The best documented U.S. figure for high-speed rail construction cost comes from California. The California High-Speed Rail Authority's 2026 Business Plan (revised draft dated May 28, 2026, taken up by the Authority's board at its June 1, 2026 meeting) puts the capital cost of the Merced-to-Bakersfield early operating segment at $35.7 billion, down about $1.0 billion from the $37 billion in its August 2025 Supplemental Project Update Report. Spread over the segment's length, that works out to roughly $209 million per mile on the 171-mile statutory segment, or about $220 million per mile on the 162-mile version the plan's cost assumptions use. Those are all-in program costs: right-of-way, utility relocation, structures, track, systems, stations, design, management and contingency.
An earlier version of this article put California's cost at $350 million per mile. That number does not appear in the Authority's plans and we have removed it.
The other active U.S. project, Brightline West between Las Vegas and Southern California, now carries a cost estimate of about $21 billion for a 218-mile line (Construction Dive, September 17, 2026; route length per the October 1, 2024 grant agreement announcement), or roughly $96 million per mile. The difference between the two projects says more about alignment and scope than about who builds them.
California High-Speed Rail: What the 2026 Plan Says
Costs and scope
The Legislative Analyst's Office briefing on the draft plan (April 27, 2026) lays out the scope choices behind the numbers. The draft assumed a shorter initial segment, 162 miles from a new South Merced station about 3.5 miles south of downtown Merced to a North Bakersfield station about 6 miles north of the previously planned site. It assumed 144 of those 162 miles would be single-tracked and that the end stations would be simple at-grade stations. The LAO noted that state law (SB 198 of 2022) defines the segment as electrified double track to downtown Merced, so these assumptions require legislative action.
For the full San Francisco-to-Los Angeles/Anaheim Phase 1, the revised plan estimates about $231.3 billion in today's dollars if built as originally designed, and about $126.1 billion under an "optimized" approach that shares existing Metrolink and Union Pacific tracks in places and assumes other agencies build some segments. The 2024 Business Plan's Phase 1 estimate was $128 billion.
Funding
The Authority forecasts $39.3 billion in capital funding through 2045. The largest piece is the state's cap-and-invest program, which the Legislature extended through 2045 in September 2025 (SB 840) with a fixed $1 billion a year for high-speed rail, about $15 billion from 2030 through 2045 per the LAO. The plan removed about $4.0 billion in federal funding after the Federal Railroad Administration terminated it in July 2025, including a $3.1 billion Federal-State Partnership agreement and $928.6 million in 2010 and 2011 awards; the Authority ended its legal challenge in December 2025.
The LAO's March 2, 2026 briefing pointed out that the funding total does not include borrowing costs, which the Authority had estimated at about $4 billion, and that once those are counted the Merced-Bakersfield segment had an estimated gap of about $2 billion under the 2025 numbers. That is the main risk for contractors: the money to finish the Central Valley exists on paper only if the state can borrow against future cap-and-invest revenue.
Construction progress
According to the 2026 Business Plan, as of February 2026 the Authority had 80 miles of guideway and 61 major structures complete on the 119-mile Central Valley Segment, 1,673 utility relocations done (93%) and all 2,288 parcels delivered to the design-builders. The plan reports an average of 1,400 workers on Central Valley construction sites each day in 2025. The target completion date for Merced to Bakersfield is 2032, one year later than before.
The next big package is track and systems. The Authority issued a request for bids in November 2025 for up to $3.5 billion of track, electrification, train control, communications and safety systems across the 119-mile segment, and on June 1, 2026 the board selected a Kiewit, Stacy and Witbeck and Herzog joint venture for the $3.5 billion contract (Construction Dive, June 2, 2026).
Brightline West: Lower Cost per Mile, Harder Financing
Brightline West is a privately led project planned to run 218 miles, mostly in the median of Interstate 15, with stations in Las Vegas, Apple Valley, Hesperia and Rancho Cucamonga. The FRA's $3 billion grant agreement was with the Nevada Department of Transportation (announced October 1, 2024). The project broke ground at its Las Vegas station site on April 22, 2024.
Since then the budget and schedule have moved. Construction Dive (September 17, 2026) reported the cost estimate rose from $12 billion in 2024 to $21 billion. The project has tapped $3.5 billion of tax-exempt private activity bonds and was hoping for a $6 billion federal Railroad Rehabilitation and Improvement Financing (RRIF) loan by late October 2026. It also faced a November 2 deadline for a $400 million equity contribution, which it had originally promised by March 31, 2026. FOX5 Las Vegas (March 5, 2026) reported that surveying was complete along the route, that service was expected to begin in late 2029, and that Brightline did not provide a construction timeline.
For contractors, the per-mile number looks attractive, but the project is financing-constrained. Until the federal loan and equity close, assume packages may be paced by cash flow rather than by schedule.
Why the Cost per Mile Differs So Much
The two projects are hard to compare directly, because each per-mile figure includes different scope and different stages of design. But the main drivers are visible.
Alignment and right-of-way. Brightline West runs mostly inside an existing interstate median through desert. California's Central Valley alignment crosses farmland, cities, highways, freight railroads, canals and irrigation systems, which is why the Authority had to relocate more than 1,600 utilities and acquire more than 2,200 parcels before the civil work could finish.
Structures. Grade separation is expensive. California's Central Valley work is heavy on viaducts, overpasses and underpasses, all needed to keep a high-speed railroad fully separated from road and rail crossings. A median alignment needs far fewer.
Scope still to come. California's Phase 1 numbers include mountain crossings into the Bay Area and Los Angeles Basin. The Authority's own plan notes that a dedicated Palmdale-to-Burbank alignment would need 26 miles of tunneling, which is one reason the optimized plan shares Metrolink track instead.
Time. California has been in planning and construction since voters approved $9 billion in bonds in November 2008 (Proposition 1A). Long schedules carry escalation, extended overhead and repeated redesign.
Delivery approach. California's civil packages were procured as design-build, and track and systems are now a separate contract. Brightline West is a private developer project with its own contracting structure. In both cases, owner-side scope changes after award are what drive cost growth, not the delivery label.
What This Means for Contractors
The California program is moving from civil work into track and systems. With the track-and-systems joint venture selected, opportunities shift toward subcontracts: catenary foundations and poles, traction power, signals and communications, rail welding, ballast and ties, and the electrical work at stations and maintenance facilities. Prime civil work in the Central Valley is largely awarded; remaining structures and guideway miles are under existing packages.
Watch the funding before you chase work outside the Central Valley. The LAO warns that spending on segments outside Merced-Bakersfield without a funding plan risks stranded assets, and as of the LAO's April 2026 review the Legislature had not enacted the statutory changes the Authority's cost estimates assume.
For Brightline West, follow the RRIF loan decision. That is the trigger for large-scale civil and track procurement.
Price long-duration risk honestly. Both projects have multi-year schedules and federal or state funding uncertainty. Escalation clauses, clear change-order mechanisms and realistic float are worth more than a sharp unit price on work that may not start on time.
For a comparison with another long linear civil market, see our piece on U.S. tunnel boring projects, and for how federal infrastructure money reaches contractors generally, our IIJA contractor guide.
Frequently Asked Questions
How much does high-speed rail cost per mile in the U.S.?
There is no single figure. California's 2026 Business Plan estimates $35.7 billion for Merced to Bakersfield, roughly $209 million to $220 million per mile depending on whether the 171-mile or 162-mile version is used. Brightline West's roughly $21 billion estimate for a 218-mile line works out to about $96 million per mile. Both are all-in project costs, not construction-only numbers.
What will the full California high-speed rail system cost?
The 2026 Business Plan estimates about $126.1 billion for Phase 1 under its optimized approach, which shares existing tracks in some areas, and about $231.3 billion if built as originally designed. The 2024 plan estimate was $128 billion.
Did California lose federal high-speed rail funding?
Yes. The FRA terminated about $4.0 billion in July 2025, including a $3.1 billion Federal-State Partnership agreement. The Authority dropped its legal challenge in December 2025 and removed those funds from its budget.
Who is building the California track and systems?
On June 1, 2026 the Authority's board selected a Kiewit, Stacy and Witbeck and Herzog joint venture for a $3.5 billion contract to install track, overhead contact system, train control and communications on the 119-mile Central Valley Segment, per Construction Dive.
When will Brightline West open?
FOX5 Las Vegas reported in March 2026 that service was expected in late 2029. As of September 2026 the project was still waiting on a $6 billion federal RRIF loan and faced a November 2 equity deadline, so the schedule depends on financing.
How many workers are on the California project?
The Authority's 2026 Business Plan reports an average of 1,400 workers on Central Valley construction sites each day in 2025, and more than 19,200 jobs created since construction began.