Every subcontractor knows the routine. You finish the work, submit the pay application, and wait. Meanwhile suppliers want to be paid on their terms, payroll goes out every week, and the line of credit charges interest on every dollar that bridges the gap.
How long the wait actually is depends on who is measuring. This article lays out what the published surveys say, what the law requires on federal and some state work, what slow payment costs a typical firm, and what you can do about it.
What the Data Says About Payment Delays
There is no government statistic for how long contractors wait to be paid. The available numbers come from industry surveys, mostly run by payment and billing software companies, and they measure different things.
Billd, 2025 National Subcontractor Market Report. Billd's fifth annual report surveyed more than 500 construction executives across 32 trades and all 50 states in the fourth quarter of 2024. Respondents reported waiting an average of 54 days after submitting a pay application, and 79% said they had paid for materials out of pocket before being paid.
Billd, 2026 National Subcontractor Market Report. As summarized by Built in an August 5, 2026 article, Billd's sixth annual report surveyed more than 600 construction industry respondents. Subcontractors reported an average of 51 days to get paid, while general contractors estimated that payment goes out in 35 days. That gap between how GCs and subs see the same process is itself a finding.
Siteline, The State of Subcontractor Billing in 2025. Siteline's report, announced August 12, 2025, said the average subcontractor waits 96 days to get paid, up from 90 days in 2019, and that only 5% of subcontractors consistently receive payment on time. Siteline's announcement does not describe its methodology or sample size.
The spread between 51 and 96 days is large, and these sources should not be blended into a single average. They likely measure different starting points, such as pay application submission versus the date work was performed, and different samples. What they agree on is that payment commonly takes well over a month, and that subs routinely finance materials and labor while they wait. Note that both companies sell payment or billing products.
One more factor sits outside these averages: retainage. Holding back a percentage of each payment until completion stretches the time to full payment far beyond the progress payment cycle. On federal construction, FAR 32.103 caps retainage at 10% of the approved estimated amount.
What the Law Requires
Payment deadlines are not just negotiated. Federal law and many state laws set them, at least for certain projects.
Federal construction: the Prompt Payment Act
On federal construction contracts, FAR 52.232-27, Prompt Payment for Construction Contracts (January 2017), implements the Prompt Payment Act (31 U.S.C. 3901 and following):
- Progress payments are due 14 days after the designated billing office receives a proper payment request (31 U.S.C. 3903(a)(6)).
- Final payment is due 30 days after the later of receipt of a proper invoice or government acceptance of the work.
- Improper invoices must be returned within 7 days of receipt.
- Subcontractor flow-down. Under 31 U.S.C. 3905(b), the prime must include a clause obligating it to pay subcontractors for satisfactory performance within 7 days of receiving payment from the agency, plus an interest penalty clause for late payment. Under 3905(c), subcontractors must flow the same clauses to their own subs and suppliers.
- Withholding from a sub is allowed only with written notice stating the amount, the specific causes and the remedial actions required, with a copy to the contracting officer.
Late payments by the government carry interest at the Treasury prompt payment rate. The Bureau of the Fiscal Service set that rate at 4.75% for July 1 through December 31, 2026. Under 3905(k), a prime's interest obligation to its subs is not an obligation of the United States, so subs collect from the prime, not the agency.
State prompt payment laws: two examples
States set their own rules for private and state-funded work. Two examples:
- Texas. Property Code Section 28.002 requires an owner to pay a contractor within 35 days after receiving a payment request, and the contractor to pay its subcontractor within 7 days after receiving the owner's payment. Section 28.004 sets interest on overdue amounts at 1.5% per month.
- California. Civil Code Section 8800 requires an owner on private work to pay undisputed progress payments within 30 days after notice demanding payment under the contract. The owner may withhold up to 150% of a disputed amount, and a wrongful withholding carries a penalty of 2% per month.
These statutes have exceptions and conditions that matter, including what counts as a proper request and when disputes justify withholding. Read your state's law and your contract together.
What Slow Payment Costs
Here is a hypothetical example to make the cost concrete. The interest rate is an assumption: the bank prime loan rate was 7.00% as of October 13, 2026 (Federal Reserve data via FRED), and many contractor credit lines are priced above prime, so this example uses 9%.
A subcontractor with $5 million in annual revenue and a 6% net margin earns $300,000 a year. Receivables outstanding are roughly annual revenue × days to collect ÷ 365.
| Days to collect | Average receivables | Annual carrying cost at 9% | Share of $300,000 profit |
|---|---|---|---|
| 35 | $479,452 | $43,151 | 14% |
| 54 | $739,726 | $66,575 | 22% |
| 96 | $1,315,068 | $118,356 | 39% |
Each day of collection time is worth about $1,233 a year for this firm ($5,000,000 ÷ 365 × 9%). Cutting collection from 54 days to 35 would save about $23,400 a year, money that would otherwise take roughly $390,000 of extra revenue at a 6% margin to earn.
The financing cost is only part of it. Slow pay ties up working capital that sureties and lenders look at, takes staff time to chase, and raises the chance of a bad debt.
Why Payment Takes So Long
Pay-when-paid chains. Subcontracts commonly tie the sub's payment to the GC's receipt of payment from the owner. Each tier adds its own processing time, so a delay at the top reaches every tier below it.
Approval and documentation. Pay applications pass through architects, owner's reps and lenders. Missing lien waivers, unsigned change orders and incorrect schedules of values all reset the clock.
Disputes used as leverage. When an owner or GC disputes one line, the whole payment sometimes waits. California's 150% withholding limit and the federal written-notice requirement both exist because of this practice.
Retainage. Holding back part of each payment until completion means the last dollars on a job are often the slowest to arrive.
How to Protect Your Cash
Negotiate terms before you sign
The contract is where you have the most leverage. Ask for a specific payment date after pay app submission, not just "per the prime contract." Push back on pay-if-paid language, ask for retainage to drop or be released when your scope is complete, and get the billing deadline and required backup in writing so you can't be rejected on a technicality.
Bill accurately and on time
Most delays start with a pay app that gets kicked back. Submit on the required date, with the required lien waivers and backup, and with change orders approved before you bill them.
Know your statutory rights
On federal work, you are entitled to the 7-day flow-down clause and interest on late payment from your prime. In states with prompt payment laws, cite the statute when payment is late. Interest provisions like Texas's 1.5% per month and California's 2% per month penalty give you something concrete to point to.
Protect lien and bond rights on every job
Serve preliminary notices on every private job, and calendar every lien and bond claim deadline the day you start work. Our mechanics lien guide covers the deadlines in Texas, California and Florida, and our construction bonding guide explains payment bond claims on public work.
Track collection time by customer
Calculate days to collect for each customer, not just your company average. Use the aging receivables tool to see who is slipping, and price slow payers accordingly, or stop bidding them.
Forecast cash weekly
A rolling 13-week cash forecast shows a shortfall weeks before it hits the bank account. The cash flow projector is a free starting point, and our article on the financial metrics every contractor should track explains how to use it with your receivables aging.
Frequently Asked Questions
How long do subcontractors wait to get paid?
It depends on the survey. Billd's 2025 report (surveyed in Q4 2024) found an average of 54 days after pay application submission; its 2026 report, as summarized by Built in August 2026, found 51 days. Siteline's 2025 report said 96 days, up from 90 in 2019. The surveys use different methods, so compare them with caution.
How fast must the federal government pay construction contractors?
Under FAR 52.232-27, progress payments are due 14 days after the billing office receives a proper request, and final payment 30 days after the later of a proper invoice or acceptance. Late payments earn interest at the Treasury prompt payment rate, 4.75% for July through December 2026.
How fast must a federal prime contractor pay its subs?
Within 7 days of receiving payment from the agency for the sub's satisfactory work, under the clause required by 31 U.S.C. 3905(b). Primes must also pay interest on late payments to subs, and must give written notice before withholding.
What is a reasonable payment term to accept?
Compare any proposed term to the statutory benchmark that applies to the project, such as 35 days owner-to-contractor and 7 days contractor-to-sub in Texas, or 14 days for federal progress payments. If you accept longer terms, price the carrying cost: at a 9% borrowing rate, every 30 days of extra wait on $200,000 costs about $1,480.
Should I stop work if I'm not being paid?
Only after checking your contract and your state's law with a construction attorney. Many contracts require written notice and a cure period first, and some state statutes give a right to suspend work for nonpayment while others don't. Stopping without a clear right can expose you to a termination claim.
Does retainage make payment terms worse?
Yes. Retainage holds back part of every payment until completion, so the full contract value is paid much later than progress payments. On federal construction, FAR 32.103 limits retainage to no more than 10% of the approved estimated amount.



