The Federal Highway Administration's 2026 bridge condition table, dated August 4, 2026, lists 624,939 highway bridges in the National Bridge Inventory (NBI), including Puerto Rico and the U.S. Virgin Islands. Of those, 41,148 are rated in poor condition. That is 6.6% of the inventory. Another 315,054 (50.4%) are rated fair and 268,737 (43.0%) are rated good.
An earlier version of this article put the count at 42,966 "structurally deficient" bridges and the repair backlog at $319 billion, citing a January 2026 data update and the ASCE report card. Neither figure matches the published sources. The 2026 FHWA table shows 41,148 poor bridges, and the dollar figures ASCE and ARTBA actually publish are covered below.
The direction of the trend is right. FHWA's 2016 table counted 48,559 poor bridges out of 614,387 (7.9%). The 2025 table counted 41,685 out of 624,193 (6.7%). So about 7,400 fewer bridges are rated poor than a decade ago, even though there are about 10,500 more bridges in the inventory.
"Structurally deficient" vs. "poor": what the rating means
FHWA's bridge tables no longer use the term "structurally deficient." Since the Pavement and Bridge Condition Performance Measures rule (published January 2017), FHWA classifies every bridge as Good, Fair or Poor using its lowest NBI condition rating for the deck, superstructure, substructure or culvert:
- Good: lowest rating is 7 or higher (on a 0 to 9 scale)
- Fair: lowest rating is 5 or 6
- Poor: lowest rating is 4 or lower
Many groups still call poor bridges structurally deficient. ARTBA's 2025 Bridge Report, for example, labels its count "Poor (Structurally Deficient)." The two terms describe roughly the same set of bridges, so this article uses FHWA's "poor" for the official count.
A poor rating does not mean a bridge is about to fail. It means at least one major component shows advanced deterioration, such as section loss, spalling, cracking or scour, and the bridge is a candidate for major rehabilitation or replacement. Owners handle these bridges with load postings, closer inspections and interim repairs.
Inspection intervals under the current NBIS
The earlier version of this article said every poor bridge must be inspected at least every 12 months. That is not what the rule says. Under 23 CFR 650.311 (eCFR, current as of October 2026):
- Routine inspections are required at intervals not to exceed 24 months under the standard (Method 1) approach.
- Intervals must be cut to no more than 12 months when the deck, superstructure, substructure or culvert is rated 3 ("serious") or lower, or when the observed scour condition is rated 3 or lower.
- Bridges in good shape can go up to 48 months if they meet every condition in the rule, including all component ratings of 6 or better and no load restrictions.
So a bridge rated 4 (poor) is not automatically on a 12-month cycle. The owner's own reduced-interval criteria decide that. The 12-month federal minimum applies once a component drops to 3.
State rankings: where the poor bridges are
These counts come from the FHWA 2026 condition table. Percentages are poor bridges divided by each state's total bridge count.
| State | Total bridges | Poor | Share poor |
|---|---|---|---|
| Iowa | 23,398 | 4,279 | 18.3% |
| Pennsylvania | 23,333 | 2,718 | 11.6% |
| Illinois | 26,946 | 2,584 | 9.6% |
| Missouri | 24,696 | 2,158 | 8.7% |
| New York | 17,613 | 1,780 | 10.1% |
| Oklahoma | 22,929 | 1,620 | 7.1% |
| North Carolina | 19,331 | 1,483 | 7.7% |
| Louisiana | 12,647 | 1,304 | 10.3% |
| West Virginia | 7,305 | 1,212 | 16.6% |
Iowa has by far the most poor bridges. That is mostly a function of its huge rural inventory of short county spans. By share of inventory, the highest rates among the states are Iowa (18.3%), West Virginia (16.6%), Maine (15.2%, 387 of 2,538), South Dakota (14.8%, 871 of 5,891) and Rhode Island (12.2%, 95 of 780). Puerto Rico is also high at 14.0% (343 of 2,450).
The lowest shares are Delaware (1.0%, 9 of 888), Arizona (1.1%, 92 of 8,590), Texas (1.1%, 619 of 57,571) and Nevada (1.4%, 30 of 2,136). Texas stands out: it has the largest inventory in the country and one of the smallest shares of poor bridges.
The earlier version of this article listed different state counts and percentages (for example, 4,571 in Iowa and a 21.4% rate in West Virginia). Those did not match any FHWA table and have been replaced.
Who improved and who slipped, 2025 to 2026
Comparing the 2025 and 2026 FHWA tables, the national poor count fell by 537. California had the biggest drop (1,284 to 891, down 393), followed by Iowa (down 144), Louisiana (down 119), Mississippi (down 117), Oklahoma (down 99) and Pennsylvania (down 95). The biggest increases were South Carolina (up 121), Ohio (up 104), North Carolina (up 101), Kentucky (up 94) and Kansas (up 69).
A one-year swing in either direction often reflects inspection timing. Most bridges are inspected every two years, so a repaired bridge may not move out of the poor column until its next cycle.
Age and condition trends
ASCE's 2025 Report Card for America's Infrastructure, which gave bridges a C, says the nation's 623,218 bridges have an average age of about 47 years and that roughly 45% have exceeded their planned design lives of 50 years. ASCE also notes that new highway bridges have been required since 2007 to have a minimum 75-year design life. The earlier version of this article gave an average age of 44 years and a breakdown of bridges by construction decade that we could not verify. Those have been removed.
ASCE says the share of bridges in poor condition fell from 8.7% in 2014 to 7.3% in 2020 and 6.8% in 2024, and the share of bridge deck area in poor condition fell from 6.7% in 2014 to 4.9% in 2024. FHWA's 2026 table puts poor deck area at about 4.8% of the national total. The catch, which both ASCE and ARTBA point out, is the fair category. Fair bridges now outnumber good ones (315,054 vs. 268,737 in the 2026 FHWA table), and each fair bridge that isn't maintained eventually drops to poor.
ASCE also reports that 63,085 bridges were posted for load in 2024, and that about 22,420 bridges are susceptible to extreme storm events.
What it costs: the backlog numbers that are actually published
There is no single official "repair backlog" figure, and the published estimates measure different things. The earlier version of this article cited a "$319 billion" ASCE estimate with a three-part breakdown. That figure and breakdown do not appear in ASCE's report card. Here is what the sources actually say:
- FHWA (as cited by ASCE, 2023 data): replacing the bridges currently in poor condition would cost $69.7 billion, and rehabilitating them would cost $47.4 billion.
- ASCE 2025 Report Card: system rehabilitation needs for bridges are estimated at $191.3 billion. Separately, ASCE's "Bridging the Gap" analysis puts the funding gap at $373 billion over 10 years to bring the nation's bridges to a state of good repair.
- ARTBA 2025 Bridge Report: using average cost data states submit to U.S. DOT, ARTBA estimates $467 billion to make all identified repairs on the roughly 220,300 bridges (35% of the inventory) it says need major repair or replacement, including 74,472 it says should be replaced.
These numbers differ because they count different bridges (poor only vs. poor plus fair) and different work (replacement vs. all needed repair). If you are quoting a backlog in a proposal or board memo, say which one you are using.
We also removed the claim that FHWA puts the average cost to replace a poor bridge at $4.35 million, along with the average-span and deck-width figures. We could not find them in FHWA publications. For the price of specific large projects, our tracker of major US bridge projects lists sourced contract values.
Federal bridge money under the IIJA
The Infrastructure Investment and Jobs Act set up two dedicated bridge programs, according to the Congressional Research Service (CRS R47022):
- The Bridge Formula Program provides $27.5 billion over FY2022 to FY2026, $5.5 billion a year. Funds are apportioned by each state's relative cost to replace poor bridges and rehabilitate fair ones. At least 15% must go to bridges off the federal-aid system, and the federal share can be 100% for publicly owned bridges below the state level.
- The Bridge Investment Program (BIP) is a discretionary program funded at $12.5 billion of contract authority over the five years, plus an average of $653 million a year authorized subject to appropriation.
The earlier version of this article added the two programs together as "$40 billion" and said "$27 billion" had reached states through Q1 2026. Neither is accurate. ARTBA's 2025 report, using Treasury data as of June 30, 2025, says states had received $21.2 billion of formula bridge money in the first four years and had committed 55% of it ($11.7 billion) to more than 6,000 bridge projects. Georgia, North Dakota and Alabama had committed 97% or more of their available funds. The same report says BIP had awarded $7.8 billion for 87 planning, small and large bridge grants in more than 40 states.
The largest single BIP award is the Brent Spence Bridge Corridor between Cincinnati and Covington, Kentucky. On December 29, 2022, the Ohio and Kentucky transportation departments received $1.635 billion in federal grants: $1.385 billion from BIP and $250 million from the MEGA program, according to the City of Cincinnati.
The funding clock matters for contractors. IIJA highway authorizations were extended through December 11, 2026 (H.R. 6500), according to CRS report R48937, updated September 11, 2026. Whether bridge formula money continues at $5.5 billion a year depends on what Congress passes next. For how state DOTs are budgeting around that, see our state DOT budget analysis.
What the cost drivers look like on a bid
We have removed the earlier version's percentage add-ons for traffic control and environmental work, permitting timelines, bridge-specific steel and concrete price changes, and trade wage rates. None of them traced to the agencies they were attributed to. What can be said with sources:
- Construction input prices are rising quickly. The BLS Producer Price Index for net inputs to construction industries (goods) was up about 11% from September 2025 to September 2026 (FRED series WPUIP2300001). That is an index, not a price per ton or per yard.
- Bridge-specific materials (structural steel, precast and prestressed girders, rebar, ready-mix) are priced locally and move with mill and plant availability. The best current numbers are your state DOT's recent bid tabs and weighted-average unit price reports.
- Federal-aid bridge work carries Davis-Bacon wage rates and Buy America requirements for iron and steel, both of which set labor and material cost floors before you price anything else.
What contractors should do now
The bridge market has three tiers. A small number of very large BIP-funded corridor projects. A steady flow of state DOT replacement and rehab lettings funded by formula money. And a long tail of county and municipal bridge replacements, which the 15% off-system set-aside helps pay for.
For most mid-size heavy civil firms, the county and state replacement work is the realistic target. Practical steps:
- Pull your state's NBI condition data (FHWA publishes it by state and county) and map where poor bridges cluster. Those counties are where replacement lettings will come from.
- Check your state's committed share of bridge formula funds. States that have already committed most of their money (per ARTBA's tracking) will have more projects under construction. States with large uncommitted balances may have a backlog of lettings coming.
- Make sure your welders hold AWS D1.5 (Bridge Welding Code) qualifications if you self-perform structural steel, and confirm your Buy America documentation process before you bid federal-aid work.
- Watch the December 11, 2026 authorization deadline. A lapse or a short extension tends to delay new state lettings.
Frequently Asked Questions
How many structurally deficient bridges are there in the US?
FHWA's 2026 National Bridge Inventory table (dated August 4, 2026) rates 41,148 bridges in poor condition, the category commonly called structurally deficient. That is 6.6% of 624,939 bridges, including Puerto Rico and the U.S. Virgin Islands. The 2025 count was 41,685, and the 2016 count was 48,559.
Which state has the most poor-condition bridges?
Iowa, with 4,279 poor bridges, 18.3% of its 23,398-bridge inventory (FHWA 2026). Pennsylvania (2,718), Illinois (2,584) and Missouri (2,158) are next. By share of inventory, West Virginia (16.6%), Maine (15.2%) and South Dakota (14.8%) follow Iowa.
How much would it cost to fix them?
It depends on which estimate you use. FHWA puts the cost to replace bridges currently in poor condition at $69.7 billion (2023 data, cited by ASCE). ASCE estimates $191.3 billion in bridge rehabilitation needs and a $373 billion 10-year funding gap. ARTBA's 2025 report estimates $467 billion to repair all of the roughly 220,300 bridges it says need major work.
Is IIJA bridge funding enough?
The IIJA provides $27.5 billion in formula bridge funds and $12.5 billion for the competitive Bridge Investment Program over FY2022 to FY2026 (CRS). As of mid-2025, states had committed $11.7 billion of the $21.2 billion in formula funds released to them (ARTBA). That is a meaningful increase, but it is well short of even FHWA's $69.7 billion replacement figure for poor bridges alone, and the authorization currently runs only through December 11, 2026.



