Construction profit margins leave little room for surprises. The Construction Financial Management Association's 2025 Financial Benchmarker, summarized by ENR on September 29, 2025, reported a pre-tax net income margin of 6.7% for the typical responding contractor in fiscal 2024. The same summary put the typical current ratio at 1.7 and days of cash at 27. A firm running on those numbers has about a month of cash and keeps less than seven cents of each revenue dollar. One bad job, one slow-paying owner, or a few months of creeping overhead can erase a year's profit.
The firms that avoid that don't wait for the year-end financial statements to find out how they did. They look at a short list of numbers every week. This article covers five of them: cash position and a 13-week forecast, work-in-progress (WIP) and profit fade, overhead rate, backlog and pipeline, and receivables aging. Each one includes the formula, how to track it, and what to do when it moves the wrong way.
Metric 1: Cash Position and a 13-Week Cash Forecast
What it is
Cash position is the money in your bank accounts plus unused credit available on your line. A 13-week cash forecast projects that number forward a quarter, week by week, using expected collections and expected payments.
Why it matters
A contractor can be profitable on paper and still run out of cash. Receivables come in slowly, payroll goes out every week, and material and equipment purchases often come before you can bill for them. A rolling forecast shows a shortfall weeks before it reaches the bank account, while there is still time to act.
How to track it
Update a simple spreadsheet each week with:
- Current bank balances and available credit
- Expected collections by week, based on open invoices and each customer's actual payment history
- Expected payments by week: payroll, suppliers, subcontractors, equipment, taxes, insurance, rent and debt service
- Net cash flow and projected ending balance for each week
Here is a hypothetical example:
| Week | Collections | Payments | Net flow | Projected balance |
|---|---|---|---|---|
| Start | $170,000 | |||
| 1 | $85,000 | $112,000 | ($27,000) | $143,000 |
| 2 | $120,000 | $98,000 | $22,000 | $165,000 |
| 3 | $45,000 | $105,000 | ($60,000) | $105,000 |
| 4 | $180,000 | $115,000 | $65,000 | $170,000 |
Week 3 shows a $60,000 drop. Seen two weeks ahead, it can be handled by pushing a collection, timing a supplier payment, or drawing on the line deliberately rather than in a panic. The cash flow projector can help you build the first version.
The forecast is only as good as its collection assumptions. Use the dates customers actually pay, not the dates in the contract.
Metric 2: Work in Progress and Profit Fade
What it is
The WIP report shows each active job's contract value (including approved changes), costs to date, estimated cost to complete, and projected profit or loss.
Why it matters
It answers the most important question in contracting: is each job making money? A job that is losing money needs to be caught while there is still work left to fix it.
How to track it
Projected profit = Revised contract value − (Costs to date + Estimated cost to complete)
The estimated cost to complete is where WIP reports go wrong. It is not the original budget minus what has been spent. It is a fresh estimate of what the remaining work will actually cost, based on current production rates, prices, and schedule. Have the project manager build it from the field each time.
Watch for fade
Fade is the drop in projected profit from the original estimate. If a job was bid at $50,000 of profit and now projects $38,000, that is $12,000 of fade, a 24% reduction. Common causes:
- Labor productivity below estimate. Track labor hours against budget by cost code, not just dollars.
- Material price changes. Prices can move between bid and purchase. See our article on material costs and margins for current producer price trends.
- Unbilled or unapproved change orders. Extra work performed but not yet approved is cost without revenue.
- Subcontractor overruns that you can't pass through.
Set a fade threshold that triggers a review, and require the project manager to explain the cause and present a recovery plan. The job cost tracker is a simple way to start tracking costs against budget.
Underbillings and overbillings
The WIP schedule also shows whether you have billed ahead of or behind the work. Billing behind the work (underbillings) means you have financed the owner's project with your own cash, and sureties and lenders look at large underbillings as a warning sign. Billing ahead (overbillings) is cash you owe in future work, not profit.
Metric 3: Overhead Rate
What it is
Overhead rate is home office overhead as a percentage of revenue or of direct cost. Overhead includes office staff, rent, vehicles not charged to jobs, insurance not charged to jobs, software, professional fees, marketing and owner compensation that isn't charged to jobs.
Why it matters
Overhead creeps: a new truck, another office hire, a software subscription nobody cancelled. If revenue doesn't grow with it, the overhead rate rises and every job has to carry more of it.
How to track it
Overhead rate = Trailing 12-month overhead ÷ Trailing 12-month revenue (or direct cost)
Using a trailing 12 months smooths out seasonal swings. Pick one basis, revenue or direct cost, and stay with it. If you build your markup from overhead as a percentage of direct cost, track it that way. Our overhead and markup guide shows how the rate turns into a markup.
Benchmarks for overhead rates are hard to compare across firms because companies classify project managers, superintendents and vehicles differently. Your own trend matters more than a published average. If the rate rises for several months in a row, find out why before it shows up in the year-end numbers.
The quarterly overhead review
Every quarter, go through each overhead line and ask whether you would spend that money if you were starting today. Cut or renegotiate what doesn't pass.
Metric 4: Backlog and Pipeline
What it is
Backlog is the value of signed contracts not yet earned. Pipeline is the value of bids outstanding and opportunities you are pursuing.
Why it matters
Backlog tells you how busy you will be. Pipeline tells you whether enough work is coming to replace it. Because estimating and sales take months to turn into revenue, a backlog problem has to be spotted early.
How to track it
- Backlog: sum of remaining contract value on signed work
- Months of backlog: backlog ÷ average monthly revenue
- Pipeline: value of outstanding bids and tracked opportunities
- Win rate: contracts won ÷ bids submitted over the trailing 12 months, by count and by value
- Expected awards: pipeline × win rate
A hypothetical example: monthly revenue of $500,000 and backlog of $4.5 million is 9 months of work. A pipeline of $8 million at a 25% win rate suggests about $2 million of future awards, or 4 more months. Total forward visibility is roughly 13 months.
Set minimums for both numbers that fit your business, and increase bidding activity as soon as either drops below them. Also track win rate by project type, size and customer. The pattern usually shows where your estimating time pays off and where it doesn't. The bid/no-bid scorecard can help you make those calls consistently.
Backlog quality
Not all backlog is equal. A large backlog of low-margin work can be worse than a smaller one at healthy margins. Track the expected gross profit in backlog, not just the revenue.
Metric 5: Accounts Receivable Aging
What it is
The AR aging report groups unpaid invoices by age: current, 31 to 60 days, 61 to 90 days, and over 90 days. Track retainage receivable separately, since it follows different timing.
Why it matters
Aging is an early warning for cash trouble. When more of your receivables move into the older buckets, cash pressure follows. The older an invoice gets, the harder it is to collect, and lien and bond claim deadlines keep running while you wait.
How to track it
Review the aging report weekly and focus on:
- Days sales outstanding (DSO): receivables ÷ annual revenue × 365. Track it by customer, not just company-wide.
- Share of receivables over 60 days. If it keeps rising, you have a collection process problem.
- Specific accounts that need action. An invoice approaching 60 days deserves a phone call. Anything older needs a written demand and a check of your lien or bond claim deadlines; our mechanics lien guide explains how those deadlines work in Texas, California and Florida.
For context on how long contractors typically wait and what statutes require, see our article on construction payment terms. The aging receivables tool can organize your open invoices by bucket.
Setting Up the Weekly Review
A weekly review doesn't need to be long or formal. Pick a fixed time early in the week, pull the numbers from your accounting and job cost system, update the cash forecast, and look at the five metrics in order. Bring anything that needs action to your project managers' meeting.
You don't need expensive software:
- Cash forecast: a spreadsheet
- WIP report: most construction accounting systems produce one; otherwise, a spreadsheet tied to job cost reports
- Overhead rate: a calculation from the income statement
- Backlog and pipeline: a spreadsheet or CRM
- AR aging: a standard report in any accounting software
How the Metrics Connect
The five numbers affect each other:
- Slower collections reduce cash and push you onto the credit line.
- Fade on active jobs means less profit flowing into future cash.
- Rising overhead eats the gross profit your jobs produce.
- Shrinking backlog means less revenue to absorb fixed overhead, which raises the overhead rate.
- Tight cash limits the work you can take on, which shrinks the pipeline.
One number moving the wrong way is something to watch. Two or more moving together means it's time to act.
Frequently Asked Questions
How accurate does a 13-week cash forecast need to be?
It needs to be directionally right: which weeks are short and roughly by how much. Near-term weeks will be more accurate than later ones. Update it weekly with actual results and roll it forward one week each time.
What should I do if the WIP report shows a job losing money?
First confirm the data: costs coded correctly and an honest estimate to complete. If the loss is real, find the cause and decide what can be recovered through change orders, crew changes or scope negotiation. Book the expected loss in your WIP rather than hiding it; late recognition only reduces your options.
Should I hire a controller or CFO?
That depends on your size, complexity and how much time the owner can spend on finance. Whatever you decide, the owner should still review the weekly metrics personally. Delegating the numbers entirely is how problems go unnoticed until year end.
Where can I find industry benchmarks?
CFMA's annual Financial Benchmarker is the main source for contractor financial ratios. Its 2025 edition, summarized by ENR in September 2025, reported a 6.7% typical pre-tax net income margin, a 1.7 current ratio and 27 days of cash for fiscal 2024; the paid version allows filtering by contractor type, region and revenue size. A CPA who specializes in construction can also compare you with similar clients. See our construction profit margins benchmark for more detail.
Bottom Line
With typical pre-tax margins around 6.7% and about a month of cash on hand, contractors can't afford to learn about problems at year end. Five numbers reviewed weekly cover most of what matters: whether you can make payroll, whether your jobs are making money, whether overhead is under control, whether enough work is coming, and whether customers are paying on time.



