AI Training Facilities: The Next Wave of Data Center Construction
Data centers have gone through several build cycles: enterprise server rooms, colocation, cloud, and hyperscale. The current cycle is driven by buildings designed around clusters of AI accelerators, and it changes what the trades actually install. Power per rack is higher, cooling moves from air to liquid, and the schedule is set by when the switchgear and transformers show up rather than when the concrete cures.
This article sticks to what can be sourced. Where a number appears, the source and date are named. Where the industry talks in round numbers nobody can trace, we have left the number out.
How big the AI buildout is right now
The best public measure of U.S. data center construction is the Census Bureau's value-put-in-place series. Census put private data center construction at a seasonally adjusted annual rate of $84.95 billion in August 2026, up 73.2% from a year earlier. Over the same period total U.S. construction spending was down 1.7% year over year, so data centers are one of the few categories growing while the rest of nonresidential work is flat or shrinking.
On the leasing side, CBRE's H1 2026 North American Data Center Trends report (released August 27, 2026) counted 7,481 MW under construction across eight primary markets, up 24.8% and above the previous record set in 2024. More than 80% of that capacity was already preleased, up from 74.3% a year earlier, and primary-market vacancy sat at 1.4%. In plain terms, most of what is being built has a tenant before it is finished.
The money behind this comes largely from four companies. Based on guidance given in late April 2026 earnings calls, as compiled by The Wealth Advisor (April 30, 2026), 2026 capital spending plans were roughly:
| Company | 2026 capex guidance (April 2026) |
|---|---|
| Alphabet | $180–190 billion |
| Amazon | approaching $200 billion |
| Microsoft | about $190 billion (calendar 2026) |
| Meta | $125–145 billion |
That adds up to roughly $725 billion at the top of the ranges. Alphabet then raised its 2026 range to $195–205 billion with its July 2026 results, according to coverage of that report. These are company-wide capital budgets. They include servers and chips, not just buildings, and they include spending outside the United States, so do not treat them as construction volume. They do tell you the owners have the cash and intend to keep spending through 2026.
For a fuller breakdown of who is spending what, see our hyperscaler capex coverage and the running data center permit tracker.
Power density: what actually changes
The defining difference in an AI training hall is power per rack. Uptime Institute's 2026 Global Data Center Survey (released July 28, 2026) describes average rack densities as rising slowly, with a growing number of operators reporting peak densities of 30 kW or more. Most of the installed base is still well below that.
AI training racks sit far above the average. The power and cooling reference design Vertiv developed with NVIDIA for the GB200 NVL72 platform, announced in October 2024, supports up to 132 kW per rack, and each of those racks holds 72 GPUs and 36 CPUs. Schneider Electric published a comparable reference architecture for the same platform. A hall built around racks like that carries several times the electrical and heat load per square foot of a conventional colocation hall.
That density works its way through every trade:
- Electrical: more and larger feeders, busway instead of whips in many designs, more transformers and switchgear per square foot of white space, and more medium-voltage work on site.
- Mechanical: heat has to leave the rack in liquid, which means coolant distribution units (CDUs), secondary fluid loops to every rack, and heat rejection plant sized for the full load.
- Structural: liquid-cooled racks with their manifolds and coolant are heavy, and the designer's floor loading and slab design have to account for that. Get the actual design loads from the structural drawings for your project; they vary by owner and rack generation.
Cooling: the move to liquid
At 100-plus kilowatts per rack, air alone cannot carry away the heat. The reference designs above use direct-to-chip liquid cooling, in which cold plates sit on the processors and coolant runs through manifolds in each rack, with CDUs separating the facility water loop from the technology loop. Vertiv describes its design as a hybrid that still uses air for the remaining load.
For a mechanical contractor, the scope change looks like this:
- Far more piping inside the white space, much of it stainless or other clean pipe, installed to cleanliness and pressure-test standards closer to process piping than to comfort HVAC.
- Water treatment and fluid chemistry management as part of the commissioning scope, since corrosion or fouling in a technology loop affects the owner's equipment directly.
- Leak detection at connections and under equipment, tied into the building management system.
- Redundant pumping and controls so a single failure does not take down a hall.
Cushman & Wakefield's 2026 Data Center Development Cost Guide, as reported by CRE Daily on August 27, 2026, found cooling equipment costs up 32% between December 2021 and early 2026. For more on the mechanical side, see our piece on liquid cooling in data centers.
What it costs to build
Old versions of this article carried a per-megawatt cost table split between "traditional" and "AI" facilities. We could not trace those figures to any published source, so they are gone. What is published:
Cushman & Wakefield's 2026 Data Center Development Cost Guide (covered by IREI on August 20, 2026 and by CRE Daily on August 27, 2026) puts all-in greenfield development cost at $8.9 million to $23.3 million per MW in the U.S. and Canada, excluding chips and GPUs. Costs rose an average of 21% per MW since the guide's previous edition in Q4 2024. The guide breaks the greenfield budget into shares that are useful for estimators:
- Power infrastructure: 21%
- Core and shell construction and sitework: 17%
- Contingencies: 16%
- Site acquisition: 7%
It also tracked equipment price increases from December 2021 to early 2026: switchgear up 60%, copper up 46%, generators and motors up 33%, cooling equipment up 32%, and transformers up 29%. The most expensive markets to build in were Silicon Valley, Chicago, New York, Northern New Jersey, Toronto and Los Angeles; Texas markets were among the cheapest.
The guide does not split out AI training halls as a separate category, so there is no reliable public "AI premium" per megawatt. In practice, higher rack density concentrates more electrical and mechanical cost into the same footprint, which is why the power share of the budget is the largest single line. For square-foot figures, our data center construction cost per square foot article covers the sourced benchmarks.
Schedule: long-lead gear sets the pace
AI owners want capacity energized when their hardware arrives, and the hardware is not the constraint most contractors need to worry about. The electrical gear is. Cushman & Wakefield's 2026 guide reported lead times of 68 to 113 weeks for pad-mounted transformers, 60 to 100 weeks for generators, and 38 to 63 weeks for medium-voltage switchgear.
Those numbers drive how these projects are delivered:
- Owners and GCs pre-purchase major electrical equipment, often before the building is fully designed.
- Design and construction overlap, with early packages for sitework, foundations and underground utilities released while the halls are still being detailed.
- Prefabricated power skids, modular electrical rooms and factory-built CDU assemblies move work off site where they can.
- Halls are commissioned and turned over in phases while construction continues next door.
If you are bidding electrical or mechanical scope, ask early who is buying the long-lead gear, when it is scheduled to ship, and what your contract says if it is late. Our guide to data center power gear lead times goes deeper on sequencing.
The trades that are hardest to find
The labor question is real but often exaggerated with invented wage numbers. What the federal data shows: the BLS May 2025 Occupational Employment and Wage Statistics put the national median for electricians at $30.38 an hour. Average hourly earnings across all construction production and nonsupervisory jobs were $41.69 in September 2026 (BLS Current Employment Statistics). Mission-critical work often pays above these medians, especially on union projects and with overtime, but we have not found a reliable published rate specific to AI data center trades.
The skills in shortest supply on AI halls are:
- Pipefitters and welders who can do clean, pressure-tested process-grade piping for liquid cooling loops.
- Electricians comfortable with medium-voltage terminations, switchgear, busway and paralleling gear.
- Commissioning agents and technicians who understand both the power train and the liquid cooling plant, because integrated systems testing on these buildings is long and unforgiving.
- Controls technicians who can integrate power monitoring, cooling, leak detection and fire alarm into one platform.
Operators feel it too. Uptime's 2026 survey found more than half of respondents had difficulty finding qualified candidates for open positions. For the trade-by-trade view, see the skilled trades shortage hitting data centers.
Where the work is
CBRE's H1 2026 report is the cleanest public snapshot of where capacity is going up. Atlanta had 2,882 MW under construction, the most of any primary market and the first time it has led the country, ahead of Northern Virginia at 2,420 MW. Northern Virginia still has by far the largest inventory, 4,496.5 MW, with vacancy of 0.2%. Inventory in the other primary markets CBRE tracks was Atlanta 1,803.2 MW, Dallas-Fort Worth 1,432.8 MW, Phoenix 1,069.2 MW, Chicago 910.6 MW, Silicon Valley 509.2 MW, Hillsboro, Oregon 491.4 MW, and New York/Tri-State 190.0 MW.
Beyond the primary markets, Cushman & Wakefield's 2026 guide estimated about $492 billion of North American data center development under construction and $1.8 trillion planned or precommitted, with frontier-market spending projected to grow from $91 billion under construction to $631 billion planned and precommitted. That is where much of the next round of large AI campuses is landing: places with land and a utility willing to serve hundreds of megawatts. Our Georgia data center market and Indiana pieces cover two of them.
What to do with this
For a contractor deciding whether to chase AI data center work, the practical takeaways are:
- Most of the work flows through a short list of national GCs. Prequalify with them before a project is announced. See the largest data center construction companies for who they are.
- Build credentials in the scopes that are scarce: process-grade piping, medium-voltage electrical, and commissioning.
- Read the procurement and schedule terms closely. With transformer lead times measured in years, delay risk belongs with whoever controls the equipment purchase.
- Watch the Census monthly spending release and the CBRE semiannual report. If preleasing drops or construction starts slow, the pipeline will show it there first.
The semiconductor fab construction market is the closest parallel: another building type where process piping, utility capacity and equipment delivery drive the schedule.
READ NEXT: Tracking Every Data Center Permit Filed in 2026
FAQ
How much more power does an AI training rack draw than a typical rack?
A lot more. Uptime Institute's 2026 survey describes average rack densities rising slowly, with a growing share of operators reporting peaks of 30 kW or more. The Vertiv and NVIDIA reference design for the GB200 NVL72 platform supports up to 132 kW per rack. That gap is why AI halls need liquid cooling and far more electrical infrastructure per square foot.
What does an AI-capable data center cost per megawatt?
Cushman & Wakefield's 2026 Data Center Development Cost Guide puts all-in greenfield cost at $8.9 million to $23.3 million per MW in the U.S. and Canada, excluding chips and GPUs, up an average of 21% since late 2024. The guide does not publish a separate AI-only figure, so be wary of anyone quoting a precise "AI premium."
What are the lead times for switchgear and transformers?
Cushman & Wakefield's 2026 guide reported 38 to 63 weeks for medium-voltage switchgear, 68 to 113 weeks for pad-mounted transformers, and 60 to 100 weeks for generators. Confirm current quotes with your suppliers, since lead times shift with factory backlogs.
How much are the big tech companies spending in 2026?
Based on April 2026 guidance, Alphabet planned $180–190 billion (raised to $195–205 billion in July), Amazon about $200 billion, Microsoft about $190 billion and Meta $125–145 billion. These are total capital budgets including servers and chips and spending outside the U.S., not construction spending.
How does a regional subcontractor get onto these projects?
Through the national GCs that run hyperscale programs, not by contacting the owner directly. Get prequalified with those GCs before projects are announced, and lead with documented mission-critical work, safety records, and capacity in medium-voltage electrical, process piping or commissioning. Our guide on how subcontractors win data center work walks through the process.



