The Money Behind the Megawatts
The Census Bureau's monthly construction spending report is the cleanest public measure of how much is going into data center buildings, and the number has moved faster than any other private category. In the release covering August 2026 (preliminary), Census put private data center construction at a seasonally adjusted annual rate of $84.95 billion. A year earlier, in August 2025, the same series was $49.05 billion, so the annual rate rose 73.2% in twelve months.
The longer view is more striking. The series stood at about $13.1 billion in August 2022 and $20.5 billion in August 2023. Averaging the twelve monthly readings for each year, the annual rate ran about $34.7 billion through 2024 and about $49.7 billion through 2025. Earlier versions of this article cited a $28.5 billion total for 2025 that we could not trace to any published source; the Census series shows spending well above that.
To put the figure in context, private nonresidential construction overall was running at $773.0 billion in August 2026, according to the same Census table. Data centers were about 11% of that. Total U.S. construction spending was about $2.20 trillion at an annual rate, down 1.7% from a year earlier, so data centers are growing hard inside a market that is flat to down overall. Our 2026 construction spending forecast covers the rest of the picture, including the 19.8% year-over-year drop in manufacturing construction.
Two cautions on the Census number. It measures construction put in place, not announced budgets, so it lags project announcements and excludes servers, chips and most IT equipment. And the monthly figures get revised, so treat the latest month as preliminary.
Where the Capacity Is Going
Dollar figures are one lens; megawatts under construction are another, and that is how the brokers track it. CBRE's North America Data Center Trends report for the first half of 2026 counted 7,481 MW under construction across its primary markets. Atlanta led with 2,882 MW, ahead of Northern Virginia at 2,420 MW. Northern Virginia is still the largest market by existing inventory, but Atlanta overtook it on construction activity.
The rest of the country is filling in behind those two. Indiana is a good example of how fast a secondary market can appear. Confirmed projects there include Amazon Web Services' $11 billion campus in New Carlisle, Google's $2 billion campus in Fort Wayne, Microsoft's $1 billion project in La Porte, and Meta's $800 million facility in Jeffersonville. We cover those in more detail in the Midwest data center surprise in Indiana. For the market-by-market map, see where every major data center is being built.
Louisiana shows the upper end of single-campus scale. When Meta announced its Richland Parish campus in December 2024, it described a four-million-square-foot facility with more than $10 billion of investment and said more than 5,000 construction workers would be on site at peak, with construction expected to continue through 2030. Turner, DPR and Mortenson were named as the builders, according to the Louisiana Illuminator's December 4, 2024 report and Meta's announcement.
Who Is Paying for It
The money comes from three groups of owners.
The first is the hyperscale cloud and AI companies: Amazon, Microsoft, Google and Meta, plus newer AI-focused builders. They all report capital spending in their earnings, but those totals include servers, networking and chips, and they cover global operations. None of them breaks out U.S. building construction as a separate line. Earlier versions of this article assigned specific U.S. construction budgets to each company ($14 billion for Microsoft, $8 billion for Google, $6 billion for Meta). Those figures were not traceable to the companies' filings and have been removed. If you see a company-level construction number, ask where it came from; it is usually an analyst's estimate carved out of total capex.
The second group is colocation and wholesale developers, who build multi-tenant buildings or build-to-suit facilities and lease them to cloud companies and enterprises. These operators are often the easier door for a regional contractor because their projects are smaller and their contractor lists are less locked in.
The third group is the utilities and power developers building substations, transmission and on-site generation to serve these campuses. That work does not show up in the Census data center line at all; it lands in the power category. Google's October 14, 2024 agreement with Kairos Power, for up to 500 MW from small modular reactors with the first unit targeted for 2030 and more through 2035, is one example of owners reaching past the grid for power.
What a Megawatt Costs
Hyperscale budgets are set per megawatt of IT capacity, not per square foot. Published benchmarks differ because they measure different scopes:
- JLL's 2026 Global Data Center Outlook puts the average global shell-and-core cost at $11.3 million per MW, and says AI tenant fit-out can add as much as $25 million per MW on top of that.
- Cushman & Wakefield's 2026 Data Center Development Cost Guide puts average greenfield development cost at $17.6 million per MW for the most modern facilities, and says costs per MW rose 21% since its previous report.
- For smaller buildings priced per square foot, Gordian's RSMeans data (published by Building Design+Construction, Q1 2026) puts a one-story data center building at $505 per square foot at the national average, from $398 in Austin to $688 in Palo Alto.
The gap between $11.3 million and $17.6 million is mostly scope. Shell and core stops at the building and its base systems; a full development number picks up more of the power and cooling plant. When an owner quotes a per-MW budget to you, find out which scope it covers before comparing your number to it. Our data center construction cost guide goes through this in more detail.
An earlier version of this article gave a percentage breakdown of a data center budget by trade (electrical 35–40%, mechanical 25–30%, and so on). We could not find a published source for those splits and have removed them. What is safe to say is the direction: in a data center, the electrical and mechanical systems, not the structure, make up most of the cost, which is the reverse of a warehouse or office shell.
What This Means for Construction Firms
General contractors
The general contractor tier is concentrated. A small group of national firms does most hyperscale work, and owners tend to reuse the same builders across campuses. Our ranking of the top 20 data center construction contractors lists them. For a firm outside that group, the realistic entry points are colocation and wholesale projects, smaller enterprise data centers, and subcontract roles on hyperscale campuses.
Electrical and mechanical subcontractors
The trades that carry the most value on these jobs are electrical (medium-voltage distribution, switchgear, UPS, generators, busway) and mechanical (chillers, cooling towers, piping, air handling and, more and more, liquid cooling distribution). Equipment, not labor, is often the scheduling constraint. Owners now commonly buy long-lead gear such as generators, transformers and switchgear themselves and hand it to the contractor as owner-furnished equipment. Our piece on data center power demands covers grid timelines, and JLL reports that the wait for a grid connection in primary markets now exceeds four years.
Specialty trades
Commissioning agents, controls integrators, fire protection contractors and concrete crews that can handle heavy slabs and equipment pads all see steady demand. The commissioning phase in particular is longer and more structured on a data center than on most commercial buildings, because every system has to be tested under load before the owner accepts it.
Labor and wages
Labor is the constraint most contractors feel first. Virginia's Joint Legislative Audit and Review Commission (JLARC) found in its 2024 study that a typical data center has about 1,500 construction workers on site at peak, and that a single building usually takes 12 to 18 months to construct. In smaller metros that is a large share of the local trade workforce.
On pay, the only defensible national baseline is the government data. The BLS Occupational Employment and Wage Statistics survey put the national median wage for electricians at $30.38 per hour in May 2025, and BLS payroll data put average hourly earnings for all construction employees at $41.69 in September 2026. Earlier versions of this article cited $45 to $65 per hour for data center journeymen in Virginia and Texas and wage premiums of 20 to 30% above prevailing rates; we could not source those figures and removed them. Data center jobs in tight markets do pay above those medians through overtime, per diem and union scale, but the size of that premium varies by local and by project. For the broader labor picture, see our coverage of the construction workforce gap.
The Colocation and Wholesale Market
Colocation operators build multi-tenant facilities where customers share a building's power, cooling and security while owning their own servers. Wholesale developers build larger halls or whole buildings to a single tenant's specifications. Both are a meaningful share of the capacity CBRE tracks, and both lean on the same mechanical and electrical trades as hyperscale work.
For a regional contractor, these projects have a few practical advantages. The owners are more numerous. The buildings are often closer to metro areas, which helps with labor. And a completed colocation project gives you the references and safety record that hyperscale procurement teams ask for. Earlier versions of this article put a $6 to $8 billion figure on 2026 colocation construction and gave typical building sizes for each segment; neither was sourced, and both have been removed.
Looking Ahead
The Census series has risen every year since 2021, and CBRE's count of capacity under construction keeps setting records. The forces behind the build-out are AI computing and cloud demand, and the constraint is power, not capital. Projects with a utility commitment and a signed tenant are the ones that move; speculative campuses waiting on a substation can sit for years.
For contractors, the practical questions are where the power is landing next and whether your firm has the people and the safety record to work on these sites. The markets to watch are the ones where CBRE is reporting new construction and utilities are approving large loads: Atlanta, Northern Virginia, Dallas, Indiana and Louisiana among them.
READ NEXT: Data Center Power Demands Are Rewriting the Construction Playbook
FAQ
How much is the US spending on data center construction in 2026?
The Census Bureau put private data center construction at a seasonally adjusted annual rate of $84.95 billion in August 2026 (preliminary), up 73.2% from $49.05 billion in August 2025. That figure covers construction put in place, not servers or IT equipment.
What does a hyperscale data center cost per megawatt?
It depends on scope. JLL's 2026 Global Data Center Outlook puts average global shell-and-core cost at $11.3 million per MW, with AI fit-out adding up to $25 million per MW. Cushman & Wakefield's 2026 cost guide puts average greenfield development cost at $17.6 million per MW for the most modern facilities. Always confirm what an owner's per-MW budget includes before comparing it to your estimate.
Which markets have the most data center construction?
In CBRE's first-half 2026 count for primary North American markets, Atlanta led with about 2,882 MW under construction and Northern Virginia followed with about 2,420 MW, out of 7,481 MW total. Indiana, Texas and Louisiana are among the fastest-growing secondary markets.
How many workers does a data center project need?
Virginia's JLARC 2024 study found about 1,500 construction workers on site at peak for a typical data center, with 12 to 18 months to build a single building. The largest campuses need far more: Meta said its Richland Parish, Louisiana campus would have more than 5,000 construction workers on site at peak.
How should a subcontractor handle labor escalation on a long data center contract?
On contracts that run more than a year, ask for an escalation clause tied to a published index rather than absorbing the risk in contingency. The BLS Employment Cost Index for construction and BLS producer price indexes for materials are common reference points. Put the index, base period and adjustment frequency in the subcontract so there is no argument later about how the adjustment is calculated.



