On May 6, 2026, Eli Lilly opened Lilly Lebanon Advanced Therapies, its first dedicated genetic medicine manufacturing facility and the first of three planned sites on its Lebanon, Indiana campus. The same day, Lilly said it would invest another $4.5 billion across two of the three Lebanon sites, and put its Indiana capital expansion since 2020 at more than $21 billion (Lilly release, May 6, 2026).
That is the shape of this job: a newly opened pharmaceutical plant running inside a live construction site, with heavy work continuing on two other projects and the total commitment still climbing. If you want to understand how the biggest industrial buildout in Indiana is being delivered, the contract structure is where to look.
What is being built, and what it costs
Lilly's main Lebanon campus is about 600 acres east of I-65 and north of SR-52, planned to include administrative offices, lab space, manufacturing, utilities, warehousing and a fire station, according to the project's construction office site (lpgrowsboone.com). It anchors the state's LEAP Research and Innovation District; IBJ reported in April 2024 that Lebanon had annexed at least 7,200 acres and the Indiana Economic Development Corp. had identified about 11,000 acres in Boone County for the district.
Three projects are in play.
Lilly Lebanon API. The active pharmaceutical ingredient site, which Lilly says will be the largest API production site in U.S. history and is scheduled to open in 2027. The original commitment was $3.7 billion. In May 2024 Lilly added $5.3 billion for tirzepatide (Mounjaro and Zepbound) ingredient capacity, raising the site total to $9 billion (Powder & Bulk Solids, May 28, 2024). IBJ described the campus in April 2024 as at least 12 buildings totaling more than 1.6 million square feet, from a 3,200-square-foot visitors center up to a pair of three-story, 330,000-square-foot manufacturing facilities.
Lilly Lebanon Advanced Therapies. The genetic medicine plant, opened May 6, 2026. Messer Construction's project team refers to it as LP2.
Lilly Medicine Foundry. A $4.5 billion center for advanced manufacturing and drug development announced in October 2024, which BioPharma Dive reported took Lilly's LEAP total past $13 billion. IBJ reported in February 2025 that it covers 1.2 million square feet in seven buildings connected by a central corridor, on a 200-acre site at SR-32 and County Road 200 West. Ground was broken May 6, 2025, and it is scheduled to open in late 2027.
Add the May 2026 commitment and the announced total across the three Lebanon sites comes to roughly $18 billion ($9 billion + $4.5 billion + $4.5 billion). Lilly has not published how the 2026 money splits between the two sites.
The scale has grown each year. The API site alone went from $3.7 billion to $9 billion in about a year. The construction office now says the Lebanon project will create up to 900 Lilly roles and an estimated 5,000 construction jobs at peak, and WFYI reported the Medicine Foundry will add demand for more than 2,000 construction jobs and 400 permanent positions. Nothing about this campus has been trimmed.
EPCM is not CM at risk, and it changes your contract
Fluor Corporation is overseeing construction of the Lebanon API facility, per the project office. On April 2, 2025, Fluor announced a second multi-billion-dollar EPCM award in Lebanon, Indiana, from "one of the world's leading pharmaceutical makers," saying the facility "represents the largest investment in an active pharmaceutical ingredient facility in U.S. history" and that the work was in addition to a first multi-billion-dollar project awarded in 2023. Fluor did not name the client, but the location and description match Lilly's. Fluor described the contract as reimbursable and booked it in the first quarter of 2025.
"Reimbursable" carries most of the meaning. Under a typical EPCM structure:
- The EPCM firm acts as the owner's agent, not as the builder. It engineers the facility, procures equipment and materials, and manages construction, but it generally does not hold the trade contracts.
- The owner usually holds the trade contracts directly, and the EPCM firm coordinates them.
- The owner carries the cost risk. There is no guaranteed maximum price wrapping the trades, so cost growth in a package lands on the owner.
- The manager is paid on a reimbursable basis rather than a lump sum with contingency buried in it.
Compare that with the two structures most contractors know better. Under CM at risk, the construction manager converts to a GMP and takes cost exposure above it. Under design-build, one entity carries design and construction liability against a fixed price.
Owners choose EPCM when scope is going to move. On a regulated pharmaceutical facility, it usually does, because process design keeps evolving through construction and regulatory expectations can shift late. The owner is buying flexibility and paying for it by keeping the risk.
For a trade contractor, that is a different job. You may be contracting with the owner rather than a GC, directed by a manager who is not your contractual counterparty, with change management running through a reimbursable process that documents everything. Fee and general conditions behave differently on a reimbursable rate schedule than on a lump sum, so run the numbers with a markup and margin calculator before you agree to rates rather than a price.
The Advanced Therapies plant had a different team. Messer Construction's self-perform crews placed its main foundation (details below). Lilly has not publicly named a construction manager for the Medicine Foundry.
The schedule is driven by qualification, not substantial completion
This is the biggest thing that separates GMP pharmaceutical construction from other verticals, and it catches contractors crossing over from commercial or conventional industrial work.
On a commercial building, you finish, you get a certificate of occupancy and the owner moves in. On a GMP facility, construction completion is only part of the way to a working plant. Systems then go through commissioning and qualification, typically installation qualification, operational qualification and performance qualification. Process welds are documented, stainless lines are cleaned, passivated and tested, cleanroom penetrations are verified, and utility systems have to show they perform within specification before commercial batches can be made.
Practical consequences for the trades:
- Documentation is a deliverable. Weld maps, material traceability certificates and test records are contract deliverables, and missing paperwork stops qualification just like missing work.
- Rework carries a qualification penalty. Cutting into a qualified system to fix something can mean requalifying it.
- Your float is not where you think. Trades that finish on time but hand over incomplete turnover packages hold up the qualification sequence.
Firms without process-piping and cleanroom experience tend to underbid this documentation load. It is a real cost and belongs in your number.
What one mat slab looks like at this scale
The clearest public picture of the physical work came from the LP2 foundation. Messer reported on December 11, 2023 that in late October its team placed a monolithic mat slab for the pharmaceutical manufacturing building: 5,548 cubic yards of concrete, about 24 million pounds, poured continuously over 13 hours by two shifts of self-perform crews with zero injuries. It took 584 truckloads from five batch plants, roughly 44 trucks an hour, on top of 1,070 tons of rebar. The team tracked truck arrivals and pump turnaround with an app and brought in a third-party mass concrete specialist to monitor and control internal temperatures.
That is one slab on one building, on a campus with at least a dozen buildings and a seven-building complex going up nearby. Scale the batch-plant demand, haul-route load and aggregate consumption accordingly and you see why regional material logistics is a constraint on a job like this. Ready-mix prices have been relatively calm lately: the BLS producer price index for ready-mixed concrete (WPU1333) was up 2.3% year over year in September 2026, while the rebar index (WPU1074051) was up 30.0%. Contractors sizing similar work can benchmark against our construction cost data.
4,500 craft workers in Boone County
The project office says that at peak, some 4,500 craft workers will be on the API site, and the wider Lebanon project estimates 5,000 construction jobs at peak. The Medicine Foundry adds demand for more than 2,000 more.
Boone County did not have thousands of idle pipefitters, electricians and millwrights waiting. Those workers travel in, and the wage and per-diem pressure spreads into the Indianapolis metro, where other commercial and industrial contractors compete for the same trades. Indiana's other megaprojects, including the data center campuses covered in our Midwest data center piece, draw on the same pool. Nationally the market is tight too: BLS JOLTS counted 251,000 construction job openings in August 2026, and ABC estimates the industry needs about 349,000 additional workers in 2026; our labor shortage coverage tracks those numbers. If you are bidding unrelated work within an hour of Lebanon over the next two years, that pressure is in your labor number whether you priced it or not. Regional demand trends are on the state construction dashboards.
What is still ahead
The API site opens in 2027 and the Medicine Foundry is scheduled for late 2027, so both are in the phase where mechanical, electrical, process piping, controls and cleanroom fit-out drive the manpower curve and qualification work starts overlapping construction.
Two things to watch. First, whether Lilly commits again. It has raised this campus several times, most recently by $4.5 billion in May 2026, and each increase extends the craft draw. Second, how staggered turnover holds up. Running a genetic medicine plant beside active heavy construction constrains the remaining work: dust control, vibration, utility tie-ins, road closures and crane picks all have to respect a facility that is now making product. That interface can quietly cost weeks, which is why turnover sequencing on a campus like this gets planned years out.
FAQ
How much is Eli Lilly investing in Lebanon, Indiana?
Roughly $18 billion in announced commitments: $9 billion for the Lebanon API site (raised from $3.7 billion in May 2024), $4.5 billion for the Lilly Medicine Foundry, and another $4.5 billion announced May 6, 2026 across two of the three Lebanon sites. Lilly says its Indiana capital expansion since 2020 exceeds $21 billion.
Who is building the Lilly Lebanon API plant?
Fluor oversees construction of the API facility under an engineering, procurement and construction management model. Fluor's April 2025 announcement described its second Lebanon EPCM award as a reimbursable, multi-billion-dollar contract.
Who built Lilly Lebanon Advanced Therapies?
Messer Construction's self-perform crews placed the building's 5,548-cubic-yard mat foundation in October 2023. The plant opened May 6, 2026.
How many construction workers are on the Lilly LEAP project?
The project office says some 4,500 craft workers will be on the API site at peak, with about 5,000 construction jobs across the Lebanon project. The Medicine Foundry is expected to create demand for more than 2,000 more.
When will the Lilly Lebanon sites open?
Advanced Therapies opened May 6, 2026. The Lebanon API site is scheduled to open in 2027, and the Lilly Medicine Foundry is scheduled for late 2027.
What is EPCM and how does it differ from CM at risk?
Under EPCM, the manager engineers, procures and manages construction on a reimbursable basis while the owner typically holds the trade contracts and keeps the cost risk. Under CM at risk, the construction manager commits to a guaranteed maximum price and carries cost exposure above it.



