Cranes kill a steady number of workers every year, and most of those deaths come from a short list of failures a lift plan is supposed to catch. The Bureau of Labor Statistics fact sheet on fatal occupational injuries involving cranes (published May 2019, covering 2011 to 2017, checked October 26, 2026) counted 297 crane-related deaths over those seven years, an average of 42 a year. Forty-three percent of them happened in private construction, and just over half (154 deaths) involved a worker being struck by an object or equipment. In 91 of those 154 cases, the object was falling. BLS also reported in June 2019 that the 33 crane-related deaths in 2017 were the fewest since its fatality census began in 1992, down from an average of 78 a year over 1992 to 2010.
The federal rules that govern this work are in OSHA's cranes and derricks standard, 29 CFR 1926 Subpart CC, which runs from section 1926.1400 through 1926.1443 in the eCFR text current as of October 22, 2026 (checked October 26, 2026). Every section number and threshold below was checked against that text. This guide walks through what Subpart CC actually requires when you plan a lift, with the section numbers an inspector will use, and corrects a few rules of thumb that circulate on jobsites but are not in the standard.
What a Lift Plan Must Contain
Subpart CC does not define a single document called a "lift plan" for ordinary picks. What it does is require a set of determinations before and during every lift, and a written-style plan for specific high-risk operations. A good lift plan is simply the place where all of those determinations get written down.
The load and the load chart
Every plan starts with the load. Section 1926.1417(o) says the equipment must not be operated in excess of its rated capacity, and the operator must verify the load is within rated capacity by one of two methods. The first is to determine the weight from a source the industry recognizes, such as the load's manufacturer, or by a recognized calculation, such as working out a steel beam's weight from measured dimensions and its known weight per foot. That information has to be given to the operator before the lift if the operator asks for it. The second method is to start hoisting and use a load weighing device, load moment indicator, rated capacity indicator or rated capacity limiter to see whether the load exceeds 75 percent of the maximum rated capacity at the longest radius that will be used. If it does, the operator has to stop and verify the weight by the first method before continuing.
That 75 percent figure is the only capacity threshold in 1926.1417, the general operating rules, and it is a trigger for weighing the load, not a ceiling. Many company safety programs set their own lower working limits for nonroutine picks, which is good practice, but those limits come from the company program, not from OSHA.
The plan should record the crane configuration, boom length, counterweight, operating radius and the load chart value at that radius, plus the weight of the hook block and rigging, since rated capacity on most charts is reduced by everything hanging below the boom tip.
Rigging and sling angles
Sling angle matters as much as sling rating. The tension in each leg of a two-leg bridle goes up as the legs flatten out. The capacity of a sling at an angle to horizontal is its vertical rating multiplied by the sine of that angle, and since the sine of 30 degrees is 0.5, a sling leg at 30 degrees from horizontal can carry only half of its vertical rating. Write the planned angle and hitch type into the plan so the rigger and the person checking the plan are working from the same numbers. The same load-path thinking applies to suspended and supported work platforms, covered in our guide to scaffold load capacity and OSHA duty ratings.
Lifts with their own planning rules
A few operations carry specific planning requirements in the standard:
- Multiple-crane lifts. Under 1926.1432, any lift where more than one crane or derrick supports the load must be planned by a qualified person, with engineering help where that person decides it is needed. The lift must be directed by a lift director, who reviews the plan in a meeting with everyone involved before the lift.
- Hoisting personnel. Under 1926.1431, using a crane to hoist workers is prohibited unless the employer shows that conventional access (a personnel hoist, ladder, stairs, aerial lift, elevating work platform or scaffold) would be more hazardous or is not possible because of the project's structural design or worksite conditions. When it is allowed, the total load must not exceed 50 percent of rated capacity for the radius and configuration. The platform and rigging must be proof tested to 125 percent of the platform's rated capacity at each jobsite, a trial lift with the unoccupied platform must be made before each shift in which people will be hoisted, and a pre-lift meeting must be held with the operator, signal person, hoisted employees and the person responsible for the task.
Beyond those, "critical lift" is a term set by company programs and project specifications rather than by Subpart CC. Typical triggers in those programs include loads near the top of the chart, picks over occupied buildings or public areas, and lifts of unusually valuable or hard-to-replace equipment. If your contract or owner's safety manual defines a critical lift, follow that definition and put the written plan in the job file.
Operator Certification and Qualified Personnel
The people around the crane are regulated as closely as the machine.
Operator certification under 1926.1427
Under 29 CFR 1926.1427, the employer must make sure every operator is trained, certified or licensed, and evaluated before running equipment covered by Subpart CC. Certification comes from a testing organization accredited by a nationally recognized accrediting agency and is issued by equipment type, or type and capacity. A certification is valid for 5 years, and a state or local license is valid for the period the licensing office sets, but no longer than 5 years. The section took effect on December 10, 2018, except for the evaluation and documentation requirements, which took effect on February 7, 2019.
The employer evaluation is separate from the card. The employer must confirm, through a demonstration, that the operator has the skills and knowledge to run the equipment safely, including its safety devices, operational aids, software, and size and configuration (lifting capacity, boom length, attachments, luffing jib, counterweight set-up). The evaluation has to be documented with the operator's name, the evaluator's name and signature, the date, and the make, model and configuration of the equipment, and that record must be available at the worksite. Once an operator passes, the employer may let that operator run other equipment that it can show does not require substantially different skills. An operator moving to a machine that does need different skills needs a new evaluation. Operators of derricks, sideboom cranes and equipment rated at 2,000 pounds or less are exempt from 1926.1427, though training requirements in their own sections still apply.
Inspectors routinely ask for both documents, and a valid card with no evaluation record is still a gap.
Signal persons and riggers
Section 1926.1419 requires a signal person when the point of operation is not in full view of the operator, when the view in the direction of travel is obstructed, or when the operator or the person handling the load decides one is needed for site-specific safety reasons. Under 1926.1428, the signal person must be qualified either by a third-party qualified evaluator or by the employer's own qualified evaluator, with documentation on site listing each type of signaling the person is qualified for. An employer-evaluator qualification is not portable to another employer. When hand signals are used, the Standard Method in Appendix A of Subpart CC applies.
Riggers have their own rules. When workers are hooking, unhooking or guiding a load inside the fall zone, 1926.1425(c)(3) requires that the materials be rigged by a qualified rigger, and 1926.1404(r) requires a qualified rigger for rigging used during assembly and disassembly. "Qualified" is a defined term in 1926.1401, so the nearest available laborer does not count unless that person meets it. Recording who fills each role is exactly what a structured job hazard analysis is built for.
The operator also has standing authority. Section 1926.1418 says that whenever there is a safety concern, the operator may stop and refuse to handle loads until a qualified person determines safety has been assured. Put that in the pre-lift briefing so nobody on the ground is surprised by it.
Ground Conditions and Power Line Clearance
Ground conditions under 1926.1402
A crane is only as stable as what is under its outriggers or tracks. Section 1926.1402 says equipment must not be assembled or used unless the ground is firm, drained and graded enough that, with supporting materials such as blocking, mats or cribbing where needed, the manufacturer's specifications for support and level are met.
The controlling entity, usually the general contractor, must make sure the needed ground preparation is provided. It must also tell the equipment user and operator about hazards beneath the set-up area, such as voids, tanks and utilities, when those hazards appear in documents it has (site drawings, as-builts, soil reports) or are otherwise known to it. If the A/D director or operator decides the ground does not meet the requirement, their employer must discuss the needed preparation with the controlling entity. Outrigger mat sizing should come from the crane's outrigger loads and a bearing value from the geotechnical report or an engineer, not from a jobsite rule of thumb.
Power line clearance under 1926.1408 and 1926.1409
Before operating, 1926.1408 requires the employer to identify the work zone and decide whether any part of the crane, load line or load could get closer than 20 feet to a power line when operated up to its maximum working radius. If it could, the employer must pick one of three options: have the utility deenergize and visibly ground the line; keep everything at least 20 feet away using the protective measures in paragraph (b); or determine the line voltage and keep everything outside the minimum clearance in Table A.
Table A sets these minimum clearances by nominal voltage:
| Voltage (nominal kV, AC) | Minimum clearance |
|---|---|
| Up to 50 | 10 feet |
| Over 50 to 200 | 15 feet |
| Over 200 to 350 | 20 feet |
| Over 350 to 500 | 25 feet |
| Over 500 to 750 | 35 feet |
| Over 750 to 1,000 | 45 feet |
| Over 1,000 | Set by the utility or a qualified registered PE |
So the flat 20-foot distance is one compliance option for lines up to 350 kV, and Table A is a different option that can allow less (or require more) once you know the voltage. Under 1926.1409, for lines over 350 kV up to 1,000 kV, every "20 feet" in those rules becomes "50 feet." If you choose the Table A option, you have to determine the line's voltage, and under 1926.1408(c) the utility must provide requested voltage information within two working days. The protective measures in 1926.1408(b) include a planning meeting with the operator and crew, tag lines that are nonconductive, and an elevated warning line or barricade visible to the operator. If the operator cannot see that line, a dedicated spotter is required in addition to one of the other listed measures. Working inside the Table A distance is prohibited except under the strict conditions of 1926.1410.
Power-line and struck-by exposures show up repeatedly in enforcement data, which we break down in OSHA's top 10 construction citations for 2026.
Assembly, Inspection, and Penalty Exposure
Assembly, disassembly, and inspection
Assembly and disassembly fall under 1926.1403 through 1926.1406 and must be directed by an A/D director, a person who is both a competent person and a qualified person, or a competent person assisted by one or more qualified persons (1926.1404(a)). For tower cranes, 1926.1435 adds its own erection, climbing and inspection rules; we cover those in how a tower crane climbs.
Section 1926.1412 sets the inspection schedule:
- Each shift: a competent person begins a visual inspection before each shift the equipment is used, completed before or during that shift. The standard does not require this one to be documented, though writing it down is the easiest way to prove it happened.
- Monthly: an inspection to the shift checklist, documented and kept for at least three months.
- Annual/comprehensive: at least every 12 months, an inspection by a qualified person, with disassembly as needed, documented and kept for at least 12 months.
- Equipment idle for 3 months or more must get a monthly-level inspection by a qualified person before it goes back into use.
A standard safety inspection checklist used every shift gives you the dated record even where the rule does not demand one.
What the penalties look like in 2026
There was no 2026 inflation increase: the Labor Department cancelled it in the Federal Register on May 27, 2026 (91 FR 31358) because BLS never published October 2025 CPI data, so the maximums set January 15, 2025 still apply. OSHA's penalties page (checked October 26, 2026) lists them as $16,550 per serious or other-than-serious violation, $165,514 per willful or repeated violation, and $16,550 per day for failure to abate. Those caps apply to every Subpart CC requirement. Crane incidents tend to pull in several sections at once (ground conditions, power lines, operator qualification, inspections), so one event can produce multiple citations that add up quickly. Actual proposed penalties depend on gravity, employer size, history and good faith, and are often lower than the maximum.
Frequently Asked Questions
Does OSHA require a written lift plan for every crane lift?
No. Subpart CC requires the load to be verified against rated capacity under 1926.1417(o), the work zone and power-line distances to be assessed under 1926.1408, and the ground to meet 1926.1402 on every lift. It specifically requires planning by a qualified person for multiple-crane lifts (1926.1432) and a pre-lift meeting, trial lift and proof test for personnel hoisting (1926.1431). Formal written critical-lift plans for other lifts usually come from company programs or contract specs.
What is the minimum clearance from power lines for a crane?
If any part of the crane, load line or load could come within 20 feet of a line, the employer must deenergize and ground it, keep a 20-foot clearance (for lines up to 350 kV), or use the Table A distance for the line's actual voltage: 10 feet up to 50 kV, rising to 45 feet for lines over 750 kV up to 1,000 kV. For lines over 350 kV up to 1,000 kV, the 20-foot figure becomes 50 feet under 1926.1409.
How often must crane operators be recertified?
A certification from an accredited testing organization under 1926.1427 is valid for 5 years. A state or local license is valid for the period the licensing office sets, up to 5 years. The employer evaluation is separate and must be redone when an operator moves to equipment that requires substantially different skills, or after retraining.
Who is responsible for ground conditions under the crane?
Under 1926.1402, the controlling entity, usually the GC, must make sure the ground preparation is provided and must tell the equipment user and operator about hazards beneath the set-up area that it knows about or that appear in documents it holds. If the A/D director or operator finds the ground inadequate, their employer must work out the needed preparation with the controlling entity.
Are shift inspections required to be written down?
Not under 1926.1412(d). Monthly inspections must be documented and kept at least three months, and annual inspections documented and kept at least 12 months. Many contractors document shift inspections anyway because it is the only proof they were done.
What are the 2026 OSHA penalties for crane violations?
The 2026 inflation adjustment was cancelled, so the 2025 maximums still apply. As of October 26, 2026, OSHA lists them as $16,550 per serious violation, $165,514 per willful or repeated violation, and $16,550 per day for failure to abate.
Your Action Item for This Week
Pick the most demanding crane lift scheduled on your site in the next two weeks and write its plan before the crane shows up. Get the load weight from a recognized source and add the rigging and hook block. Record the crane configuration, radius and the chart capacity at that radius, the sling angles, the swing-radius barricade, and the distance and voltage of the nearest power line. If anything could come within 20 feet of that line, call the utility now to confirm the voltage or arrange deenergizing. Then check that your operator's certification is current, that you have a signed employer evaluation on file for that machine, and that your signal person's qualification paperwork is on site.



