ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Economy

WIP Reports for Contractors: How to Stop Misjudging Profit on Active Jobs

Mike Callahan·May 22, 2026·Updated October 18, 2026·12 min read

Share this with your estimator.

WIP Reports for Contractors: How to Stop Misjudging Profit on Active Jobs

Most contractors find out a job is losing money too late, and usually for the same reason. The billing looked fine, the cash came in, and nobody updated the cost-to-complete. A work-in-progress (WIP) schedule is built to catch that. It puts every open contract on one page and forces the question of whether the job is making the money you think it is.

This guide covers how the WIP math works, how it fits US accounting rules under ASC 606, what the tax rules say about percentage-of-completion, and what a surety underwriter does with your schedule. The dollar examples are hypothetical and are there only to show the arithmetic.

An earlier version of this article opened with a first-person story and included specific thresholds, such as an under-billing "red flag" percentage, a quarterly surety "floor" and software size bands, that we couldn't source. We removed them.

What a WIP schedule tells you

A WIP schedule lists each open contract with at least these columns:

  • Contract value, including approved change orders
  • Costs incurred to date
  • Estimated total cost at completion, which is costs to date plus estimated cost to complete
  • Billings to date

From those inputs it calculates the percent complete, revenue earned to date, gross profit earned to date, and whether the job is over-billed or under-billed.

The most common way to measure progress is cost-to-cost:

Percent complete = costs incurred to date ÷ estimated total cost at completion

Here's a worked example with made-up numbers. A $1,000,000 contract has $480,000 of cost incurred and an estimated total cost of $800,000. It's 60% complete, so earned revenue is $600,000. If you've billed $700,000, you're over-billed by $100,000. If you've billed $550,000, you're under-billed by $50,000.

Everything that follows comes back to that calculation.

How the accounting rules frame it

ASC 606 and cost-to-cost

Under US GAAP, revenue from contracts with customers falls under ASC 606. Construction contracts commonly meet the criteria for recognizing revenue over time, and many contractors still measure progress with the cost-to-cost input method. Wiss, a CPA firm, makes the point in its January 6, 2026 guidance for contractors, and it notes that the method has to be adjusted for costs that don't reflect progress.

Two adjustments matter on almost every WIP:

  • Uninstalled materials. When major materials are delivered but not installed, counting their full cost toward percent complete can overstate progress. Wiss describes excluding those costs from the progress measure and, where control has transferred, recognizing revenue on the material at cost (zero margin), with margin earned as the remaining work is done.
  • Inefficient costs. Wiss also says inefficient costs must be excluded from the progress measure. Its examples are materials over-bought because of poor planning and cost overruns from rework, because those costs "don't represent progress toward completing the performance obligation."

That second point is why rework and productivity losses shouldn't push your percent complete up. If they do, the WIP recognizes revenue and profit you haven't earned.

Contract assets and liabilities

ASC 606 also changed how these balances appear on the balance sheet. EisnerAmper's guidance for the construction industry explains that contract assets and liabilities are accumulated and presented on a net basis at the individual contract level. Contract assets include costs and estimated earnings in excess of billings (under-billings), retainage receivable, and uninstalled materials. Contract liabilities include billings in excess of costs and estimated earnings (over-billings), net of conditional retainage receivable.

Many contractors and sureties still say "over-billings" and "under-billings." On GAAP statements, the captions are contract assets and contract liabilities.

Retainage is conditional

The same EisnerAmper guidance notes that retainage is usually conditional, because payment depends on completing future obligations under the contract. Under ASC 606, conditional retainage belongs in the contract asset or liability, not in ordinary receivables. In practice, money held as retainage is not cash you can plan around until the conditions for release are met. Track it on its own line on the WIP: amount held, release conditions and expected release date.

Loss jobs get recognized in full, right away

When a contract is expected to lose money, the whole projected loss is booked when it becomes evident. It is not spread over the rest of the job. LaPorte, a CPA firm, cites FASB ASC 605-35-25-46, which still applies to construction-type contracts after ASC 606 took effect: when current estimates of total contract revenue and cost show a loss, the entire loss is recognized in the period it becomes evident.

That's why a cost-to-complete update can move year-end results so sharply. When the update turns a job from profit to loss, you reverse the profit already recognized and book the full projected loss in the same period.

What the tax rules say

Tax accounting for long-term contracts is separate from GAAP. Under Internal Revenue Code section 460, long-term construction contracts generally use the percentage-of-completion method. Section 460(e) exempts home construction contracts and certain other construction contracts. To qualify, the taxpayer must estimate at the start that the contract will be completed within two years, and must meet the gross receipts test of section 448(c) for the year the contract is entered into.

For taxable years beginning in 2026, IRS Revenue Procedure 2025-32 sets the section 448(c) threshold at average annual gross receipts of $32,000,000 or less over the prior three tax years. If you're near that line, talk to your CPA before the year you cross it. The switch affects how you report contracts already in progress.

Your tax method and your GAAP statements can differ. The WIP you give your surety should follow your GAAP statements.

Over-billings: useful cash, but they can hide a fade

Over-billing early in a job is common. Front-loaded schedules of values, mobilization and early-trade billing bring cash in before it's earned. That isn't wrong. The risk is in what it can hide.

If cost-to-complete goes up and nobody updates it, the WIP keeps showing the original margin while the cash cushion from over-billing covers the gap. When the estimate finally catches up, percent complete drops, the over-billing gets larger, and the projected margin falls, often by a lot and all in one period. Under the loss rule above, if the job goes into a loss, the whole loss is booked at once.

Sureties know this pattern. In a CBIZ article on surety bonding, the firm says the work schedules in a contractor's statements should tie into the balance sheet and income statement, so the underwriter can see "what projects are overbilled or under billed, and if there are any jobs with gross profit fades."

The fix is operational. Cost-to-complete needs a real update from the project manager on a regular schedule, not a budget-minus-actuals calculation.

Under-billings: find out why

An under-billing means you've earned more than you've invoiced. Common causes:

  • Changed work done without a signed change order, so there is cost but no contract value to bill against
  • A schedule of values or pay application that hasn't kept up with progress in the field
  • A pending change order that the owner or GC hasn't approved

Some under-billings are timing and clear up with the next pay application. Others are unapproved scope you may never collect. The WIP review is where you figure out which is which and assign someone to get the paperwork signed.

Cost-to-complete is the number that matters

Every other number on the WIP depends on the estimated cost to complete. Subtracting spent-to-date from the original budget gives you remaining budget, not cost to complete. A real estimate works through each remaining cost code:

  1. What scope is actually left in the field, not in the budget?
  2. What are unit costs actually running at, and what happens if that rate continues through the remaining work?
  3. Which changes are coming, both billable additions and unrecoverable overruns?
  4. What schedule, weather, supply or labor risks are left, and what's a realistic allowance for them?

An honest cost-to-complete moves from period to period, up when problems show up and down when a favorable buyout locks in. If the projected margin on a job never changes, ask how it's being estimated. You can sanity-check margins with the markup and margin calculator.

Change orders: approved or pending

Decide on a written policy for how pending change orders show up on the WIP, and apply it the same way every time. Whether and how unapproved changes can be counted in the transaction price is an accounting judgment under ASC 606, so set the policy with your CPA. Operationally, the safest rule is to keep the cost on the WIP and keep unsigned changes out of contract value until they are approved in writing. Then track the pending amounts on a separate log so they stay visible.

What your surety does with the WIP

Surety underwriting is built around a contractor's financial statements and the job schedules attached to them. The CBIZ article lays out what underwriters expect:

  • Statement level. CBIZ describes three levels of CPA work: compilation, review and audit. It says most sureties will require at least a review-level statement. Compiled statements limit how large a job you can bid and how much total work you can carry. Audits give the most assurance.
  • Percentage-of-completion accounting. CBIZ says sureties require statements prepared on a percentage-of-completion basis, so the underwriter can see sales, gross profit, receivables, under-billings, payables and over-billings by project.
  • Work schedules for open and closed jobs. Year-end and interim statements should include schedules for open and completed jobs, plus breakdowns of direct and overhead costs, all tied to the balance sheet and income statement.

Gross profit fade is the thing those schedules are built to expose. If jobs keep finishing at lower margins than your earlier WIPs showed, the underwriter will discount your current projections. If margins hold up through completion, your estimates gain credibility. Our construction bonding guide explains how capacity is set, and our report on bonding capacity tightening covers current underwriting conditions.

Building a WIP routine

A WIP only helps if it's current. A schedule built once a year for the surety tells you what already happened. One updated regularly lets you act while there's still time to recover. A workable routine:

  • Project managers update cost-to-complete and pending changes on every active job on a set schedule.
  • Accounting ties costs and billings to the general ledger and produces the schedule.
  • Ownership reviews any job whose projected margin moved, every under-billing, and every job projected to lose money, and assigns follow-up.
  • The CPA reviews the policies for uninstalled materials, inefficient costs, change orders and loss provisions at least once a year, before the year-end statement.

Spreadsheets work for many smaller contractors. Larger firms usually pull the WIP straight from construction accounting software so job cost and billing come from the same records. What matters most is that the schedule ties to the ledger and the cost-to-complete estimates are honest. For training, the Construction Financial Management Association (CFMA) offers WIP courses and publishes articles on WIP analysis in its Building Profits magazine.

For the other numbers that go in the same surety package, see the 5 financial metrics every contractor should track. Start each job's WIP from the same numbers you bid by building your budgets in the cost estimator.

Frequently Asked Questions

What is a WIP report in construction?

A work-in-progress report lists every open contract and compares contract value, costs to date, estimated total cost and billings to date. From those it calculates percent complete, earned revenue and gross profit, and whether each job is over- or under-billed. It's the main tool for managing jobs under percentage-of-completion accounting and a standard part of a surety's financial review.

How often should I update my WIP?

Often enough to catch a problem while you can still fix it. There is no single required frequency for every contractor, and sureties and lenders set their own reporting terms. Many contractors produce the WIP monthly and update cost-to-complete on large active jobs more often. Your surety will want it with year-end and interim statements.

How does ASC 606 affect WIP reporting?

Construction contracts commonly qualify for revenue recognition over time, and cost-to-cost is still widely used to measure progress. ASC 606 requires adjusting that measure for costs that don't reflect progress, such as uninstalled materials and inefficient costs like rework. On the balance sheet, over- and under-billings are presented as net contract liabilities and contract assets by contract, and conditional retainage is included in those balances.

What happens when a job is projected to lose money?

Under FASB ASC 605-35-25-46, which still applies to construction-type contracts, the entire projected loss is recognized in the period it becomes evident. It isn't spread over the rest of the job.

When can a contractor avoid percentage-of-completion for taxes?

Under IRC section 460(e), home construction contracts are exempt. Other construction contracts qualify only if the contractor estimates at the start that the job will be done within two years and meets the section 448(c) gross receipts test. For tax years beginning in 2026, that test is $32 million or less in average annual gross receipts over the prior three years, per IRS Revenue Procedure 2025-32. Confirm with your CPA.

Why does my surety want WIP schedules?

Underwriters use them to see which jobs are over- or under-billed, whether margins are fading, and whether your estimates hold up through completion. Sureties generally require percentage-of-completion financial statements with schedules of open and completed jobs that tie to the balance sheet and income statement, and most require at least a CPA-reviewed statement.


READ NEXT: The 5 Financial Metrics Every Contractor Should Track

MC

Mike Callahan

20-Year General Contractor

More from Mike Callahan→
attach_money

Track construction material prices & market data

BLS PPI pricing for lumber, steel, concrete, copper, and more — updated monthly.

Track prices free