ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Commercial

Liquid Cooling Is Changing How Data Centers Are Built

Lisa Chen·April 10, 2026·Updated October 18, 2026·12 min read

Share this with your estimator.

Liquid Cooling Is Changing How Data Centers Are Built

Why Air Alone Stopped Being Enough

For most of the last thirty years, data center cooling meant moving air: cold air into the front of the racks, hot air out the back, and a plant of chillers, computer room air handlers and economizers to keep the cycle going. That model still runs the majority of the world's server rooms. What has changed is the top end of the market, where AI hardware now puts more heat into a single rack than an air system can carry away at any reasonable fan power or footprint.

The clearest public marker is NVIDIA's GB200 NVL72 platform. In October 2024 Vertiv announced a 7 MW reference architecture co-developed with NVIDIA for that platform, and Vertiv's release says the design "supports up to 132kW per rack," using a hybrid of liquid cooling for the chips and air cooling for the rest of the heat. That is a vendor design figure, not a field measurement, but it is the number owners and engineers are designing around when they plan a GB200-class data hall.

Compare that with what is actually installed across the industry. Uptime Institute's 2026 Global Data Center Survey (field work March 17 to May 1, 2026; 801 owner/operator respondents; findings report dated August 2026) found that the most common rack density in 69% of facilities is still under 10 kW per rack. Another 20% reported a modal density of 10 to 19 kW, 8% reported 20 to 49 kW, and 3% reported 50 kW or more.

The peaks tell a different story. When Uptime asked for the highest rack density deployed anywhere in the facility, the share reporting 50 kW or more rose from 10% in 2025 to 13% in 2026, and the share reporting 20 to 49 kW rose from 22% to 26%. Facilities whose highest rack was under 10 kW fell from 32% to 25%. So the typical rack is still an air-cooled rack, but a growing slice of sites now has at least some racks that air cannot handle on its own, and the new AI campuses are being designed from the slab up around liquid.

For contractors, that split matters. Most of the work on a new AI campus is a liquid-cooled job with an air-cooled tail, while most retrofit work in existing enterprise and colocation halls is the opposite: an air-cooled room that needs a liquid loop added to a few rows. For the general contractors leading the large campuses, see our ranked list of the top 20 data center contractors.

The Two Main Approaches

There are two families of liquid cooling in commercial use. They put very different scopes in front of mechanical and electrical subcontractors.

Direct-to-chip (cold plate)

Direct-to-chip cooling bolts a metal cold plate onto the hottest components on each server, usually the GPUs and CPUs. Coolant runs through channels in the plate and carries heat out of the rack. Schneider Electric's description of Motivair's product line, which it bought into in 2024, lists the main parts of these systems: coolant distribution units (CDUs), rear-door heat exchangers, cold plates and chillers.

The CDU is the piece contractors set and pipe. It separates the technology cooling loop that runs to the racks from the facility water system that runs back to the central plant, and it controls flow, pressure and temperature on the rack side. CDUs can be in-row, at the end of a row, or in a gallery outside the data hall, depending on the owner's standard.

On the facility side, the water temperature the IT gear will accept drives the whole plant design. ASHRAE TC 9.9's Thermal Guidelines, 5th edition (March 2021), define liquid cooling classes by the upper limit of facility water temperature: W17, W27, W32, W40, W45 and W+ (above 45°C), according to a July 2024 summary from Upsite Technologies. The lower classes need chillers to hold temperature; the warmer classes can run on cooling towers or dry coolers for much of the year. That is why many GB200-era designs lean on warm-water loops, and why the chiller tonnage on an AI campus can look small relative to its IT load.

Most hyperscale AI halls today use cold plates for the chips and keep some air cooling for memory, storage, power supplies and networking gear. That is the "hybrid" in the Vertiv reference design. Plan on both systems in the same room.

Immersion

Immersion cooling puts the whole server in a tank of dielectric fluid. In single-phase immersion the fluid stays liquid and is pumped through a heat exchanger. In two-phase immersion the fluid boils off the hot components, condenses on a coil at the top of the tank, and drips back down.

Immersion changes the room more than cold plates do. Racks become horizontal tanks, the floor has to carry fluid-filled tanks rather than standard racks, and the owner will want spill containment details worked out in the slab design rather than added later. Tank weights and fluid volumes are set by the specific vendor's product, so pull them from the submittal data rather than from a rule of thumb.

Two-phase immersion has an extra supply-chain question. Many of the engineered fluids used for two-phase cooling were fluorinated chemicals, and 3M, a major supplier, announced on December 20, 2022 that it would exit PFAS manufacturing and work to discontinue PFAS use across its portfolio by the end of 2025. Owners specifying two-phase systems now have to confirm which fluid will be used and whether it remains available and permitted for the life of the facility. That uncertainty is one reason cold plate systems have taken the lead in large AI deployments.

What Changes on the Job

Piping becomes the critical path

An air-cooled hall has a modest number of large chilled water connections serving air handlers. A liquid-cooled hall adds a secondary loop with branch piping, manifolds and quick-disconnects serving every rack or tank. The connection count per data hall goes up sharply, and every one of those joints sits above or near equipment the owner cannot afford to get wet.

That pushes the mechanical scope toward the standards pipefitters know from pharmaceutical and semiconductor work: clean cutting and joining, documented flushing, water treatment and filtration before the loop ever touches a server, and pressure testing to the project specification and the governing piping code. The test procedures, hold times and acceptance criteria belong in the contract documents. Read them before you bid, because a hall that fails a hold test after the racks are set is an expensive problem for everyone.

Leak detection and controls

Owners are adding leak detection cable under and around piping runs, isolation valves at row and rack level, and CDU controls tied into the building management system. Controls integrators and commissioning agents get a bigger role, and the electrical scope picks up power and monitoring for the CDUs themselves.

Raised floors are optional

Liquid-cooled halls don't need an underfloor air plenum. Many new AI halls are built slab-on-grade with overhead piping, power busway and cable tray, which means more coordination in the overhead zone and heavier hanger and support design. Some owners still use raised floor for piping or cabling, so check the basis of design rather than assuming either way.

The central plant looks different

Warm-water liquid loops let designers lean on cooling towers, dry coolers and economizer hours instead of compressor-based cooling. That shift interacts with water use. Microsoft said in December 2024 that beginning in August 2024 it launched a new data center design that "consumes zero water for cooling," using chip-level cooling and a closed loop. Microsoft said projects in Phoenix, Arizona and Mt. Pleasant, Wisconsin would pilot the design in 2026, that new sites on the design would begin coming online in late 2027, and that each would avoid more than 125 million liters of water per year. Microsoft also said the move from evaporative to mechanical cooling would increase its power usage effectiveness (PUE), offset in part by warmer-water chillers. For contractors, a closed-loop design means more mechanical cooling equipment and fewer evaporative towers.

Equipment prices have moved

Cooling gear has gotten more expensive along with everything else in the data center supply chain. CRE Daily's August 27, 2026 summary of Cushman & Wakefield's 2026 Data Center Development Cost Guide reports that all-in greenfield costs in the U.S. and Canada run $8.9 million to $23.3 million per MW (excluding chips and GPUs), up 21% per MW since the late-2024 edition. The same summary lists cooling equipment prices up 32%, switchgear up 60% (December 2021 to early 2026) and generators and motors up 33%. JLL's 2026 Global Data Center Outlook (January 5, 2026) forecasts shell-and-core costs of $11.3 million per MW and says tenant fit-out for AI infrastructure can reach $25 million per MW. Liquid cooling equipment sits largely in that tenant fit-out bucket.

For a more detailed cost breakdown, see our data center construction cost per square foot and per MW guide.

Who Is Driving It

The demand side is the hyperscale and AI cloud operators deploying GPU clusters. NVIDIA's rack-scale platforms set the density; companies such as Vertiv and Schneider Electric are building the power and cooling packages around them.

The supplier side has been consolidating. Schneider Electric agreed in October 2024 to buy an initial 75% stake in Motivair, a Buffalo, New York liquid cooling company, for $850 million in cash, with the remaining 25% expected in 2028, according to Facilities Dive (October 21, 2024). The same article cited a July 2024 Dell'Oro Group projection that the data center liquid cooling market would exceed $15 billion by 2028. Treat that as a forecast from one analyst firm, not a measured market size.

On the U.S. construction side, the volume is real. Census Bureau data put data center construction spending at a $84.95 billion seasonally adjusted annual rate in August 2026, up 73.2% from a year earlier. Not all of that is liquid-cooled, but the AI share of new capacity is where the high-density, liquid-cooled halls are concentrated. For the trade-by-trade labor picture, see our breakdown of data center construction wages by trade.

What Mechanical and Electrical Contractors Should Do

Get your fitters trained on clean piping practice. Flushing, filtration, water treatment and documented pressure testing are the core of a liquid cooling scope. Fitters with pharmaceutical, semiconductor or lab process piping experience transfer well.

Learn the CDU and manifold products your target owners use. Each owner tends to standardize on a short list of CDU vendors and quick-disconnect hardware. Factory training and installer familiarity with those products shortens startup and reduces punch-list risk.

Price the testing and commissioning scope honestly. Flushing, water treatment, hold tests, leak detection verification and integrated systems testing take crew time and calendar time. They are easy to underestimate on a first job.

Plan for hybrid rooms. The Uptime numbers show most facilities still run air-cooled racks, and even GB200 reference designs keep an air component. Contractors who can build, test and commission both systems in the same hall are the ones owners call back.

Watch the long-lead list. Cooling equipment is on the same constrained supply chain as switchgear and generators. Confirm CDU and chiller lead times at bid time, not at buyout. Our guide to data center electrical equipment lead times covers the power side of that schedule.

The Bottom Line

Liquid cooling is no longer an experiment at the top of the market. NVIDIA's GB200 reference design puts up to 132 kW in a single rack, Uptime's 2026 survey shows the share of sites with racks at 50 kW or more rising year over year, and Census data shows data center construction spending running at a record pace. At the same time, most existing data halls are still air-cooled, which means the near-term work splits between new liquid-first AI campuses and retrofits that add a liquid loop to existing rooms.

For mechanical and electrical subcontractors, the scope that matters is precision piping, testing and controls integration. Firms that build that capability now will be in a better position as more owners standardize on liquid-cooled designs.


READ NEXT: Prefab and Modular Data Centers — The Factory-Built Future

FAQ

How much heat does an AI rack put out compared with a typical rack?

Vertiv's October 2024 reference architecture for NVIDIA's GB200 NVL72 supports up to 132 kW per rack. By contrast, Uptime Institute's 2026 Global Data Center Survey found that 69% of operators report a most-common rack density under 10 kW. The gap between those two numbers is why AI halls are designed around liquid cooling from the start.

Is direct-to-chip or immersion cooling more common in new AI data centers?

Direct-to-chip (cold plate) cooling, usually paired with some air cooling for the remaining components, is the approach used in reference designs such as Vertiv's GB200 NVL72 architecture. Immersion is used in some deployments but changes the room layout more, and two-phase immersion faces fluid supply questions after 3M's December 2022 commitment to exit PFAS manufacturing by the end of 2025.

Does liquid cooling make a data center cheaper to build?

There is no published, sourced figure showing a net construction cost reduction, and costs are rising overall. A summary of Cushman & Wakefield's 2026 Data Center Development Cost Guide puts all-in U.S. and Canada greenfield costs at $8.9 million to $23.3 million per MW excluding chips, up 21% per MW since late 2024, with cooling equipment prices up 32%. JLL's 2026 outlook says AI tenant fit-out can add up to $25 million per MW on top of shell and core.

What facility water temperatures do liquid-cooled servers use?

ASHRAE TC 9.9's Thermal Guidelines, 5th edition (2021), define facility water classes W17, W27, W32, W40, W45 and W+ by their upper temperature limit in degrees Celsius. The warmer classes allow more cooling-tower or dry-cooler operation and less chiller use. The design class comes from the IT vendor's spec and the owner's basis of design.

Q: What should a mechanical contractor expect in testing and turnover on a liquid-cooled hall? Expect flushing and water treatment before the loop is connected to IT equipment, pressure hold tests to the project specification and governing piping code, leak detection verification, and integrated systems testing with the CDU controls and building management system. The specific test pressures, hold durations and documentation requirements are set in the contract documents, so read them before you price the job.

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
gavel

Find commercial construction bids in your state

Live federal solicitations from SAM.gov — filtered by state, value, and trade.

Browse open bids