Flood Infrastructure Construction Hits $16.5B Pace

Lisa Chen·April 10, 2026·Updated October 18, 2026·10 min read

Share this with your estimator.

Flood Infrastructure Construction Hits $16.5B Pace

The cleanest public measure of flood-control construction is the Census Bureau's "conservation and development" category, which covers non-power dams, levees, locks, dikes, sea walls, bulkheads, tide gates, jetties, erosion control and dredging. Public spending in that category ran at a seasonally adjusted annual rate of $16.5 billion in August 2026 (preliminary), up from $12.9 billion in August 2025, an increase of about 28% (Census Value of Construction Put in Place, public SAAR table, August 2026 release). Federal owners, mostly the U.S. Army Corps of Engineers, accounted for $10.4 billion of that rate, and state and local governments for $6.1 billion.

That is not all flood work. Dredging for navigation and ecosystem projects sit in the same category, and a lot of urban flood control is built as stormwater and drainage under the sewer category. But it is the closest dated number available, and it is moving in the right direction for heavy civil contractors.

The federal grant side has been less steady. FEMA's main pre-disaster mitigation program was canceled in April 2025, ordered restored by a federal court, and reopened in 2026 at a smaller scale. This article sorts out where the money comes from now, what the large projects look like, and what the work involves.

Where Flood Construction Money Comes From

Army Corps of Engineers

The Corps builds and funds most large federal flood risk management projects: levees, floodwalls, channels, diversions, pump stations and coastal storm risk projects. The Infrastructure Investment and Jobs Act gave the Corps $17.1 billion in emergency appropriations, according to the Congressional Research Service (CRS Insight IN11723, updated April 18, 2025). CRS lists $2.55 billion of that for coastal flood risk management and $2.50 billion for inland flood risk management, plus $251 million for Flood Control and Coastal Emergencies repairs to existing projects, including non-federal levees. About 68% of the total went to the Corps' Construction account.

Corps project funding is allocated through annual work plans and, for IIJA money, through published spend plans and addendums. Those documents list projects by name, so they are the best place to find out what will reach bid in your district.

FEMA mitigation grants

FEMA's Building Resilient Infrastructure and Communities (BRIC) program funded pre-disaster mitigation projects, including drainage and flood protection. Its status over the past 18 months, per CRS Insight IN12609 (June 30, 2026):

  • April 4, 2025: FEMA announced it was ending BRIC and said about $882 million in IIJA funding would be returned to the Treasury or reapportioned by Congress. FEMA's FY2024 notice of funding opportunity, issued January 6, 2025 with $750 million available, had already been retracted in mid-February 2025.
  • April 16, 2025: FEMA said it would cancel FY2020 through FY2023 projects whose funds had not been distributed. Obligated projects already under construction could finish.
  • December 11, 2025: A federal judge in Massachusetts ruled the termination unlawful and issued a permanent injunction. The ruling does not require any particular grant and does not stop FEMA from replacing BRIC with a different program.
  • March 6, 2026: The court ordered FEMA to enforce the ruling and to issue the FY2024 funding notice.
  • FEMA then issued a single combined FY2024 and FY2025 notice with $1 billion available, closing July 23, 2026.

The IIJA had added $1 billion to BRIC, $200 million a year for FY2022 through FY2026. Contractors should treat BRIC-funded projects as possible but slow: awards from the 2026 round will take time to reach design and bid, and the program's long-term future is still a policy question.

FEMA's Flood Mitigation Assistance program followed a similar path. Its FY2024 notice, which offered $600 million, opened January 6, 2025 and was retracted February 14, 2025; a January 2026 CRS insight (IN12642) found no new FMA awards in FY2024 through FY2026 at that point. Check FEMA's FMA page and Grants.gov for any reissued notice before planning around FMA money. The Hazard Mitigation Grant Program, which follows presidential disaster declarations, continues to fund buyouts, elevations and local flood projects in declared areas.

State programs

States with their own flood funds are a steadier source. Texas is the largest example. The Texas Water Development Board's Flood Infrastructure Fund, approved by voters through a constitutional amendment, lists 118 committed projects and $830 million committed on its program page (accessed October 18, 2026). The Legislature added more than $624 million from general revenue in 2023 (Senate Bill 30, 88th Legislature), and TWDB's draft intended use plan for state fiscal years 2026-27, dated May 13, 2026, offers at least $312.4 million in grants and zero-interest loans.

Other coastal and river states run their own programs through bond acts, coastal authorities and resilience offices. Check your state's water development or emergency management agency for current funding rounds; the dollar amounts change every budget cycle.

Major Projects That Show the Scale

Fargo-Moorhead Area Diversion

The $3.2 billion Fargo-Moorhead diversion is a 30-mile channel that routes Red River floodwater around the metro area. The Forum of Fargo-Moorhead (January 14, 2026) reported the project was about 80% complete at the start of 2026, with 80% of channel excavation done, and that the Diversion Authority approved a $1 billion cash budget for 2026, about $774 million of it in milestone payments to builders. The authority's executive director called 2026 the last year of major construction, with substantial completion expected by fall 2026 so the system can operate in a 2027 flood. The river was rerouted through the control structure in August 2025.

Coastal Texas Project

The Coastal Texas Project, aimed at storm surge protection for the Houston-Galveston region, carries an estimated cost of $34.38 billion, according to the Texas Comptroller's Fiscal Notes (May 2024). The Galveston Bay Storm Surge Barrier System, including the Bolivar Roads gate system at the bay entrance, accounts for $31.20 billion, with a federal share of $19.41 billion and a non-federal share of $11.79 billion. As of that report the project was authorized but not funded for construction; it needs a federal "new start" designation, which in turn requires preliminary engineering design. Treat it as a long-horizon opportunity, not a near-term bid.

What Flood Construction Involves

Levees

New and rebuilt levees are mostly earthwork: borrow sourcing, stripping, foundation preparation, fill placed in controlled lifts and compacted to the density the specifications call for, with field density testing on every lift. Quality control matters because one weak reach can compromise an entire system.

Modern levee work often adds seepage cutoff walls (soil-bentonite, cement-bentonite or soil-cement slurry walls), relief wells and toe drains to handle underseepage, overtopping protection such as turf reinforcement mats or articulated concrete block, and instruments like piezometers and settlement plates. The equipment spread is classic heavy civil: scrapers, articulated trucks, dozers with GPS grade control, pad-foot and smooth-drum rollers, plus slurry wall rigs where cutoffs are required.

Floodwalls

Where there is no room for an earthen levee, owners build floodwalls. I-walls and T-walls in reinforced concrete, often on driven piles or drilled shafts, are common in urban reaches. Steel sheet pile walls with concrete caps are used where driving conditions allow.

Pump stations and gates

When gates close, rainwater on the protected side has to be pumped out. Flood pump stations involve deep excavation and dewatering, mass concrete for wet wells and intakes, large mixed-flow or axial-flow pumps, switchgear and motor controls, and backup generation. Gate structures and tide gates add heavy steel fabrication and mechanical work. These are the highest-value pieces of most flood systems per square foot and need tight coordination between civil, mechanical and electrical subs.

Nature-based features

Both the Corps and FEMA now encourage nature-based features in flood projects: living shorelines, marsh restoration, floodplain reconnection and constructed wetlands. The work calls for contractors comfortable working in water and wetlands, with native plant materials and with environmental monitoring requirements. It is a smaller market than levees and walls, but it shows up more often as a component inside larger contracts.

Insurance and Local Incentives

FEMA's Community Rating System gives flood insurance premium discounts of 5% to 45% in participating communities, and more than 1,500 communities take part, according to FEMA's CRS page (updated October 5, 2026). Communities earn credit for floodplain management activities, including maintaining flood protection and drainage systems. That gives local governments a financial reason to fund flood projects even when federal grants are uncertain, and it is part of why local drainage bonds and stormwater fees keep showing up on ballots. Our stormwater infrastructure analysis covers the drainage side of the same problem.

How Contractors Can Position for Flood Work

Get on Corps district bidder lists and watch SAM.gov for Corps solicitations under flood risk management projects in your area. Some levee and floodwall work is let as small business set-asides or through multiple-award task order contracts, so check the set-aside status on each notice.

Read the Corps work plan each spring. It names the projects that received construction money that fiscal year, and those are the ones that will be advertised.

Follow state flood funds. Texas posts its intended use plan and commitments; other states publish similar lists. Local sponsors that receive state money still have to bid the work.

Treat FEMA-funded projects as slower. Grant obligations, environmental review and benefit-cost documentation add months before a project reaches bid, and the program changes of 2025 and 2026 added more uncertainty.

For dam rehabilitation, a related market with overlapping crews and equipment, see our dam safety analysis.

Frequently Asked Questions

How much is spent on flood infrastructure construction?

The Census Bureau's public conservation and development category, which includes dams, levees, sea walls, tide gates and dredging, ran at a $16.5 billion seasonally adjusted annual rate in August 2026, up about 28% from a year earlier. Federal projects accounted for $10.4 billion of that. Urban drainage built under sewer and stormwater budgets is counted separately.

Is FEMA's BRIC program still running?

FEMA ended BRIC on April 4, 2025, but a federal court ruled the termination unlawful on December 11, 2025 and enforced that ruling on March 6, 2026. FEMA then issued a combined FY2024 and FY2025 funding notice with $1 billion available, which closed July 23, 2026. The court did not bar FEMA from replacing BRIC with a different program in the future.

How much did the infrastructure law give the Army Corps for flood control?

The IIJA provided $17.1 billion to the Corps in total. CRS lists $2.55 billion for coastal flood risk management, $2.50 billion for inland flood risk management and $251 million for emergency repairs to existing flood projects.

Which states have their own flood funding programs?

Texas has the most visible one: its Flood Infrastructure Fund lists $830 million committed to 118 projects, and the draft 2026-27 plan offers at least $312.4 million more. Other coastal and river states fund flood work through bond acts and coastal authorities; check your state's water or emergency management agency for current rounds.

When will the Fargo-Moorhead diversion be finished?

Project leaders expected substantial completion by fall 2026, with the system ready to operate in a 2027 flood, according to January 2026 reporting by the Forum of Fargo-Moorhead. The project cost is $3.2 billion.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
map

See infrastructure spending data for your state

Federal contract awards, top contractors, and spending trends — all 50 states.

View your state