ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Commercial

2026 Data Center Construction Forecast: What's Coming Next

Lisa Chen·April 10, 2026·Updated October 18, 2026·10 min read

Share this with your estimator.

2026 Data Center Construction Forecast: What's Coming Next

Data center construction in the U.S. is running far ahead of what most 2026 forecasts expected. The Census Bureau's construction spending release covering August 2026 put private data center construction at a seasonally adjusted annual rate of $84.95 billion, up 73.2% from $49.05 billion in August 2025. That figure is preliminary and will be revised, but the direction has been consistent all year.

An earlier version of this article said data center construction was about $32 billion in 2025 and forecast $35 billion for 2026, with a table attributing 2025 and 2026 estimates to Turner & Townsend, JLL, CBRE and Dodge. We could not find those figures in any of those firms' publications, and they are far below the Census numbers. We also removed a regional spending table, liquid cooling adoption percentages, a megawatt demand series, switchgear lead times, utility queue sizes and a workforce estimate that had no traceable source. What remains below is either Census data or a named forecast with a date.

What the Census Numbers Show

The Census Bureau tracks data center construction as a subcategory of private office construction in its monthly value of construction put in place. Annual totals (not seasonally adjusted) from the Census private construction table:

Year Data center construction put in place
2022 $12.6B
2023 $20.0B
2024 $34.8B
2025 $49.7B
Jan-Aug 2026 $45.2B (vs. $31.9B Jan-Aug 2025, +41.7%)

Source: U.S. Census Bureau, Value of Private Construction Put in Place, table data through August 2026 (preliminary).

The monthly annual-rate series shows the acceleration through 2026. The seasonally adjusted annual rate was $56.2 billion in January 2026, $58.1 billion in March, $65.7 billion in May, $72.7 billion in June, $79.0 billion in July and $84.95 billion in August.

Two things to keep in mind. Census measures construction put in place each month, so it lags announcements and does not count servers, GPUs or most IT equipment. And the most recent months are revised as more survey responses come in.

For context, total U.S. construction spending was $2.20 trillion at an annual rate in August 2026, down 1.7% from a year earlier, and manufacturing construction was down 19.8%. Data centers are growing inside a flat-to-down market. Our construction spending forecast covers the overall numbers, and the data center construction boom report has more on where the work is happening.

The Named Forecasts

We kept only forecasts we could find in a dated publication.

AIA Consensus Construction Forecast (July 2026)

The American Institute of Architects' Consensus Construction Forecast panel issued its mid-year update on July 20, 2026. As reported by HPAC Engineering on July 31, 2026, the panel now expects data center construction spending to rise 33% in 2026 and another 25% in 2027. In January 2026 the same panel had forecast 26% growth for 2026 and 16% for 2027, so both years were revised up.

The same update cut the overall construction outlook to a 0.3% decline in 2026, followed by 3.0% growth in 2027, and forecast an 11.6% drop in manufacturing construction in 2026.

As a rough guide, applying AIA's growth rates to the Census 2025 total of $49.7 billion would give about $66 billion for 2026 and about $83 billion for 2027. That is our arithmetic, not AIA's published dollar figure. The January-through-August 2026 total is already running 41.7% ahead of the same period in 2025, which is faster than the 33% the panel forecast for the full year.

JLL 2026 Global Data Center Outlook (January 2026)

JLL's outlook, published January 5, 2026, is a capacity and cost forecast rather than a U.S. spending forecast. Its main points for builders:

  • Global data center capacity could reach about 200 GW by 2030, with nearly 100 GW of new capacity added between 2026 and 2030.
  • Global supply is forecast to grow at about a 14% compound annual rate through 2030, and the Americas at about 17%.
  • Average construction cost for shell and core rose from $7.7 million per MW in 2020 to $10.7 million in 2025, and JLL forecasts a 6% increase to $11.3 million per MW in 2026. Tenant technology fit-out for AI infrastructure can reach $25 million per MW on top of that.
  • The average wait for a grid connection in primary data center markets exceeds four years.
  • Total investment could reach up to $3 trillion by 2030, including about $1.2 trillion in real estate value and roughly $870 billion of new debt financing.

Data Center Frontier's January 8, 2026 summary of the report also noted JLL's finding that 57% of projects were delayed in 2025.

CBRE North America Data Center Trends (H1 2026)

CBRE counts megawatts rather than dollars. Its first-half 2026 report counted 7,481 MW under construction across its primary North American markets, led by Atlanta at 2,882 MW and Northern Virginia at 2,420 MW. Together those two markets were a little over 70% of the primary-market pipeline.

Where the Work Is Going

Power, more than land or incentives, decides where data centers get built. A few sourced data points:

  • Northern Virginia is still the largest existing market, but Dominion Energy's contracted data center load reached roughly 53.8 GW by July 2026, which shows how much demand is waiting on transmission and generation.
  • Atlanta overtook Northern Virginia in megawatts under construction in CBRE's first-half 2026 count.
  • The Midwest has added large campuses quickly. Confirmed Indiana projects include Amazon Web Services' $11 billion campus in New Carlisle, Google's $2 billion campus in Fort Wayne, Microsoft's $1 billion project in La Porte and Meta's $800 million facility in Jeffersonville. Our Indiana data center report covers them.

The national electricity picture explains the pressure. Lawrence Berkeley National Laboratory's December 2024 report for the Department of Energy found data centers used 176 TWh in 2023, about 4.4% of U.S. electricity, and projected 6.7% to 12% by 2028. Our article on how data center power demand is reshaping construction covers what that means for substations, onsite generation and utility work. For a national project map, see where every major data center is being built.

What Drives Cost and Schedule

Three sourced reference points for anyone pricing or scheduling data center work:

  1. Duration and crew size. Virginia's Joint Legislative Audit and Review Commission (JLARC) found in 2024 that a single data center building typically takes 12 to 18 months to build, with about 1,500 construction workers on site at peak. Campuses are built in phases, so one site can keep crews busy for years.
  2. Cost per square foot. The Buildermuse cost benchmark file, drawn from Gordian's RSMeans data published in early 2026, puts a one-story data center at about $505 per square foot at the national average. Our data center cost per square foot guide explains why owners often budget per megawatt instead.
  3. Cost per megawatt. JLL's forecast of $11.3 million per MW for shell and core in 2026 is a global average, not a U.S. bid number, and excludes tenant fit-out.

Material prices are also moving. The BLS producer price index for copper wire and cable was up 30.8% year over year in September 2026, and the index for steel mill products was up 27.6%. Those are index changes, not dollar prices. Spot copper was about $6.53 a pound on October 16, 2026. Our copper price guide tracks the electrical side.

What This Means for Construction Firms

General contractors. The largest campuses are concentrated among a relatively small group of experienced GCs. Our list of the top 20 data center contractors shows who they are and how they choose subcontractors. Firms without a data center track record usually get in through smaller colocation or enterprise projects first.

Electrical contractors. Electrical scope runs from utility switchyards and medium-voltage gear down to rack power, and every system is load-tested during commissioning. The constraint is qualified crews. BLS put the national median wage for electricians at $30.38 an hour in May 2025, and data center markets with several campuses under way compete hard for the same people. Our data center trades report covers which trades are most in demand.

Mechanical contractors. Higher rack densities for AI push cooling toward liquid systems, which shifts work from air handlers and ductwork to piping, coolant distribution and controls. We removed earlier adoption percentages because we could not source them, but the direction is clear from owner specifications on new AI campuses.

Suppliers. Long-lead electrical equipment such as transformers, switchgear and generators is a recurring schedule risk on data center jobs. Ordering early, sometimes before the GMP is set, is common practice on large campuses.

What to Watch Through 2027

  1. The Census monthly series. Each month's release shows whether the $85 billion annual rate holds. Revisions to June through August 2026 are worth watching too.
  2. AIA's January 2027 Consensus Forecast, which will update the 25% growth call for 2027.
  3. CBRE's second-half 2026 count of megawatts under construction.
  4. Utility interconnection timelines. JLL's four-year average grid wait is the biggest single reason announced projects slip.
  5. Stalled projects. Not every announcement turns into construction. Our page on the Matrix campus in Sulphur Springs, Texas shows how a power and land dispute stopped a 3,000 MW plan.

FAQ

How much is being spent on data center construction in 2026?

The Census Bureau put U.S. data center construction at an $84.95 billion seasonally adjusted annual rate in August 2026, up 73.2% from August 2025. Actual spending from January through August 2026 was $45.2 billion, up 41.7% from the same months of 2025. The full-year 2025 total was $49.7 billion.

What is the forecast for data center construction in 2027?

The AIA Consensus Construction Forecast panel's July 2026 update projects data center construction spending will grow 25% in 2027, after 33% growth in 2026. AIA publishes growth rates; applying them to the Census 2025 base gives about $83 billion for 2027, by our arithmetic.

Was data center construction really $28.5 billion or $32 billion in 2025?

No. Those figures appeared in earlier versions of this and other articles without a traceable source. Census data show $49.7 billion of data center construction put in place in 2025.

How much does it cost to build a data center per megawatt?

JLL's 2026 Global Data Center Outlook puts average shell-and-core construction cost at $10.7 million per MW in 2025 and forecasts $11.3 million in 2026. AI tenant fit-out can add up to $25 million per MW. These are global averages, so check local bids.

Which markets have the most data center construction?

CBRE's first-half 2026 report counted 7,481 MW under construction in its primary North American markets, with Atlanta at 2,882 MW and Northern Virginia at 2,420 MW.

How long does a data center take to build?

JLARC's 2024 study found a single building usually takes 12 to 18 months, with about 1,500 workers at peak. Campuses take years because they are built in phases, and grid connections can take longer than construction; JLL says the average wait in primary markets exceeds four years.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
gavel

Find commercial construction bids in your state

Live federal solicitations from SAM.gov — filtered by state, value, and trade.

Browse open bids