Nobody publishes a reliable national total for the culvert replacement backlog under rural roads. Culverts under 20 feet of span are not in the National Bridge Inventory, and most are owned by counties, towns and forest road agencies that keep their own records, if they keep them at all. What is published is more useful for contractors anyway: hard numbers from the programs that are actually paying for culvert replacement, and what those programs have learned about cost.
An earlier version of this article cited an $18 billion rural backlog, a $45,000 median cost per culvert, state allocation figures for a "formula" culvert program, per-foot pipe prices, margin percentages and three first-person job stories. None of that could be verified, and the federal culvert program is a competitive grant, not a formula allocation to states. Those claims have been removed.
The Federal Program: Culvert AOP Grants
The Infrastructure Investment and Jobs Act created the National Culvert Removal, Replacement, and Restoration Grant program, which FHWA runs as the Culvert Aquatic Organism Passage (Culvert AOP) program. According to FHWA's FY2023-2026 notice of funding opportunity, IIJA appropriated $200 million a year for FY2022 through FY2026, or $1 billion in total. Program funds are available until expended, with no obligation or expenditure deadline.
Key rules from the NOFO and FHWA's program page (updated June 24, 2026):
- It is competitive. States, units of local government and Indian Tribes apply directly; there are no formula allocations to states.
- Projects must replace, remove or repair culverts or weirs in a way that meaningfully improves or restores passage for anadromous fish (species such as salmon, steelhead, shad, river herring, lamprey and sturgeon).
- The program prioritizes projects that would open more than 200 meters of upstream habitat (49 U.S.C. 6703(e)(2)).
- The federal share is 80 percent for states and local governments, which must provide at least a 20 percent match. Tribes are not required to provide a cost share.
- There is no minimum or maximum award size.
Where the money stands
The first round, FY2022, put $196 million toward 59 tribal, state and local governments to fix or remove 169 culvert barriers and reopen about 550 miles of stream habitat, AASHTO Journal reported on August 25, 2023. One example: Maine DOT received $9.2 million to replace nine barriers at road crossings and improve access to 37 miles of habitat, which works out to roughly $1 million per crossing.
The remaining four years of funding were folded into one competition. FHWA announced up to $800 million in FY2023-2026 funds on June 2, 2026, replacing a June 2024 notice; applicants under the earlier notice had to resubmit using a mandatory template. Applications closed July 16, 2026. The NOFO said FHWA anticipated announcing selections the last week of August 2026, but as of FHWA's program page update no awards from this round were posted. When selections are announced, they become the construction pipeline for 2027 and 2028.
The match is the bottleneck for small owners
A 20 percent local match on a $1 million crossing is $200,000, which can be a large share of a small county's annual road budget. Tribes, which do not need a match, and state DOTs with dedicated fish-passage programs are better positioned to use the money. For a broader look at how federal-aid programs reach contractors, see our IIJA contractor guide.
What Fish-Passage Culverts Actually Cost: The Washington Example
Washington is the clearest public cost record for fish-passage culvert replacement, because its program has been under a federal court order for more than a decade. According to WSDOT, 21 northwest Washington tribes sued over culverts under state roads, and in March 2013 the court issued a permanent injunction requiring the state to significantly increase its effort to remove state-owned culverts that block salmon and steelhead habitat.
Under the injunction, as WSDOT summarized it for the Washington State Transportation Commission in October 2024, the state must open 90 percent of blocked habitat behind its 2013 "significant gain" barriers (those with more than 200 meters of upstream habitat) by 2030, and correct the rest at the end of the structure's life or as part of other projects.
Progress and cost, from WSDOT's own reporting:
| Measure | Figure | Source date |
|---|---|---|
| Injunction barrier culverts corrected | 176 | June 1, 2025 |
| Habitat access improved | About 655 miles | June 1, 2025 |
| Injunction barrier culverts corrected | 200 | June 2026 |
| Habitat access improved | 705 miles | June 2026 |
| Barriers expected under contract in the 2025-27 biennium | 155 to 175 | October 2025 letter to the Legislature |
The program estimate is the number that should get an estimator's attention. WSDOT's October 2024 presentation lists the history of its injunction compliance estimate:
| Year | Program estimate | Note |
|---|---|---|
| 2009 | $1.88 billion | Did not include inflation |
| 2012 | $2.4 billion | Included inflation and steady delivery through 2030 |
| 2018 | $3.8 billion | Higher program-level estimate, updated inflation |
| 2023 | $7.8 billion | Site-specific program-level estimate |
| 2024 | $8.8 billion | Includes structurally failing culverts |
WSDOT gave five reasons the estimate kept rising: planning-level assumptions replaced by engineered estimates, high-complexity sites, a large amount of work compressed into a short timeframe (with more consultant use and alternative delivery), construction volatility, and cost escalation.
The same presentation lists the ten highest-cost remaining barriers not yet under contract. They range from $80 million (I-5 at Indian Creek) to $240 million (I-90 at an unnamed tributary to Lake Creek), totaling $1.3 billion. Those are not culvert swaps. They are interstate crossings where a fish-passable structure means a new bridge, a relocated ramp, a new stream channel and utility relocations. WSDOT's example at I-90 and Lewis Creek involves four new bridges, a relocated on-ramp, a new roundabout, a noise wall relocation and a new stream channel.
Why Fish-Passage Culverts Cost More Than Pipe Swaps
A like-for-like pipe replacement and a fish-passage crossing are different jobs. The cost drivers that separate them:
- Structure type. Passage designs usually need a wider opening with a natural streambed through it, which pushes the structure from round pipe to open-bottom arches, three-sided precast boxes or short-span bridges.
- Stream simulation. Placing and grading streambed material inside and through the structure, often to a design gradation, is real work with its own inspection.
- Water management. Stream diversion, dewatering, fish exclusion and relocation must happen inside agency in-water work windows, which can force schedules into a few summer months.
- Traffic. A crossing under a through road needs a detour, staged construction or a temporary bridge. On federal-aid highway projects, 23 CFR 630.1108(f) requires traffic control to be paid through separate pay items rather than as incidental work.
- Depth and fill. Deep fills mean more excavation, shoring and haul. Our excavation cost per cubic yard guide covers current unit costs from DOT bid data.
- Materials. Steel and precast concrete dominate structure cost. BLS producer price indexes for September 2026 show steel mill products up 27.6 percent year over year and ready-mix concrete up 2.3 percent (index changes, not dollar prices).
Because of those items, it is common for a fish-passage replacement to cost several times what the old pipe did. The Maine and Washington figures above show the range: about $1 million per crossing in a statewide package on rural roads, and up to hundreds of millions where a crossing sits under an interstate.
How to Position for the Work
- Track the Culvert AOP selections. When FHWA announces the FY2023-2026 awards, the recipient list names every sponsor and project. Each one becomes a design contract and then a construction bid.
- Learn the in-water work windows in your state. They drive crew planning and can make or break a schedule.
- Team with stream restoration specialists if you do not self-perform streambed construction, planting and bank stabilization. Many specifications treat that scope as integral to the crossing.
- Watch for bundled and progressive design-build contracts. WSDOT describes progressive design-build as a new delivery method for its program, used to get many sites under contract at once.
- Read the federal requirements in the bid package. Federally funded crossings carry domestic-content and wage provisions that small local owners do not always spell out clearly, so ask before bid day.
Culvert work also overlaps with small-bridge replacement, since a crossing that grows past 20 feet of span becomes a bridge for inventory purposes. Our rural bridge replacement guide covers that side of the market, and our coverage of water main break costs shows a similar funding gap on buried water infrastructure.
To put these numbers to work on your next bid, start with our free construction cost estimator and the markup margin calculator.
Your Action Item for This Week
Pull the FY2022 Culvert AOP award list for your state and find which sponsors have not yet advertised construction. Then check whether those same sponsors applied in the 2026 round. Owners who already have one funded crossing in design are the most likely to have a second one coming, and the design consultant on the first job is the person to call.
Frequently Asked Questions
How much federal money is available for culvert replacement?
IIJA appropriated $200 million a year for FY2022 through FY2026, $1 billion in total, for FHWA's Culvert AOP grant program. The first round awarded $196 million in 2023 for 169 barriers. Up to $800 million in FY2023-2026 funds was offered in a June 2026 notice; applications closed July 16, 2026, and selections had not been posted on FHWA's program page as of its last update.
Who can apply for Culvert AOP grants?
States, units of local government and Indian Tribes. Projects must improve passage for anadromous fish. States and local governments pay at least a 20 percent match; Tribes do not have to provide a match.
What does a fish-passage culvert replacement cost?
It varies with the crossing. Maine DOT's 2023 grant was $9.2 million for nine barriers, about $1 million each. Washington's most expensive remaining injunction crossings under interstates are estimated at $80 million to $240 million each, and WSDOT's total program estimate reached $8.8 billion in 2024.
Why do fish-passage projects cost more than replacing a pipe?
They usually require a wider structure with a natural streambed, stream diversion and fish relocation inside limited in-water work windows, and often a detour or staged construction. Interstate crossings can require new bridges, ramps and stream channels.
What is Washington's culvert injunction?
A permanent federal court injunction issued in March 2013 after 21 northwest Washington tribes sued over state-owned culverts that block salmon and steelhead. WSDOT must open 90 percent of blocked habitat behind its 2013 significant-gain barriers by 2030. As of June 2026, WSDOT had corrected 200 injunction barrier culverts and improved access to 705 miles of habitat.