ProBuildermuse Pro is live — Fire sale: Pro for $1.99/mo.Get Pro
Buildermuse
Commercial

Virginia Data Center Construction: 2.4 GW Underway in 2026

Lisa Chen·April 10, 2026·Updated October 18, 2026·11 min read

Share this with your estimator.

Virginia Data Center Construction: 2.4 GW Underway in 2026

The Largest Data Center Market in the World

Northern Virginia is the largest data center market in the world. Virginia's Joint Legislative Audit and Review Commission (JLARC) said so in its December 2024 report, Data Centers in Virginia, citing Cushman & Wakefield data: the Northern Virginia market accounts for 13 percent of all reported operational data center capacity globally and 25 percent of capacity in the Americas.

This article used to say the corridor held "25 million square feet." That number was too low. JLARC counted more than 63 million square feet of data center space across Virginia on about 7,200 acres, using roughly 5,050 MW of power, and found that 80 percent of the state's industry is concentrated in three Northern Virginia localities. The slug of this page still carries the old figure, but the numbers below are the sourced ones.

For contractors, the story in 2026 is that the market is still growing fast, it is almost fully leased, and power, not demand, sets the pace. Here is what the public data says, what it costs to build, and what the tax and power rules mean for bids.

For the general contractors behind most of these campuses, see our ranked list of the top 20 data center contractors.

How Much Is Being Built Right Now

CBRE's North American Data Center Trends H1 2026 report, released September 8, 2026, gives the cleanest current picture.

Metric (CBRE, H1 2026) Northern Virginia Eight primary North American markets
Inventory 4,496.5 MW not stated as a single figure in the release
Under construction 2,420.2 MW 7,481 MW
Vacancy 0.2% (down from 0.7% a year earlier) 1.4%
Net absorption, H1 2026 467.6 MW 1,456 MW

Three things in that table matter to builders. First, Northern Virginia alone has about a third of all the capacity under construction in CBRE's primary markets. Second, 0.2% vacancy means there is effectively nothing to lease, so any power-ready building gets taken. CBRE says more than 80% of all capacity under construction across its primary markets is already preleased. Third, CBRE notes that power constraints are stretching completion timelines even as more projects move from planning into construction. That shows up in the field as shells that finish ahead of their utility energization date.

CBRE's figures are in megawatts of capacity, not square feet. Floor area is a poor measure for data centers because power density per square foot keeps rising. If someone quotes you a Northern Virginia market size in square feet, ask what year and what source.

Where the Work Is: Loudoun and Prince William

JLARC found that 80 percent of Virginia's data center industry sits in three Northern Virginia localities: Loudoun, Prince William, and Fairfax. Loudoun alone accounts for roughly half of the state's industry by number of sites, building square footage, and estimated energy use.

Loudoun County

Loudoun, home of the Ashburn cluster usually called Data Center Alley, is the most mature market. The tax stakes there are large. JLARC's report summary, as presented by Prince William County's Office of Sustainability in December 2024, puts Loudoun's data center tax revenue at $733 million, or 31 percent of total local revenue. JLARC said that across the five localities with mature markets, data center revenue ranged from less than 1 percent to 31 percent of local revenue.

That revenue is why Loudoun keeps approving data centers. It is also why local politics around noise, transmission lines, and land use gets so heated. JLARC documented resident noise complaints near data centers in both Loudoun and Prince William and recommended that localities write data center noise rules into zoning ordinances rather than relying on general noise ordinances, which typically carry a maximum civil penalty of $500.

An earlier version of this article cited a "2025 Loudoun noise ordinance adding $2 million to $5 million per project." We could not find a source for that figure, so it has been removed. If you are bidding in Loudoun, read the actual zoning conditions on the specific rezoning or special exception. Screening, setbacks, and acoustic requirements are written project by project.

Prince William County

Prince William is the main expansion market. JLARC's summary puts Prince William's data center tax revenue at $110 million, or 7 percent of local revenue. That share is far smaller than Loudoun's, which tells you the county's market is younger.

Earlier versions of this article gave megawatt, square footage, and worker counts for specific QTS and Amazon campuses in Prince William. We could not verify those figures against the companies or the county, so they have been removed. Check the county's planning records for the rezoning on any specific campus you are pursuing.

Power: The Constraint That Sets the Schedule

Dominion Energy serves most of Northern Virginia's data center load. Reporting on Dominion's second-quarter 2026 update, MarketScale wrote on August 9, 2026 that the utility had contracted about 53.8 gigawatts of data center capacity as of July 2026, up 5.3 GW since December. "Contracted" here covers several stages of agreements, from engineering studies through signed electric service agreements, so it is not the same as load that will be energized soon.

Earlier versions of this article claimed a "40 gigawatt interconnection queue" against "30 gigawatts of generating capacity" and a "3 to 7 year" lead time for transmission upgrades. We could not source those numbers and have removed them. The one figure on timing we can source is broader: JLL's 2026 Global Data Center Outlook (January 5, 2026) says the average wait for a grid connection in primary data center markets now exceeds four years.

JLARC's 2024 report spells out why. It modeled two demand scenarios and found that even meeting half of unconstrained demand would be difficult. Without Virginia Clean Economy Act requirements, that scenario would need about one large 1,500 MW natural gas plant every two years for 15 consecutive years, matching the busiest building period of the past decade (2012 to 2018). For contractors, that cuts two ways:

  • Data center starts in Northern Virginia are gated by power, so projects can sit after site work while energization dates are confirmed.
  • The utility side is a large construction market of its own: substations, transmission lines, and generation. That work runs through Dominion and the State Corporation Commission, not through the data center owner.

For more on how power is changing where and how data centers get built, see our analysis of data center power demand.

Taxes: The Exemption, and the New Consumption Tax

Virginia's data center sales and use tax exemption is the biggest economic development incentive the state runs. JLARC found that it provided $928.6 million in tax savings in fiscal 2023 and is used by about 90 percent of the industry measured by megawatts.

The qualification thresholds, per JLARC and Holland & Knight's August 20, 2026 summary of the 2026 legislation:

  • At least $150 million in new capital investment
  • At least 50 new jobs paying at least 150 percent of the locality's prevailing average wage (lower thresholds apply in certain distressed localities)
  • A memorandum of understanding with the Virginia Economic Development Partnership
  • The exemption runs through June 30, 2035, with possible extensions to 2040 and 2050 for operators meeting larger thresholds

The 2026 General Assembly kept the exemption but added a new tax on electricity consumed by data centers. Holland & Knight reports that it is $0.011 per kilowatt-hour, effective July 1, 2026 through June 30, 2028, with annual collections capped at $600 million. The Joint Subcommittee on Tax Policy is studying the exemption, with recommendations due by December 15, 2026.

The exemption applies to qualifying computer equipment bought by the data center operator and its tenants. Contractors should not assume their own material purchases are tax-exempt. Confirm with the owner what its agreement covers before you price sales tax. Our state data center incentives guide compares Virginia with other states.

Construction Costs and Labor

Earlier versions of this article listed Virginia land prices per acre, shell and MEP costs per square foot, and an all-in "$8 to $12 million per MW." None of those ranges were sourced, so they are gone. Here are benchmarks you can cite:

  • Gordian's RSMeans data, as reported by Building Design+Construction on April 24, 2026, puts a one-story data center building at a $505 per square foot national average in Q1 2026, ranging from $398 in Austin to $688 in Palo Alto.
  • JLL's 2026 Global Data Center Outlook forecasts the 2026 global average shell-and-core cost at $11.3 million per MW. JLL adds that the tenant's tech fit-out can cost as much as $25 million per MW for AI infrastructure.

Our data center construction cost per square foot and per MW guide explains how to use both.

On labor, JLARC reported that a data center building usually takes 12 to 18 months to build, a full campus can take five or more years, and about 1,500 workers are on site at the height of construction. JLARC estimated the industry supports 74,000 jobs, $5.5 billion in labor income, and $9.1 billion in GDP in Virginia each year, mostly from construction rather than operations. Bureau of Labor Statistics wage data for May 2025 puts Virginia's median electrician wage at $30.24 an hour, close to the national median of $30.38. Statewide medians understate what data center crews earn in Northern Virginia, where the work competes for every journeyman available. Our guide to data center trades in demand covers which crafts are tightest.

What Comes Next

The sourced facts point to three things for contractors.

Northern Virginia will stay the biggest single market. CBRE has 2,420 MW under construction there and vacancy at 0.2%. Demand is not the problem.

Power decides who builds when. With Dominion reporting about 53.8 GW of contracted data center capacity and JLL putting average primary-market grid waits above four years, the projects that move are the ones with confirmed energization dates. Ask for that date before you commit estimating resources.

The policy ground is shifting. A new consumption tax took effect July 1, 2026, and a legislative study of the exemption reports by December 15, 2026. Neither stops construction, but both are worth watching if you are bidding work that will deliver in 2028 or later.

For a look at where else data center work is going, see our coverage of Midwest data center construction.

FAQ

How big is Virginia's data center market?

JLARC counted more than 63 million square feet of data center space in Virginia on about 7,200 acres, using roughly 5,050 MW, in its December 2024 report. CBRE puts Northern Virginia's inventory at 4,496.5 MW in H1 2026, with 2,420.2 MW under construction and 0.2% vacancy.

Is Northern Virginia really the largest data center market in the world?

Yes. JLARC, citing Cushman & Wakefield, reported that Northern Virginia accounts for 13 percent of all reported operational data center capacity globally and 25 percent in the Americas.

How much power has Dominion contracted for data centers?

About 53.8 GW as of July 2026, per MarketScale's report on Dominion's Q2 2026 update. That figure spans several contract stages and is not all near-term load. JLL says average grid connection waits in primary data center markets exceed four years.

What does Virginia's data center tax exemption require?

At least $150 million in new capital investment and at least 50 new jobs paying 150 percent of the local prevailing average wage, plus an MOU with the Virginia Economic Development Partnership. It runs through June 30, 2035. JLARC found it saved the industry $928.6 million in fiscal 2023.

What is Virginia's new data center electricity tax?

$0.011 per kWh of electricity consumed, effective July 1, 2026 through June 30, 2028, capped at $600 million a year in collections, according to Holland & Knight's August 2026 summary.

How long does a Virginia data center building take to build?

JLARC reported about 12 to 18 months per building, with full campuses taking five or more years and about 1,500 workers on site at peak.


READ NEXT: Data Center Power Demand Is Reshaping Construction

LC

Lisa Chen

PE/PMP Civil Engineer

More from Lisa Chen→
gavel

Find commercial construction bids in your state

Live federal solicitations from SAM.gov — filtered by state, value, and trade.

Browse open bids