Grid construction is a much bigger market than most contractors assume. The Edison Electric Institute's September 2025 functional projection puts investor-owned utility capital spending for 2025 at $37.6 billion on transmission and $66.0 billion on distribution, a combined $103.6 billion, out of $207.9 billion in total capital expenditures. That total is itself a record. EEI's industry chart shows actual investor-owned utility capex of $178.2 billion in 2024 and projects $220.7 billion in 2026, rising to $248.4 billion in 2029, for roughly $1.1 trillion over 2025 through 2029.
An older figure still circulates: about $28 billion a year. That number matches the U.S. Energy Information Administration's estimate of transmission spending alone by major utilities, $27.7 billion in 2023 in real 2023 dollars (EIA Today in Energy, November 18, 2024). The same EIA analysis put distribution capital spending at $50.9 billion that year. Neither figure is total grid spending, and both are now a year or more behind the utility capital plans.
This piece walks through where the money is going, what the Census Bureau shows on the construction side, and the two constraints that set the pace of the work: equipment lead times and line crews.
How Big the Grid Construction Market Actually Is
There are three useful public measures, and they count different things.
| Measure | Latest value | What it covers |
|---|---|---|
| EEI IOU transmission capex | $37.6B (2025 projection, Sept 2025) | Investor-owned utilities only |
| EEI IOU distribution capex | $66.0B (2025 projection, Sept 2025) | Investor-owned utilities only |
| EIA major-utility transmission spending | $27.7B (2023, real 2023 $) | FERC Form 1 filers |
| EIA major-utility distribution capital spending | $50.9B (2023, real 2023 $) | FERC Form 1 filers |
| Census private construction, electric | $141.2B SAAR (Aug 2026, preliminary) | Generation, transmission and distribution structures |
Sources: EEI Industry Capital Expenditures (updated September 2025); EIA, November 18, 2024; Census Bureau Value of Construction Put in Place, private seasonally adjusted annual rate table, August 2026 release.
The Census line is the one that measures construction put in place rather than utility budgets. Private electric construction ran at a $141.2 billion seasonally adjusted annual rate in August 2026, up from $127.4 billion in August 2025, an increase of about 11%. The broader Census power category, which also includes oil and gas structures such as pipelines, was $186.0 billion SAAR in August 2026 across private and public owners (FRED series TLPWRCONS), versus $171.4 billion a year earlier. Annual totals of the unadjusted power series tell the longer story: roughly $118 billion a year from 2019 through 2021, then $151 billion in 2023, $168 billion in 2024 and $172 billion in 2025 (FRED TLPWRCON, summed monthly values).
Keep in mind the Census electric category includes power plants as well as lines and substations, and EEI's functional chart puts generation at $63.2 billion, or 30%, of 2025 projected IOU capex. Public power systems and co-ops sit outside EEI's numbers, so the true national total for wires and substations is higher than the $103.6 billion IOU figure.
Where Transmission and Distribution Money Goes
Distribution: the largest slice
Distribution has been the biggest line in utility capital budgets for years. EEI's functional chart shows distribution at 32% of projected IOU capex in both 2024 ($59.8 billion) and 2025 ($66.0 billion). EIA's two-decade analysis reached the same conclusion from the other direction: distribution capital spending was the main driver of the rise in total utility spending between 2003 and 2023.
For contractors, distribution work means pole replacement, reconductoring, underground conversions, new feeders and distribution substations, and the automation hardware (reclosers, switches, sensors) that utilities are adding for faster fault isolation. It is steady, high-volume work, often let through multi-year alliance or master service agreements rather than one-off bids.
Transmission: bigger projects, longer lead times
Transmission was 18% to 19% of projected IOU capex in EEI's 2024 and 2025 functional charts ($35.9 billion and $37.6 billion). EIA found transmission spending nearly tripled between 2003 and 2023 and rose $2.7 billion (11%) in 2023 alone, mostly from station equipment, poles and software for regional markets.
Transmission work ranges from rebuilding existing lines on the same right-of-way to new high-voltage corridors and interstate HVDC lines. The new corridors get the headlines, but rebuilds and substation expansions make up much of the volume.
Federal grants
The Infrastructure Investment and Jobs Act created DOE's $10.5 billion Grid Resilience and Innovation Partnerships (GRIP) program. DOE's program page (accessed October 18, 2026) lists up to $3.46 billion announced in the first round (October 18, 2023), about $4.2 billion in the second (October 18, 2024), and nearly $2 billion for a third funding opportunity announced March 12, 2026. Those dollars require cost share and flow through utilities, so contractors see them as utility work, not as direct federal contracts.
How a Transmission Line Gets Built
The sequence is broadly the same on most overhead lines, though crew size and equipment change with voltage and terrain.
Right-of-way and access. Crews clear vegetation inside the easement, build temporary access roads and pads strong enough for cranes and drill rigs, and set up material yards. Wetland mats, erosion control and environmental monitoring are often a large share of the early cost on greenfield routes.
Foundations. Lattice towers typically sit on four separate footings; tubular steel poles usually sit on a single drilled shaft. Geotechnical conditions drive the design, so foundation scope is one of the least predictable items in an early estimate. Rock, high groundwater and poor soils all show up here first.
Structure erection. Lattice towers are assembled on the ground and lifted in sections, or built up piece by piece. Steel poles are set in one or several sections with cranes. Helicopters are used in rough terrain.
Wire stringing. Conductor and shield wire are pulled through travelers with puller-tensioner rigs, then sagged, clipped in and spaced. Road, river and energized-line crossings need guard structures and outage coordination, and those crossings often set the pace of this phase.
Termination and energization. The line ties into substations at both ends, where relay settings, protection testing and commissioning have to line up with the utility's outage schedule.
Per-mile costs vary too much by voltage, terrain, structure type and land cost for a national average to be useful. Regional transmission organizations publish planning-level unit costs (MISO's Transmission Cost Estimation Guide is the most widely used example); check that you have the current edition before using any number from it.
The Two Bottlenecks: Equipment and Crews
Transformer and switchgear lead times
Wood Mackenzie's September 2025 report with American Clean Power, Making the Connection: Meeting the Electric T&D Supply Chain Challenge, put average Q2 2025 lead times at 128 weeks for power transformers, about 143 weeks for generator step-up transformers and about 44 weeks for switchgear. (POWER magazine, January 2, 2026, reported the GSU figure from the same survey as 144 weeks.) POWER also reported, from Wood Mackenzie data, that power transformer prices were up 77% since 2019.
The BLS producer price index for electric power and specialty transformer manufacturing (PCU335311335311) was 475.1 in September 2026, preliminary, versus 255.5 in January 2020, an 86% rise. That is an index, not a dollar price, but the direction is clear. For more on how this plays out inside the fence, see our substation construction cost breakdown.
The practical effect: on many projects the transformer, not the field work, sets the energization date. Utilities are ordering long-lead equipment before final project approvals, and contractors who can show they understand owner-furnished equipment schedules have an edge at prequalification.
Line workers
The Bureau of Labor Statistics May 2025 Occupational Employment and Wage Statistics put the national median wage for electrical power-line installers and repairers (SOC 49-9051) at $45.83 an hour, or $95,320 a year. That is well above the $30.38 median for electricians in the same survey. Storm work, per diem and overtime raise actual earnings on many transmission jobs, but there is no reliable public average for those totals.
Line work is a long apprenticeship trade, so crew supply responds slowly to demand. Large transmission projects compete with storm restoration and distribution programs for the same people, and contractors who keep crews year-round through utility service agreements are in the best position to staff a new line.
Interconnection Queues and Planning Reform
Lawrence Berkeley National Laboratory's Queued Up: 2025 Edition (published December 2025, data through the end of 2024) counted about 10,300 active interconnection requests totaling roughly 2,290 GW: 1,400 GW of generation and 890 GW of storage. Active queue capacity fell 12% in 2024 as more than 700 GW withdrew and about 500 GW of new requests came in. The typical project built in 2024 took 55 months from interconnection request to commercial operation, compared with 36 months in 2015 and 22 months in 2008. Only about 408 GW of the active total had a draft or executed interconnection agreement.
For contractors, the number to watch is the projects with signed agreements, because each one that proceeds needs a point-of-interconnection substation, a short tie line and often network upgrades.
Two FERC rules shape the pipeline. Order No. 2023, issued in July 2023, moved interconnection to a cluster-study, first-ready-first-served process meant to clear speculative requests out of the queue. Order No. 1920, issued May 13, 2024, requires transmission providers to plan regionally over at least a 20-year horizon and to revisit those plans at least every five years; Order No. 1920-A in November 2024 gave states a larger role in scenario development and cost allocation. Compliance filings under these rules are still working through the regions, so their effect on actual construction starts will show up over several years.
What Contractors Should Do With This
Watch the utility capital plans in your territory, not national averages. Every investor-owned utility publishes multi-year capex guidance in its earnings materials, and the T&D split is usually broken out. Rate case filings list specific programs such as pole replacement, undergrounding and substation rebuilds.
Pull your ISO or RTO's transmission expansion plan and sort it by in-service year. Projects scheduled for 2028 and 2029 are being designed and procured now, and their transformers are already on order or should be.
Get on master service agreements. Much distribution work is never publicly bid. Prequalification, safety record and the ability to field crews on short notice for storms count for more than price on these contracts.
Price escalation into multi-year bids. With transformer and switchgear prices still rising on the BLS index, fixed-price bids that run past 2027 need escalation clauses or owner-furnished major equipment.
For the federal side of infrastructure funding more broadly, see our IIJA contractor guide.
Frequently Asked Questions
How much do utilities spend on grid construction each year?
Investor-owned utilities projected $37.6 billion for transmission and $66.0 billion for distribution in 2025, according to EEI's September 2025 functional capex chart, out of $207.9 billion in total capital spending. Public power and co-ops add to that. On the construction side, the Census Bureau put private electric construction at a $141.2 billion annual rate in August 2026, a category that also includes power plants.
Is the $28 billion figure correct?
Only as a transmission number. EIA estimated transmission spending by major utilities at $27.7 billion in 2023 (real 2023 dollars). It does not include distribution, which EIA put at $50.9 billion in capital spending that year, and it predates the larger 2025 utility capital plans.
How much federal funding goes to grid construction?
DOE's GRIP program, created by the Infrastructure Investment and Jobs Act, totals $10.5 billion. DOE announced up to $3.46 billion in October 2023, about $4.2 billion in October 2024, and nearly $2 billion for a third funding opportunity in March 2026. That is small next to utility capital budgets, which are recovered through rates.
How long are transformer lead times?
Wood Mackenzie's Q2 2025 survey, published with American Clean Power in September 2025, averaged 128 weeks for power transformers, roughly 143 weeks for generator step-up units and about 44 weeks for switchgear.
What do line workers earn?
BLS reports a May 2025 national median of $45.83 an hour ($95,320 a year) for electrical power-line installers and repairers. Pay on transmission projects varies with overtime, travel and union agreements.
How long does it take to get a new generator connected to the grid?
LBNL found the typical project built in 2024 took 55 months from interconnection request to commercial operation, up from 36 months in 2015.



