VA hospital construction delays are some of the best documented in public building. The Government Accountability Office has reviewed the Department of Veterans Affairs' major construction program repeatedly since 2009, and its testimony gives project-by-project numbers on cost growth and schedule slip. Those numbers are more useful to a contractor than the round figures that get repeated online, because they show where the time and money actually went.
A note on one of those round figures. GAO's January 2015 testimony (GAO-15-332T) said that in April 2013 VA was managing 50 major medical-facility projects "at a cost of more than $12 billion." That $12 billion is the size of the program at the time, not the amount it ran over. The overruns on the four largest projects GAO examined totaled a bit over $1.5 billion.
This article walks through what GAO found, what changed in the law after the Aurora, Colorado hospital, and how the current flagship replacement hospital in Louisville, Kentucky has tracked. For the size of VA's overall capital need and current appropriations, see our companion piece on the VA hospital construction backlog.
What GAO Measured on VA's Largest Hospitals
In April 2013 (GAO-13-302), GAO looked at VA's four largest medical-facility projects: Denver (actually Aurora, Colorado), Las Vegas, New Orleans and Orlando. It found cost increases of 59% to 144%, totaling nearly $1.5 billion, and schedule delays of 14 to 74 months, with an average delay of 35 months per project. That average, just under three years, is the most defensible single number for how late VA's big hospitals ran in that period.
GAO updated the figures in January 2015 testimony to the House Veterans' Affairs Committee (GAO-15-332T). As of December 2014, compared with the original estimates VA gave Congress:
| Project | Initial estimated cost | Estimated cost (Dec. 2014) | Increase | Initial completion | Estimated completion | Months late |
|---|---|---|---|---|---|---|
| Las Vegas | $325 million | $585 million | 80% | April 2009 | Summer 2015 | 86 |
| Orlando | $254 million | $616 million | 143% | April 2010 | January 2015 | 57 |
| Denver (Aurora) | $328 million | $800 million | 144% | February 2014 | April 2015 | 14 |
| New Orleans | $625 million | $1.035 billion | 66% | December 2014 | February 2016 | 14 |
GAO counted total time to complete, from VA's approval of the architect-engineer to the estimated finish, at 8.5 to 11.25 years for these four projects. In a footnote it recorded that Naval Facilities Engineering Command officials told GAO that, historically, medical facility projects take approximately four years from design to completion.
The Denver line in that table was already out of date when GAO published it. VA told GAO that final cost and schedule for Denver would be set once the Army Corps of Engineers issued a long-term contract, so it could not give updated numbers. By April 2015 (GAO-15-564T), GAO said cost increases across the four projects ranged from 66% to 427%, and that Denver's cost had grown by nearly $930 million since GAO's 2013 report, with the completion date unknown.
Earlier work showed the problem was not limited to four projects. GAO's December 14, 2009 report (GAO-10-189) reviewed 32 ongoing major construction projects with an estimated total cost of about $6.1 billion as of August 2009. Of those, 18 had cost increases ranging from 2% to 285%, and 11 were projected to finish late, four of them by more than 24 months. GAO noted at the time that VA did not conduct cost or schedule risk analyses and did not require an integrated master schedule for major projects. VA agreed to start doing both.
Why the Projects Slipped
GAO's explanations are specific, and they line up with what experienced healthcare builders see on large owner-driven jobs.
Scope changed after the number went to Congress. Las Vegas was first planned as an expanded clinic co-located with Nellis Air Force Base. VA later decided that an inpatient center shared with the Air Force would not meet local veterans' needs and built a full medical center instead. Under the 2009 report, the Las Vegas estimate had gone from $286 million to about $600 million.
Shared-facility deals fell apart. In both Denver and New Orleans, VA originally planned facilities shared with a local university and switched to stand-alone hospitals when the partnership could not be finalized. In Denver, talks with the University of Colorado Hospital ran from 1999 to late 2004. VA picked an architect-engineer for a stand-alone project in 2005, suspended the design in 2006 while it acquired a new site, restarted in 2007, and suspended again in January 2009 when it cut scope for lack of funding. GAO said that by then costs had risen about $470 million, partly because VA now carried the full cost of operating rooms and other specialized space alone.
Sites moved. In Orlando, VA's site changed three times between 2004 and 2010. The existing hospital site proved too small, and before VA could close on a larger parcel, the owner sold half of it to another buyer.
Ground conditions surprised the owner. At Denver, VA found asbestos and faulty electrical systems in existing buildings, a buried swimming pool and a mineral-laden underground spring that had to be pumped and treated continually, which affected plans for underground parking.
Process slowed the field. In 2013 GAO reported that VA did not consistently use medical equipment planners, which led to redesign, demolition and work suspensions in Orlando when equipment specifications changed. It also found that contractors received conflicting direction from different VA offices, and that VA's multi-level change-order approval process caused long delays and higher costs. GAO lists its three 2013 recommendations (assign equipment planners, define roles for contractors, and streamline change orders) as closed and implemented; VA issued the related guidance and a contract modification handbook in August and September 2013.
Delivery method came too late. VA and the Corps had been developing an Integrated Design and Construction approach that brings the contractor in during design. GAO found that Denver started as design-bid-build and switched to IDC after the project was under way, too late to get the full benefit.
None of these causes is unique to VA. What made VA's results worse was that several of them hit the same projects, and that every change needed approval through a federal chain before the field could act on it.
Aurora and the $100 Million Rule
The Aurora hospital became the case Congress used to change how VA builds. Construction Dive reported on February 11, 2016 that the hospital would cost $1.7 billion, about three times the original contract price, and was scheduled to open in 2018, four years behind schedule. The Associated Press, as published by CBS News Colorado on July 20, 2018, described the opened Rocky Mountain Regional VA Medical Center as a $1.7 billion facility more than $1 billion over budget and five years late.
The legal response came in Public Law 114-58, signed September 30, 2015. Section 502 added subsection (e) to 38 U.S.C. 8103, which requires VA to enter into an agreement with an appropriate non-VA federal entity to provide full project management services, covering design, acquisition, construction and contract changes, for any "super construction project," defined as a medical facility project involving a total expenditure of more than $100 million. The requirement applies to the Denver project and to any super construction project authorized on or after the date of enactment. In practice the Army Corps of Engineers has filled that role.
A separate threshold governs whether a project counts as major construction at all. The Congressional Research Service's June 2026 report on FY2026 VA appropriations (R48968) says the major construction account funds projects expected to cost more than $30 million, a figure increased annually as stipulated in law, and that Congress reviews, approves and funds major projects one at a time. Projects at or below $30 million go through the minor construction account and are approved inside VA.
For contractors, the $100 million rule changes who you are dealing with on large VA hospitals. Your owner's representative is usually a Corps district, your contract is a Corps contract, and your change-order process runs through Corps procedures. Our guide to how to bid federal construction contracts covers the general mechanics.
Louisville: A Replacement Hospital Two Decades in the Making
The new Louisville VA Medical Center is the clearest current example of how long a VA replacement hospital takes from decision to opening, and how the post-Aurora model works.
VA's project page for the new Robley Rex VA Medical Center (last updated August 4, 2026) lays out the history. The CARES Commission recommended a new Louisville medical center in 2004. VA announced a replacement hospital in June 2006, and funding was approved in September 2008. A 34-acre site off Brownsboro Road was selected on June 29, 2012. A lawsuit challenging the site, filed in March 2018, was dismissed on March 18, 2021.
On August 17, 2021, VA and the Corps' Louisville District awarded an $840 million construction contract to Walsh-Turner Joint Venture II. The Construction Index reported at the time that the project was scheduled to be complete in 2025. VA's page says all construction options, worth $68 million, were exercised in October 2022, describes a 910,115-square-foot medical center plus a 42,205-square-foot central utility plant (972,000 square feet for the whole project), and says parking will grow from 1,650 to 2,600 spaces. The Corps' Louisville District serves as design and construction project manager under a 2015 interagency agreement.
The current schedule is later than the original. VA's project timeline lists completion in April 2027, although an FAQ on the same page still says early 2026. Federal award data agree with the later date: USAspending shows total obligations of $971.8 million on the Walsh-Turner contract and a period of performance ending April 7, 2027, with the record last modified July 15, 2026. Spectrum News reported on December 17, 2025 that the area engineer put the contractors at about 85% complete.
Measured from the 2006 replacement decision to an April 2027 finish, Louisville will have taken about 21 years. Almost all of that time passed before a contractor mobilized. Construction itself, from a September 2021 start to April 2027, is roughly five and a half years, against an original 2025 target. That pattern, long pre-construction and a moderate construction-phase slip, is typical of what the record shows for VA hospitals.
What This Means for Bidders
The record points to a few practical habits for firms that pursue VA healthcare work.
Read the history before you price. A VA project that has gone through site changes, scope changes or a partnership collapse carries that history into its drawings. Ask how many times the design was suspended and restarted, and whether a medical equipment planner was assigned from the start.
Price the change-order cycle, not just the change. GAO repeatedly identified multi-level change-order review as a source of delay and cost. Even with VA's 2013 reforms and Corps management on large projects, a federal hospital change takes longer to approve than a private one. Carry the cash flow and extended general conditions that go with that.
Plan for site conditions. Denver's buried pool and underground spring are reminders that federal hospital sites are often former military or institutional land with older buildings and utilities on them. Your geotechnical and hazardous-materials review should be thorough before you commit to a number.
Know the compliance stack. VA work carries Davis-Bacon wage determinations, certified payroll, Miller Act bonds and, at many stations, Veterans First set-asides for service-disabled veteran-owned firms. Our explainer on Davis-Bacon prevailing wage on federal bids covers the wage side.
Use the smaller programs to build a record. Minor construction and non-recurring maintenance work at a single medical center is where most firms earn the past performance that large VA and Corps solicitations ask for. For per-square-foot context on hospital work generally, see our hospital construction cost per bed guide.
What to Watch
Watch Louisville's turnover. An April 2027 completion is the current contract date; whether the Corps hands the building to VA on that schedule will be the first full test of the post-2015 management model on a new replacement hospital.
Watch FY2027 appropriations. CRS's September 14, 2026 overview (R49347) reports that no regular FY2027 appropriations bills had been enacted and that a continuing resolution signed September 2, 2026 (P.L. 119-103) funds VA through December 11, 2026, largely at FY2026 rates. Under a CR, new major construction starts generally wait.
Watch for new GAO work. Most of GAO's detailed VA construction reviews date from 2009 to 2015. Any new review of Corps-managed super construction projects would give the first independent read on whether the 2015 law closed the gap.
Frequently Asked Questions
How long are VA hospital construction delays on average?
The best documented figure comes from GAO's April 2013 report (GAO-13-302), which found delays of 14 to 74 months, averaging 35 months, on VA's four largest medical-facility projects in Denver, Las Vegas, New Orleans and Orlando. By December 2014 the range had grown to 14 to 86 months, according to GAO-15-332T. We have not found a GAO or VA figure averaging delays across VA's entire current portfolio.
How much did VA's largest projects go over budget?
GAO's January 2015 testimony put cost increases at 66% to 144% compared with initial estimates, a total of over $1.5 billion, for the four largest projects. By April 2015, after further growth at Denver, GAO put the range at 66% to 427%. The Aurora hospital ultimately opened in 2018 at about $1.7 billion, more than $1 billion over budget, according to the Associated Press.
Where does the "$12 billion" figure come from?
GAO said in 2015 that as of April 2013 VA was managing 50 major medical-facility projects at a cost of more than $12 billion. That is the total value of the program at the time, not the amount of overruns.
Who manages large VA hospital construction now?
Since Public Law 114-58 (September 30, 2015), 38 U.S.C. 8103(e) requires VA to have a non-VA federal entity provide full project management for medical facility projects over $100 million. The Army Corps of Engineers manages projects such as the new Louisville VA Medical Center.
What is the status of the new Louisville VA hospital?
VA and the Corps awarded an $840 million contract to Walsh-Turner Joint Venture II on August 17, 2021, with completion originally targeted for 2025. USAspending shows $971.8 million obligated and a contract end date of April 7, 2027, and VA's project timeline lists April 2027 completion.
What is the dollar line between major and minor VA construction?
According to CRS report R48968, major construction covers projects expected to cost more than $30 million, a threshold increased annually as stipulated in law. Projects at or below that line are minor construction.



