The CHIPS and Science Act is now four years old, and the construction it paid for has moved past its peak. The law appropriated $52.7 billion for semiconductor programs from FY2023 through FY2027, according to the Congressional Research Service (CRS report R47523). The construction-relevant piece is smaller: $39 billion for manufacturing incentives to build or expand fabs, which the Commerce Department can award only through FY2026 (CRS report R49031, July 14, 2026).
An earlier version of this article said fab construction would reach $52 billion in 2026 and that awards had triggered $450 billion of private commitments. We could not source either claim. The verified picture is below.
What the Construction Data Shows
The Census Bureau tracks private construction put in place at computer, electronic and electrical manufacturing plants. It is the closest public measure of chip-fab construction (it also includes battery and electrical equipment plants), and it tells a clear story.
| Period | Computer/electronic/electrical plant construction (Census, $ billions) |
|---|---|
| 2021 (annual) | 12.1 |
| 2022 (annual) | 42.7 |
| 2023 (annual) | 100.4 |
| 2024 (annual) | 122.1 |
| 2025 (annual) | 96.8 |
| June 2024 (SAAR, series peak) | 126.4 |
| August 2025 (SAAR) | 95.4 |
| August 2026 (SAAR, preliminary) | 52.3 |
Source: Census Bureau, Value of Construction Put in Place, tables privtime and privsatime (August 2026 data released October 1, 2026; downloaded October 18, 2026).
In August 2026, spending was running at $52.3 billion a year, down 45% from a year earlier and down 59% from the June 2024 peak. January through August 2026 totaled $37.9 billion, 45.3% below the same months of 2025. Total private manufacturing construction was $168.2 billion SAAR, down 19.8% year over year, and the chip-and-electronics line accounts for most of that drop.
What that curve means on the ground: the first wave of fab shells, the concrete, steel and envelope work that dominates put-in-place dollars, is largely built. Several second-phase fabs have been delayed or slowed. The work has not stopped, but the volume is roughly back to 2022 levels. We track individual project status in our companion semiconductor fab construction tracker.
Where the CHIPS Money Went
By January 31, 2025, Commerce's CHIPS Program Office had made final awards to 19 companies totaling up to $30.7 billion in direct funding plus $5.5 billion in loans, covering 40 commercial fab projects, according to CRS. A later $275 million increase to Micron brought direct funding awarded to $30.9 billion. Another 12 companies signed preliminary terms for 18 projects; as of June 2026, CRS found no public record that any of them had received a final award.
The largest final awards, from the CRS table (which sums direct funding and loans) and NIST's CHIPS award listings (updated August 6, 2026):
| Company | Main construction sites | Total incentives (CRS) | Final award date |
|---|---|---|---|
| TSMC Arizona | Phoenix, AZ | $11.565B (NIST lists $6.6B direct funding) | Nov 15, 2024 |
| Intel | Chandler, AZ; New Albany, OH; Hillsboro, OR; Rio Rancho, NM | $7.865B | Nov 26, 2024 |
| Micron | Boise, ID; Clay, NY | $6.165B, raised to $6.44B June 12, 2025 | Dec 10, 2024 |
| Samsung | Taylor and Austin, TX | $4.745B | Dec 20, 2024 |
| Texas Instruments | Sherman, TX; Lehi, UT | $1.61B | Dec 20, 2024 |
| GlobalFoundries | Malta, NY; Burlington, VT | $1.587B | Nov 20, 2024 |
| SK hynix | West Lafayette, IN | $958M | Dec 19, 2024 |
| Amkor | Peoria, AZ | $407M | Dec 20, 2024 |
| GlobalWafers | Sherman, TX; St. Peters, MO | $406M | Dec 17, 2024 |
NIST's site-level listings break some of these down: Intel's direct funding is listed as $3.94 billion for Chandler, $1.5 billion for New Albany, $1.86 billion for Hillsboro and $500 million for Rio Rancho; Texas Instruments as $900 million for two Sherman fabs and $700 million for one Lehi fab; GlobalFoundries as $1.45 billion for Malta and $125 million for Burlington. On October 14, 2026, Commerce agreed to amend GlobalFoundries' award to reallocate up to $955 million toward silicon photonics, silicon-germanium and advanced packaging (NIST CHIPS page).
What Changed in 2025 and 2026
The award terms did not stay fixed. CRS reports that the administration said in March 2025 it intended to renegotiate CHIPS agreements. Three changes matter for construction:
Intel traded grant money for equity. In August 2025, the federal government agreed to release $8.9 billion to Intel, $5.7 billion from the unpaid portion of its CHIPS direct funding award plus $3.2 billion from the Secure Enclave program, in exchange for Intel stock (CRS R49031, citing Intel's August 22, 2025 Form 8-K). NPR reported on August 22, 2025 that, per Intel's statement, the government agreed to buy 433.3 million shares at $20.47 each, a 9.9% stake. For contractors, the practical point is that Intel's money is no longer tied to the original project-by-project milestone payments.
TSMC and Micron raised their commitments. TSMC announced on March 4, 2025 that its U.S. investment would reach $165 billion, adding three fabs, two advanced packaging plants and an R&D center, and said the expansion would support 40,000 construction jobs over four years. TSMC's Arizona page now describes the project as having grown "from $12 billion to $265 billion." Micron's award was raised by $275 million in June 2025.
The tax credit deadline moved to the front. The advanced manufacturing investment credit, raised from 25% to 35% of qualifying capital expense, applies only to projects that begin fab construction before December 31, 2026 (CRS R49031). That deadline gives owners a reason to start site work on planned fabs this year, which may mean a burst of early-phase earthwork, foundation and utility contracts even as overall spending falls.
Project Status, Site by Site
Here is where the large projects stand, using company statements and CRS.
TSMC, Phoenix, Arizona. Per TSMC's Arizona page: the first fab started high-volume production on its N4 process in Q4 2024. Construction of the second fab's structure was completed in 2025, with volume production targeted for the second half of 2027 (CRS notes this was moved up from 2028 because of AI-related customer demand). The third fab broke ground in April 2025 and targets volume production by the end of the decade. Initial construction on a fourth fab and the first advanced packaging plant began in early 2026. The campus covers more than 1,100 acres.
Intel, New Albany, Ohio. Intel said on February 28, 2025 that construction of its first Ohio fab would finish in 2030, with operations starting between 2030 and 2031, after the project had originally been slated for 2025. Spectrum News reported at the time that the basement level was complete and ground-level work was underway at a slower pace. CRS notes Intel told local media in July 2025 the project could be cancelled if it could not find more manufacturing customers.
Micron, Clay, New York. Micron's December 2024 award announcement described roughly $100 billion of investment in New York and $25 billion in Idaho over about two decades. In November 2025, Micron pushed the expected opening of the first Clay fab from 2028 to the third quarter of 2030; Onondaga County attributed the delay to "labor and supply chain shortages" (CRS R49031).
Samsung, Taylor, Texas. NIST describes the Taylor project as two 2nm logic foundry fabs and an R&D lab. CRS reports Samsung's estimated total investment across Taylor and Austin at $37 billion. Samsung originally announced Taylor in November 2021 with production planned for 2024; that date has slipped more than once.
Texas Instruments, Sherman and Lehi. NIST lists the Sherman award as two 300mm fabs for analog and embedded processing chips and the Lehi award as one 300mm fab.
We removed the earlier version's project-level dollar figures for fab shells, electrical packages and per-site worker counts (for example, "12,000 construction workers" at TSMC Arizona), because none could be traced to a published source.
What Goes Into a Fab, From a Contractor's Seat
No single public source gives a reliable cost-per-square-foot for fab construction, and published estimates vary widely depending on whether process tools are included. What is not in dispute is the scope mix:
Structure and shell. Fabs are large, heavy, multi-level buildings with a cleanroom level, a subfab below it for process utilities, and an interstitial level above for air handling. Vibration control drives the structure, so expect deep foundations, thick slabs and stiff framing.
Cleanroom. Raised floors, sealed wall and ceiling systems, fan filter units across the ceiling, static-dissipative surfaces and tight temperature and humidity control. Installation follows clean-build protocols that slow every trade compared with ordinary commercial work.
Process utilities. Ultra-pure water production and distribution, bulk and specialty gas systems (including toxic and pyrophoric gases), chemical delivery, exhaust and abatement, process cooling water, and compressed dry air and nitrogen. High-purity piping, orbital welding and double-containment systems are the specialty trades that get bid separately and are hardest to staff.
Power. Fabs draw utility-scale power, so the work includes on-site substations, medium-voltage distribution, UPS for critical loads and backup generation.
Tool install. After the building is turned over, process tool hook-up is its own long phase, heavy on pipefitters and electricians.
Workforce: Still the Constraint
CRS lists labor availability as one of the main factors behind fab delays. TSMC pushed production at its first Phoenix fab from 2024 to 2025 in July 2023, citing an "insufficient amount of skilled workers with those specialized expertise required for equipment installation in a semiconductor-grade facility." Its plan to bring workers from Taiwan led to friction with the Arizona Building and Construction Trades Council, resolved by an agreement in December 2023 that included support for a training program.
On the funding side, GAO found 13 of the 19 fab award recipients received a combined $293 million dedicated to workforce development; Intel received about $50 million to develop semiconductor and construction workers with local schools and programs (cited in CRS R49031). The Semiconductor Industry Association projected 67,000 semiconductor jobs going unfilled by 2030, separate from the construction workforce.
The earlier version of this article claimed the boom needed 40,000 to 50,000 more construction workers, that Phoenix construction wages had risen 18% to 22%, and that high-purity piping paid 30% to 50% more. None of those figures could be sourced. For trade wage data that is sourced, the Bureau of Labor Statistics' May 2025 occupational survey put the national median for electricians at $30.38 an hour. Our construction workforce gap analysis covers national shortage estimates.
What This Means for Your Crew
Mechanical and pipe contractors. High-purity process piping is the specialty with the most persistent demand, and tool hook-up continues for years after a shell tops out. Orbital welding qualifications and clean-build experience are the entry ticket.
Electrical contractors. Medium-voltage, substation and industrial controls experience carries over between fabs and data centers. With chip-plant spending down and data center spending up sharply, firms with that experience have options in both markets.
General contractors and civil firms. The December 31, 2026 tax credit deadline for starting fab construction may produce early-phase site and foundation contracts this year. Prime contracts on leading-edge fabs are concentrated among a small group of specialist firms, so subcontracting is the usual way in.
Everyone. Treat announced investment figures as long-range intentions, not backlog. Intel Ohio and Micron New York have both moved their first-fab dates out by years, and the Census spending line has fallen by nearly half in twelve months.
Frequently Asked Questions
How much money is in the CHIPS Act?
CRS reports the CHIPS Act appropriated $52.7 billion for FY2023 through FY2027. Of that, $50 billion went to the CHIPS for America Fund, which includes $39 billion for fab manufacturing incentives and $11 billion for research and development. Commerce can award the manufacturing incentive money only through FY2026.
How much has been awarded for fab construction?
By January 2025, Commerce had made final awards to 19 companies totaling up to $30.7 billion in direct funding plus $5.5 billion in loans for 40 projects; a later Micron increase brought direct funding to $30.9 billion (CRS R49031, July 2026). The largest awards went to TSMC, Intel, Micron and Samsung. The "$36 billion in grants and $12 billion in loans" figure in the earlier version of this article did not match any source.
Is semiconductor fab construction growing in 2026?
No. Census data show private construction at computer, electronic and electrical plants at $52.3 billion SAAR in August 2026, down 45% from a year earlier and 59% below the June 2024 peak. First-wave fab shells are largely built and several second-phase projects have been delayed.
What happened to Intel's CHIPS grant?
In August 2025, the government agreed to release $8.9 billion to Intel, $5.7 billion from its CHIPS award and $3.2 billion from the Secure Enclave program, in exchange for Intel stock, a stake reported at 9.9%. Intel had received a CHIPS award of about $7.9 billion in November 2024.
Is there a deadline that affects when fabs start construction?
Yes. The 35% advanced manufacturing investment tax credit applies only to projects that begin fab construction before December 31, 2026, according to CRS. Owners with planned fabs have an incentive to start site work before then.
How long does it take to build a fab in the United States?
It varies, and recent U.S. projects have run long. TSMC announced its first Phoenix fab in 2020 and began high-volume production in Q4 2024. Intel's first Ohio fab, originally slated to open in 2025, is now scheduled to finish construction in 2030. Micron's first Clay, New York fab is now expected to open in the third quarter of 2030.


