Carpenters working in residential building construction earned a mean of $30.71 an hour and a median of $29.13 an hour as of May 2025, according to the Bureau of Labor Statistics Occupational Employment and Wage Statistics (OEWS) program. That is the closest federal figure to a residential framing labor rate, and it is an employee wage. A framing subcontractor's price also covers taxes, insurance, workers' comp, overhead and profit.
No public source publishes a national per-square-foot rate for residential framing labor. Framing subs set that price market by market, and the only reliable way to get it is to collect local bids on your own plans.
Across all industries, the 670,090 carpenters BLS counted earned a mean of $31.55 an hour ($65,630 a year) and a median of $29.12. The rest of this page covers what the public data does show: the size of the framing package in a new house, carpenter wages state by state, what is pushing on the price, and how to manage it.
What NAHB's framing cost includes
In the National Association of Home Builders' 2024 Cost of Constructing a Home survey (conducted fall 2024, report dated January 20, 2025), framing averaged $70,982 per home, or 16.6% of total construction cost. That figure covers framing including the roof ($49,763), trusses ($12,903), sheathing ($6,513), general metal and steel ($1,718) and other items ($85). NAHB's own methodology notes that each category includes labor paid directly by the builder, subcontractor costs and materials, so it is a framing package number, not a labor-only number.
The NAHB survey home averaged 2,647 square feet of finished area and a $665,298 sales price. That puts the full framing package (labor and materials combined) at about $26.82 per finished square foot by simple division of NAHB's two published numbers. That is not a labor rate, and NAHB cautions that its sample is national and too small for a geographic breakdown.
Framing is the third-largest construction stage in NAHB's 2024 Cost of Constructing a Home survey, not the largest. Interior finishes (24.1%) and major system rough-ins (19.2%) were larger shares. Framing's share has moved around: 17.4% in 2019, 20.5% in 2022 and 16.6% in 2024.
Carpenter wages by state, BLS May 2025
Framing labor is one of the most regionalized costs in residential construction. A framing crew in Houston works in a fundamentally different labor market than a crew in Boston, not because the work is different, but because cost of living, union density and the depth of the local workforce vary from market to market. A national average will sit too high for some markets and too low for others.
The figures below are BLS OEWS May 2025 mean hourly wages for carpenters (occupation code 47-2031) across all industries in each state, pulled from the BLS public data API on October 18, 2026. They are wages paid to employees, not what a framing subcontractor charges a builder, which also has to cover payroll taxes, workers' compensation, insurance, equipment, overhead and profit. Use them to compare markets, not as a bid price.
| State | Mean hourly wage | Carpenter employment |
|---|---|---|
| Illinois | $38.62 | 19,570 |
| Massachusetts | $38.31 | 18,540 |
| Washington | $38.06 | 26,960 |
| California | $37.89 | 100,750 |
| New York | $36.52 | 40,630 |
| Oregon | $34.08 | 15,110 |
| Minnesota | $33.81 | 14,930 |
| Maryland | $33.19 | 9,770 |
| Colorado | $31.82 | 12,740 |
| District of Columbia | $31.73 | 1,540 |
| Indiana | $31.22 | 15,240 |
| Pennsylvania | $30.39 | 30,630 |
| Ohio | $30.09 | 18,450 |
| Arizona | $28.36 | 16,230 |
| Idaho | $26.96 | 8,380 |
| Virginia | $26.63 | 20,460 |
| Utah | $26.62 | 15,220 |
| Tennessee | $25.96 | 8,200 |
| Florida | $25.27 | 39,300 |
| Texas | $24.51 | 33,540 |
| North Carolina | $24.28 | 13,480 |
| Georgia | $24.18 | 9,190 |
Source: BLS OEWS, May 2025 estimates. National mean for comparison: $31.55.
Among the 22 jurisdictions in the table, mean carpenter wages range from $24.18 an hour in Georgia to $38.62 in Illinois, a spread of $14.44 an hour.
Both Pacific Northwest states in the table are above the national mean. Washington carpenters averaged $38.06 an hour in May 2025, third-highest of the states in this table, and Oregon averaged $34.08. Washington's 26,960 carpenters make it the sixth-largest workforce in this table, behind California, New York, Florida, Texas and Pennsylvania.
California has by far the largest carpenter workforce in the country among these states, 100,750 jobs, with a mean wage of $37.89. Seismic framing details (hold-downs, shear wall nailing schedules, straps) add complexity and inspection steps compared with wind-only framing in many inland markets, and that shows up in crew time, but the wage data alone puts California in the top tier rather than at the very top.
The Mountain West splits. Colorado's mean wage was $31.82, right around the national figure, while Arizona ($28.36), Idaho ($26.96) and Utah ($26.62) sit below it. A statewide mean blends the Denver metro with rural counties, so local bids on your own plans matter more than the state figure.
The Southeast remains one of the lower-wage carpenter markets. Georgia ($24.18), North Carolina ($24.28), Florida ($25.27), Tennessee ($25.96) and Virginia ($26.63) all came in below the national mean. Florida has the third-largest carpenter workforce in this table at 39,300. Coastal Florida work carries additional framing requirements for high-wind zones (more connectors, tighter nailing, and in the High-Velocity Hurricane Zone counties, extra product approval rules), which affects crew time even where hourly wages are moderate.
Texas carpenters averaged $24.51 an hour in May 2025, $13.38 below California and $13.55 below Washington. With 33,540 carpenters, Texas has a deep workforce, and the wage data supports its long-standing reputation as one of the more affordable major framing markets. No public source publishes framing subcontract pricing for Dallas-Fort Worth, Houston, Austin or San Antonio, so builders in those metros should benchmark against several local bids on the same plan.
The Midwest is not uniform. Illinois posted the highest mean carpenter wage in this table at $38.62, which tracks with the Chicago market's union presence. Minnesota ($33.81) is also above the national mean. Indiana ($31.22) and Ohio ($30.09) sit close to it. Minnesota's short building season concentrates framing demand into fewer months, which builders there should account for when scheduling.
Northeast and Mid-Atlantic states cover a wide range. Massachusetts ($38.31) and New York ($36.52) are both well above the national mean. Pennsylvania ($30.39) is slightly below it, while Maryland ($33.19) and the District of Columbia ($31.73) are near or above it. Statewide figures blend the Boston and New York metros with lower-cost areas, and tight urban lots and staging limits can add crew time that no wage table captures.
Comparing framing bids on the same scope
Since local bids are the benchmark, make sure the bids you compare cover the same scope. Some crews quote by the square foot of living area. Others quote by the square foot of floor area including garages and covered porches. Still others quote by the board foot of lumber, and some quote a lump sum without saying how they got there.
Always clarify what's included: walls, trusses, sheathing and hardware, or walls and trusses only with sheathing as a separate line? Specialty framing like coffered ceilings, arched openings and complex roof geometry is often priced separately.
What pushes residential framing labor rates up
No public series tracks year-over-year changes in what framing subcontractors charge. On the cost side, NAHB's survey shows framing's share of construction cost fell from 20.5% in 2022 to 16.6% in 2024. On the wage side, you can compare the BLS OEWS May 2025 figures above with the May 2024 release on bls.gov for your state. Beyond that, the best we can do is describe the forces pushing on the price and put numbers on them where the data allows.
Workforce supply comes first. Framing is physically demanding work, and builders across the country report difficulty filling crews. What BLS does show is where carpenters work: as of May 2025, 204,290 carpenters were employed in residential building construction, 108,660 in nonresidential building construction and 228,220 across specialty trade contractors.
Other sectors compete for the same workers. Commercial construction, industrial work and infrastructure spending all draw on them. The BLS data puts a number on the pull: carpenters in nonresidential building construction averaged $34.42 an hour in May 2025, compared with $30.71 in residential building construction, a gap of $3.71 an hour. Carpenters in heavy and civil engineering construction averaged $33.96. When a framer can earn more per hour on a commercial site, often with steadier hours, a residential builder has to compete on schedule, pay or both.
Cost of living matters too. Framing crews need to live somewhere, and in markets where housing costs have climbed, wage expectations follow. When builders compare markets, the wage table above is only part of the picture; what a crew needs to earn to live near the work counts as well.
Framing carries some of the highest workers' comp rates in residential construction because of fall and struck-by exposure. Rates are set by state (through NCCI or independent state bureaus) and by carrier, so they vary widely. Check your state's current carpentry classification rates with your agent, and ask framing subs for their experience modifier, since a sub with a poor safety record carries a higher comp cost into every bid.
OSHA fall protection rules for residential construction, safety training and documentation all add cost to framing operations. These are good things, because framing is dangerous work and those rules save lives. But they add cost, and that cost gets passed through in the subcontract price. For a look at the human toll this trade carries, see our coverage of construction suicide rates.
Panel plants, layout robots and BIM
Framing technology is evolving in ways that could affect labor costs over the next decade.
Truss plants have used computer-driven saws and assembly tables for years, and automated wall panel lines are spreading into off-site framing shops. These systems live in factories, not on the jobsite, and are best suited to high-volume work. How much they will reduce the labor component of framing at scale is not yet established by public data.
Layout is moving to digital tools as well. Dusty Robotics' FieldPrinter prints the layout from the digital building model directly onto the slab or deck, replacing manual measurement and chalk lines. The company's website, checked October 18, 2026, advertises "10x faster layout" and says one person can lay out 10,000 to 15,000 square feet per day. Those are manufacturer claims, not independent measurements. The company lists multifamily residential among its project types.
Wall panels and truss packages can also be generated from the building model, with cut lists, fastener schedules and assembly instructions produced by software. These BIM-to-fabrication workflows are already standard in the truss industry and are expanding into wall panel and floor system fabrication.
None of these technologies will replace skilled framers in the near term. But they will gradually shift the skill mix toward technology-assisted construction, which could moderate cost increases over time by letting each worker produce more per hour.
Managing framing costs without cutting quality
There are legitimate strategies for managing framing costs that don't involve squeezing your crews or cutting structural corners. Results depend on your plans, your crew and your market, so price each option on a real plan before you commit.
Advanced framing, also called optimum value engineering (OVE), reduces lumber use through techniques like 24-inch stud spacing where code allows, single top plates with connector plates, two-stud corners with drywall clips, right-sized headers, and eliminating unnecessary cripple studs and blocking. Fewer pieces means less material and fewer cuts and nails. The catch is that your framing crew needs to be trained in the approach, your plans need to be detailed enough to support it, and your building official needs to be on board. To see what a change in stud count does to the material bill, total the board feet for each layout in our lumber calculator.
Panelized wall systems move much of the framing labor off site. Prefabricated wall panels are built in a factory or covered yard and delivered to the site. They arrive squared and often sheathed, ready for installation by a smaller crew using a telehandler or crane. The trade-off is a higher material price (the panels include the fabricator's labor and markup) and the need for equipment access on site. For production builders with standardized plans, the schedule savings can make panelization pencil out. Run the numbers on your own plans before committing.
Plan design does some of the work before a crew shows up. Floor plans that minimize exterior corners, use standard lumber lengths, align load paths vertically and avoid complex roof geometries are less expensive to frame. A simple rectangular plan with a hip roof will frame faster than a complex plan with multiple bump-outs, bay windows and intersecting roof lines. Work with your designer to keep framing efficient without sacrificing curb appeal.
If you're starting multiple homes a year, negotiate a volume rate with your framing crew. The crew benefits from predictable, continuous work, and you benefit from a lower per-unit price. How large a discount you can get depends on your market and your volume; there's no reliable public benchmark for it.
Build relationships with your framing crews, not just your framing contractors. Know the lead carpenters by name. Understand their scheduling constraints. Pay them on time, every time. Provide clean, organized job sites with materials staged and ready. The framers who have a choice of which builders to work for will prioritize the builders who treat them well and make their job easier. We think being the builder of choice for the best framing crews in your market is worth more than most cost reduction strategies.
Compare pre-engineered roof trusses against stick framing on your own plans. NAHB's 2024 survey shows trusses averaging $12,903 per home when priced separately from framing, and truss share of construction cost rose from 2.1% in 2019 to 3.0% in 2024. Trusses are engineered and built to specification, so quality is consistent, and they typically install faster than stick-framed rafters. Get both prices for the same roof and compare the installed totals.