a competent person survey and classify confined spaces before work starts, and repeat the survey as the building closes in.
- Monitor the atmosphere where conditions call for it, including battery rooms during charging and anywhere engines run.
- Plan rescue for each permit space before anyone enters.
Falls
- Engineer anchor points for recurring overhead work such as cable tray runs, and install them before the trades arrive.
- Have a competent person inspect scaffolds before each shift, and inspect aerial lifts before use.
- Plan for rescue of a worker suspended in a harness, and practice it.
Heat
- Monitor heat inside the closed-in shell, not just outdoors.
- Set work and rest schedules that account for arc-rated clothing and other heavy PPE.
- Provide water, shade or cooled break areas, and a buddy system, and train crews and foremen on heat illness symptoms.
- Acclimatize new and returning workers.
Documentation
A site-specific safety plan, daily pre-task plans, training records that show names, dates and trainers, and inspection logs for scaffolds and fall protection are what an inspector asks for first. They're also what an owner's safety team will audit.
For more on who builds these projects and how the schedule runs, see our list of the top data center construction contractors and our phase-by-phase data center construction timeline.
Frequently Asked Questions
Does OSHA have a National Emphasis Program for data center construction?
No. OSHA's list of National Emphasis Programs, as of October 2026, doesn't include one for data centers. The fall protection, heat, silica, and trenching and excavation programs do apply to the hazards on data center jobs.
What is OSHA's heat rule status in 2026?
OSHA proposed a heat injury and illness prevention rule on August 30, 2024. Hearings ended July 2, 2025, and the post-hearing comment period closed October 30, 2025. OSHA's rulemaking page shows no final rule yet. OSHA revised its heat National Emphasis Program on April 10, 2026, and can cite heat hazards under the General Duty Clause.
Is NFPA 70E an OSHA requirement?
No. NFPA 70E is a consensus standard, not an OSHA regulation. OSHA's construction electrical rules, such as 1926.416 and 1926.417, require protection from contact with energized circuits and tagging of deenergized circuits. Many owners require NFPA 70E compliance by contract as the way to meet those obligations on energized work.
What are OSHA's maximum penalties for 2026?
For penalties assessed after January 15, 2026: $16,550 per serious or other-than-serious violation, $16,550 per day for failure to abate, and $165,514 per willful or repeated violation.
Are data center construction sites more dangerous than other commercial jobs?
BLS doesn't publish data center injury rates, so there's no official comparison. In 2024, the total recordable case rate was 1.9 per 100 full-time workers in nonresidential building construction and 1.8 for electrical contractors, the industries that do most of the work. What's different about data center jobs is how much energized electrical work, confined space and indoor heat exposure they combine on one site.



