A lot of what happened on the Brent Spence Bridge Corridor Project this summer happened late at night.
The project team's closure list, as reported by WXIX FOX19 and WCPO in mid-June 2026, ran like this. June 28, around 10 p.m.: the exit ramp from the eastbound U.S. 50/Sixth Street viaduct to Second Street closed permanently. June 29, around 11 p.m.: the I-75 South exit ramp to Second Street (Exit 1A) closed permanently, to be replaced by a ramp to Third Street. July 7, around 11 p.m.: the ramp from the westbound U.S. 50/Sixth Street viaduct to Gest Street closed permanently, with a replacement in a future phase. July 8, around 11 p.m.: the northbound I-71 ramp to Second Street closed, scheduled to reopen in fall 2028. July 9, around 10 p.m.: Second Street dropped to one lane between the Clay Wade Bailey Bridge and Elm Street, where it stays through spring 2027.
That is what a $4.05 billion job looks like when it is threaded through a downtown that never stops. The interstate stays open, and the work gets staged in the hours fewest people are using it.
What is being built
The project builds a new cable-stayed companion bridge just west of the existing Brent Spence Bridge, which has carried I-71 and I-75 across the Ohio River between Cincinnati and Covington since it opened on November 25, 1963, according to the project timeline. The companion bridge design, unveiled in June 2025, is a cable-stayed independent deck bridge: instead of a steel truss holding up the lower deck, both decks hang from the cable system, with no steel connecting the two decks. The project team said cost, constructability and schedule decided the bridge type, and that the chosen design was lower in cost and easier to build than the alternatives. Through traffic moves to the new structure; northbound drivers use its top level. The existing bridge stays in service for local traffic.
That is not the whole scope. According to the May 8, 2026 groundbreaking release from Kentucky Gov. Andy Beshear's office, every connection to the existing bridge gets overhauled in both states, including more than 30 overpasses or underpasses in Ohio and a dozen in Kentucky, along with new approaches, redesigned ramp configurations, and new pedestrian and bike paths. The project's August 2026 newsletter describes the full corridor as eight miles of roadway, including two miles of approaches to the companion bridge, plus stormwater upgrades. The project timeline says the prime contract covers six of those eight miles, and the two northernmost miles will be built under separate contracts.
The existing bridge also gets fixed. The same release says that in 1985 the bridge was reconfigured to add a fourth lane in each direction by removing the emergency shoulders and narrowing the lanes. This project reverses that: back to three lanes each way, with shoulders restored. ODOT Director Pamela Boratyn said the project "will fix the paralysis that grips the region when accidents occur," which is the practical consequence of a bridge with nowhere to put a broken-down truck.
The project timeline says the bridge was designed for 80,000 vehicles a day. Construction Dive, citing the federal permitting dashboard, reported in March 2026 that it carries about 160,000. More than $1 billion in freight moves through the corridor daily, according to the state release.
Who is building it and what it costs
The owners are the Ohio Department of Transportation and the Kentucky Transportation Cabinet, working with the Federal Highway Administration. The Walsh Kokosing joint venture of Walsh Construction and Kokosing Construction holds the design-build contract. The project fact sheet lists AECOM as lead designer, Jacobs as Independent Companion Bridge Engineer, and Parsons as the independent design quality firm; Walsh's own groundbreaking announcement lists AECOM and Jacobs as its design team members. Either way, the structure puts separate reviewers on the design outside the design-builder's lead designer.
The current phase is $4.05 billion, according to the state release. Construction Dive reported in March 2026 that the overall estimate had risen to $4.4 billion, about $700 million above the earlier $3.6 billion figure, and that the construction portion going forward is $4.05 billion. The same article cited the FHWA National Highway Construction Cost Index, which rose 61 percent nationally from 2020 through 2025, as the reason, by way of a March 17 announcement from the city of Covington.
Federal money covers a large share. The project timeline says the corridor was awarded $1.635 billion in federal grants on December 29, 2022. FHWA's June 2024 Bridge Investment Program report lists $1,385,000,000 of that as a BIP large bridge grant, funded across several fiscal years, starting with $533.2 million from FY 2022. That leaves about $250 million from a second USDOT grant. The state release says the balance will come from KYTC and ODOT state revenues and/or financing, with each state paying for its own highway work and the two splitting the companion bridge.
There are no tolls. Sen. Mitch McConnell said in the groundbreaking release that the cost would be shared between state and federal governments "so that no one traveling through would have to pay a toll."
The states have not priced everything. Future phases, including more work on the eight-mile corridor and the rehabilitation of the existing Brent Spence Bridge, will be estimated closer to the time of construction, per the state release.
The 2026 work: groundwork first, then the river
Heavy construction began in spring 2026, according to the fact sheet, and the governors broke ground on May 8 at the Duke Energy site where the companion bridge will cross the river. Much of the first construction season was work that has to finish before a bridge can be built.
- Demolition. The ARTIMIS building came down in November 2025 to clear the companion bridge approach. Demolition at Longworth Hall started April 1, 2026, removing the 1960s addition and then about 200 feet of the original 1904 building. The August 2026 newsletter says crews reclaimed the original bricks and will use them to rebuild the east facade.
- Utility relocations and clearing on both sides of the river. In Covington, Third Street reopened on September 14 after extensive utility relocation, according to the September 30 newsletter.
- Retaining walls on the Kentucky side. The project's construction update page says crews are building new walls on the west side of the interstate, one to stabilize the hillside and one to support the highway, to make room to tie the new bridge into the existing road.
- Ramps and approaches in Ohio. A temporary ramp from southbound I-75 to Third Street opened September 27. The construction update page says work around Second Street will build structures connecting the companion bridge to the street grid and free up nearly 11 acres of land for future development.
The river work has started. The July 31 newsletter reported the first concrete pour for the companion bridge foundation in July. The construction update page says crews are building the Pete Rose Pier as a working dock to move materials and equipment, and that construction will soon begin on one of the first pylons on the Kentucky side, with barges and temporary work platforms visible from the river.
Marine foundation work on a navigable river is a different discipline from land-based bridge work. The Ohio is a working commercial waterway, so barge and crane operations have to coexist with towboat traffic, and river stage changes what can be done on a given day. The project's own July newsletter included a 1961 photo of a crane barge driving steel sheet piling for a cofferdam at one of the original bridge's piers, the same basic method of keeping water out of a foundation excavation that river crews still use.
Why build everything at once instead of the bridge first? The August newsletter put it plainly: if the companion bridge were built first and everything else followed in sequence, the finished structure would sit unconnected for years. The design and management teams have spent nearly 2 million hours planning the construction sequence, according to that newsletter.
Staffing 6 million hours
The state release puts this phase at approximately 6 million hours of work and more than 700 skilled tradespeople, with the workforce potentially reaching 1,000 at peak.
Six million hours spread from spring 2026 to substantial completion of the approaches in 2033 is a sustained draw on two regional labor markets. Ironworkers, operating engineers, pile drivers, laborers, carpenters and cement masons all come out of the same Cincinnati and Northern Kentucky hiring pool that every other highway job in the area is drawing from. The project's September newsletter profiled J&B Steel Erectors, a woman-owned rebar installer, whose owner said the job lets the firm keep union ironworkers employed close to home. Contractors chasing subcontract packages here should model labor availability, not just the wage rate. For a regional baseline on that labor pool, see our Ohio state construction dashboard and the Kentucky dashboard.
The night-work profile compounds it. Closures that take effect at 10 and 11 p.m. and lane restrictions timed around commuter volumes mean a meaningful share of hours fall outside a standard day shift. If you are pricing a package on this corridor, that shift structure goes straight into labor cost; the overtime calculator is a quick way to see what a night-heavy schedule does to a bid.
Working beside live traffic is also the hazard that defines this job. Crews building approach structures are working next to an interstate carrying about 160,000 vehicles a day, which is why so much of the schedule moves into low-volume windows. The permanent closures in June and July are not just traffic management. They are how the contractor takes ground away from moving vehicles and turns it into a work zone. Our guide to federal highway work zone safety rules covers the standards that apply.
The project team is also running outreach aimed at smaller firms. The September newsletter announced a free six-week workshop series for small businesses and emerging heavy civil contractors, held Tuesdays from October 6 through November 17, 2026 at the project office in Longworth Hall.
Why it matters
This corridor is one of the country's worst freight bottlenecks, and the project will keep generating subcontract and supplier procurement across Ohio and Kentucky for years: foundations, structural steel, rebar, precast, retaining walls, paving, drainage, electrical and signing. A grant-funded design-build package of this size cascades into hundreds of smaller awards.
It is also one of the largest single draws on the IIJA's dedicated bridge money. Its $1.385 billion BIP grant was the biggest of the FY 2022 large bridge awards in FHWA's report. For the national picture, see our tracker of every major US bridge project and how IIJA bridge formula money is moving past the halfway mark. For more on how public money is moving through state programs, see Buildermuse's public works coverage.
What happens next
Through the rest of 2026 and into 2027: foundation and pylon work in the river, more approach structures and retaining walls, and continued utility relocation. Expect more ramp and lane changes announced on short notice with late-evening start times; that has been the pattern since June.
The companion bridge is expected to open to traffic in 2031, with approach work substantially complete in 2033, pending weather and schedule, according to the fact sheet. Rehabilitation of the 1963 bridge follows, on a schedule and budget the states have not yet set.
FAQ
How much does the Brent Spence Bridge project cost?
The current construction phase is $4.05 billion, per the May 8, 2026 state groundbreaking release. Construction Dive reported in March 2026 that the overall estimate rose to $4.4 billion, up about $700 million from the earlier $3.6 billion figure. Future phases, including rehabilitation of the existing bridge, have not been priced.
How much federal money is in the project?
$1.635 billion in federal grants, awarded in December 2022. FHWA lists $1.385 billion of that as a Bridge Investment Program large bridge grant. The rest of the cost is split between Ohio and Kentucky.
Who is the contractor on the Brent Spence Bridge Corridor?
The Walsh Kokosing joint venture (Walsh Construction and Kokosing Construction) is the design-builder. AECOM is lead designer, Jacobs is the Independent Companion Bridge Engineer, and Parsons is the independent design quality firm, per the project fact sheet.
Will the new Brent Spence bridge have tolls?
No. Ohio and Kentucky structured the funding with federal grants and state money so drivers will not pay a toll.
When will the companion bridge open?
The companion bridge is expected to open in 2031, with approach work substantially complete by 2033.
How many workers will the project employ?
The states estimate about 6 million hours of work and more than 700 skilled tradespeople, possibly reaching 1,000 at peak construction.



